Highland Park Building 2- K25 Wing A Phase 2
by SIDDHI GAURAV ENTERPRISES · Kolshet, Thane 400607Also near Dhokali, Balkum, Majiwade
What’s in the report? →Possession date of Highland Park Building 2- K25 Wing A Phase 2 (MahaRERA P51700005485): 30 April 2027, moved from 30 December 2024 (24 months later). It has 186 homes, 91% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700005485, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700005485, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Highland Park Building 2- K25 Wing A Phase 2?
3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Highland Park Building 2- K25 Wing A Phase 2 has moved
30 December 2024
Completion date given when the project was registered
29 December 2025
Extended at the builder's request (MahaRERA application EXT51700024400)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 December 2026
Extended at the builder's request (MahaRERA application EA22122518915)
Reason the builder gave MahaRERA:
“The progress of the project slowed due to various reasons which overall impacted the timely completion of the Project, such as Covid 19 and contractor-related challenges, which affected the continuity of work. We faced operational setbacks…” Read the full reason
“The progress of the project slowed due to various reasons which overall impacted the timely completion of the Project, such as Covid 19 and contractor-related challenges, which affected the continuity of work. We faced operational setbacks due to labour shortages, and gaps in coordination among subcontractors. These issues affected adherence to planned schedules and slowed overall execution of the work. Throughout this period, we continued to prioritize the interests of our allottees. We assure you that the delays were never due to negligence but due to circumstances beyond our immediate co…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Highland Park Building 2- K25 Wing A Phase 2’s extension records on MahaRERA (P51700005485), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Highland Park Building 2- K25 Wing A Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- HIGHLAND PARK BUILDING 6 AND 7- K23 PHASE 1P51700006811 · possession 31 Dec 2019
- MahaRERA registration
- P51700005485
- Status
- Registered and active
- Builder
- SIDDHI GAURAV ENTERPRISES
- Location
- Kolshet, Thane · 400607
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 186
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Highland Park Building 2- K25 Wing A Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 2- K25- WING A | 100% | 100% | 95% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING 2- K25- WING A: covers 35 (Lower Podium + Upper Podium + Ground + 32 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Highland Park Building 2- K25 Wing A Phase 2 every 1–2 months.
Highland Park Building 2- K25 Wing A Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 2- K25- WING A (36 floors, 186 units)
- Land: 2,673 sq m (about 0.7 acres) · sanctioned built-up 3,812 sq m · recreational space 637 sq m
- Land, as filed: S. N. 87/2 AND 82/6
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Siddhi Real Estate Developers (a group of 5 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 6 finished, all within the promised date; 7 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 13 complaints on MahaRERA across 7 projects.
Read Google reviews of Highland Park Building 2- K25 Wing A Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Highland Park Building 2- K25 Wing A Phase 2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Highland Park Building 2- K25 Wing A Phase 2
What is the possession date of Highland Park Building 2- K25 Wing A Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Highland Park Building 2- K25 Wing A Phase 2 in Kolshet, Thane is 30 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Highland Park Building 2- K25 Wing A Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Highland Park Building 2- K25 Wing A Phase 2's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Highland Park Building 2- K25 Wing A Phase 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2026, giving the reason "The progress of the project slowed due to various reasons which overall impacted the timely completion of the Project, such as Covid 19 and contractor-related challenges, which affected the continuity of work. We faced operational setbacks due to labour shortages, and gaps in coordination among subcontractors. These issues affected adherence to planned schedules and slowed overall execution of the work. Throughout this period, we continued to prioritize the interests of our allottees. We assure you that the delays were never due to negligence but due to circumstances beyond our immediate co…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Highland Park Building 2- K25 Wing A Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Highland Park Building 2- K25 Wing A Phase 2 in Kolshet, Thane is P51700005485.
Is Highland Park Building 2- K25 Wing A Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 is registered as P51700005485 and its status is "Registered and active".
What is the current construction status of Highland Park Building 2- K25 Wing A Phase 2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING 2- K25- WING A is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Highland Park Building 2- K25 Wing A Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Highland Park Building 2- K25 Wing A Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 is registered on MahaRERA as P51700005485, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Highland Park Building 2- K25 Wing A Phase 2?
Highland Park Building 2- K25 Wing A Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Highland Park Building 2- K25 Wing A Phase 2?
For a flat in Highland Park Building 2- K25 Wing A Phase 2 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Highland Park Building 2- K25 Wing A Phase 2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Highland Park Building 2- K25 Wing A Phase 2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Highland Park Building 2- K25 Wing A Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Highland Park Building 2- K25 Wing A Phase 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: HIGHLAND PARK BUILDING 6 AND 7- K23 PHASE 1 (P51700006811, possession 31 Dec 2019). Check that your agreement names the registration of your own wing.
How can I get updates if Highland Park Building 2- K25 Wing A Phase 2's possession date changes?
The latest dates are on Highland Park Building 2- K25 Wing A Phase 2's MahaRERA page (P51700005485). GharKundli's Kundli Watch sends a free WhatsApp update on Highland Park Building 2- K25 Wing A Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Highland Park Building 2- K25 Wing A Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 has one building filed: BUILDING 2- K25- WING A with 36 floors and 186 units.
How big is the land of Highland Park Building 2- K25 Wing A Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 stands on 2,673 sq m of land (about 0.7 acres), with 3,812 sq m of sanctioned built-up area and 637 sq m of recreational open space.
What is the track record of Highland Park Building 2- K25 Wing A Phase 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Real Estate Developers (a group of 5 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 6 finished, all within the promised date; 7 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 13 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Highland Park Building 2- K25 Wing A Phase 2?
Google Maps has reviews of Highland Park Building 2- K25 Wing A Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Highland Park Building 2- K25 Wing A Phase 2?
Highland Park Building 2- K25 Wing A Phase 2 by SIDDHI GAURAV ENTERPRISES is in Kolshet, Thane, pincode 400607 (near Dhokali, Balkum, Majiwade), Maharashtra, and is registered on MahaRERA as P51700005485, per GharKundli's check of MahaRERA records. Its land is filed as S. N. 87/2 AND 82/6. GharKundli lists all 218 MahaRERA projects in Sandozbaugh (400607).
How many flats are in Highland Park Building 2- K25 Wing A Phase 2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 has 186 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was Highland Park Building 2- K25 Wing A Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Park Building 2- K25 Wing A Phase 2 was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Does Highland Park Building 2- K25 Wing A Phase 2 have any legal issues or court cases?
3 court cases are listed for Highland Park Building 2- K25 Wing A Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Highland Park Building 2- K25 Wing A Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHI GAURAV ENTERPRISES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Highland Park Building 2- K25 Wing A Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Sandozbaugh (400607)
- Marigold B wing
- Odysseus
- Lodha Amara Tower 47 and 48
- Lodha Amara Tower 44
- Regency Business Park Phase V
- Lodha Crown Kolshet - Tower 3
- Forestville - Phase 1
- The Helios
Other projects by SIDDHI GAURAV ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.