by Sagar Enterprise · Kavesar, ThaneAlso near Kasarvadavli, Anand Nagar

Possession: AROMA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700028361. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AROMA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AROMA has moved

  1. 30 September 2024

    Completion date given when the project was registered

  2. 30 November 2026

    Extended at the builder's request (MahaRERA application EA15072621758)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 30/10/2024 and we have also initiated the process for…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 30/10/2024 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, total parking, sanctioned number of floors and the number of floors for which CC has been issued. In view of this as the said project obtained full OC uploading consents from al…”

Source: AROMA’s extension records on MahaRERA (P51700028361), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AROMA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700028361
Status
Completed
Builder
Sagar Enterprise
Location
Kavesar, Thane · 400615
Project type
Others
Registered on
22 Feb 2021
Completion date at registration
September 2024
Latest completion date
November 2026
Delay so far
26 months
Homes
132
Sold or booked
90%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of AROMA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AROMA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • AROMA: covers 25 (Basement+ Ground+ 23 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AROMA every month.

AROMA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sagar Enterprise has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 16 months); 1 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of AROMA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AROMA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AROMA

What is the possession date of AROMA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AROMA in Kavesar, Thane is 30 November 2026 — 26 months later than 30 September 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AROMA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AROMA's builder has filed on MahaRERA, the official one, is 30 November 2026, already 26 months later than the 30 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AROMA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 30/10/2024 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, total parking, sanctioned number of floors and the number of floors for which CC has been issued. In view of this as the said project obtained full OC uploading consents from al…".

What is the RERA number of AROMA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AROMA in Kavesar, Thane is P51700028361.

Is AROMA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA is registered as P51700028361 and its status is "Completed".

What is the construction status of AROMA?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA's status on MahaRERA is "Completed". As filed by the builder, slab work on AROMA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AROMA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is AROMA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA is registered on MahaRERA as P51700028361, its MahaRERA status is "Completed", its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AROMA's possession date changes?

The latest dates are on AROMA's MahaRERA page (P51700028361). GharKundli's Kundli Watch sends a free WhatsApp update on AROMA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AROMA have?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA has one building filed: AROMA with 25 floors and 137 units.

How much parking does AROMA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for AROMA.

How big is the land of AROMA?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA stands on 2,970 sq m of land (about 0.7 acres), with 5,619 sq m of sanctioned built-up area.

What is the track record of AROMA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Enterprise has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 16 months); 1 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AROMA?

Google Maps has reviews of AROMA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AROMA?

AROMA by Sagar Enterprise is in Kavesar, Thane (pincode 400615), near Kasarvadavli, Anand Nagar, Maharashtra, and is registered on MahaRERA as P51700028361, per GharKundli's check of MahaRERA records.

How many homes are in AROMA?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA has 132 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.

When was AROMA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AROMA was registered on MahaRERA on 22 February 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on AROMA?

No court cases are listed for AROMA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AROMA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sagar Enterprise, which has 5 other projects registered on MahaRERA.

Other projects in Kavesar

All 158 projects in Kasarvadavali (400615) →

Other projects by Sagar Enterprise

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.