Vihang Commercial Building 10
by VIHANG INFRASTRUCTURE PVT LTD · Ovale Village, Thane 400615Also near Near Kanchan Pushpa, Ghodbunder Road, Vadavali & OwaleRegistered on MahaRERA as “COMMERCIAL BUILDING 10”
What’s in the report? →Possession date of Vihang Commercial Building 10 (MahaRERA P51700046036): 30 December 2025, moved from 31 December 2024 (12 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700046036. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700046036, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Vihang Commercial Building 10?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vihang Commercial Building 10 has moved
31 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51700027626)
Reason the builder gave MahaRERA:
“THE PROJECT CONSTRUCTION IS NOT COMPLETED AND THE PURCHASER IS AWARE OF IT. THERE ARE ONLY TWO PREMISES IN THE PROJECT. THE PURCHASER HAS GIVEN CONSENT FOR EXTENTION FOR PROJECT COMPLETION DATE. WE HAVE UPLOADED THE CONSENT FORM OF THE PURC…” Read the full reason
“THE PROJECT CONSTRUCTION IS NOT COMPLETED AND THE PURCHASER IS AWARE OF IT. THERE ARE ONLY TWO PREMISES IN THE PROJECT. THE PURCHASER HAS GIVEN CONSENT FOR EXTENTION FOR PROJECT COMPLETION DATE. WE HAVE UPLOADED THE CONSENT FORM OF THE PURCHASER. WE ARE REQUESTING YOU TO CONSIDER IT AND EXTEND THE DATE”
Source: Vihang Commercial Building 10’s extension records on MahaRERA (P51700046036), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vihang Commercial Building 10
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 9 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700046036
- Status
- Lapsed (registration period ended)
- Builder
- VIHANG INFRASTRUCTURE PVT LTD
- Location
- Ovale Village, Thane · 400615
- Project type
- Commercial
- Registered on
- 15 Jun 2022
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 0
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 9
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Vihang Commercial Building 10, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| COMMERCIAL BUILDING no 10 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- COMMERCIAL BUILDING no 10: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vihang Commercial Building 10 every 1–2 months.
Vihang Commercial Building 10: buildings, flats and land, as filed on MahaRERA
- Buildings: COMMERCIAL BUILDING no 10 (2 floors, 2 units)
- Land: 775 sq m (about 0.2 acres) · sanctioned built-up 775 sq m · recreational space 8,718 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vihang Enterprises (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 3 finished, all within the promised date; 13 still being built, none past the promised date yet; 2 lapsed. 59 complaints on MahaRERA across 5 projects.
Read Google reviews of Vihang Commercial Building 10 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vihang Commercial Building 10: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vihang Commercial Building 10
What is the possession date of Vihang Commercial Building 10?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vihang Commercial Building 10 in Ovale Village, Thane is 30 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vihang Commercial Building 10?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vihang Commercial Building 10's builder has filed on MahaRERA, the official one, is 30 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vihang Commercial Building 10 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10's builder applied to MahaRERA to extend the completion date once: to 30 December 2025, giving the reason "THE PROJECT CONSTRUCTION IS NOT COMPLETED AND THE PURCHASER IS AWARE OF IT. THERE ARE ONLY TWO PREMISES IN THE PROJECT. THE PURCHASER HAS GIVEN CONSENT FOR EXTENTION FOR PROJECT COMPLETION DATE. WE HAVE UPLOADED THE CONSENT FORM OF THE PURCHASER. WE ARE REQUESTING YOU TO CONSIDER IT AND EXTEND THE DATE".
What is the RERA number of Vihang Commercial Building 10?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vihang Commercial Building 10 in Ovale Village, Thane is P51700046036.
Is Vihang Commercial Building 10 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 is registered as P51700046036 and its status is "Lapsed (registration period ended)".
What is the current construction status of Vihang Commercial Building 10? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on COMMERCIAL BUILDING no 10 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vihang Commercial Building 10 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vihang Commercial Building 10 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 is registered on MahaRERA as P51700046036, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vihang Commercial Building 10?
Vihang Commercial Building 10 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vihang Commercial Building 10?
For a flat in Vihang Commercial Building 10 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Vihang Commercial Building 10 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Vihang Commercial Building 10?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Vihang Commercial Building 10 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vihang Commercial Building 10 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vihang Commercial Building 10's possession date changes?
The latest dates are on Vihang Commercial Building 10's MahaRERA page (P51700046036). GharKundli's Kundli Watch sends a free WhatsApp update on Vihang Commercial Building 10 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vihang Commercial Building 10 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 has one building filed: COMMERCIAL BUILDING no 10 with 2 floors and 2 units.
How big is the land of Vihang Commercial Building 10?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 stands on 775 sq m of land (about 0.2 acres), with 775 sq m of sanctioned built-up area and 8,718 sq m of recreational open space.
What is the track record of Vihang Commercial Building 10's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Enterprises (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 3 finished, all within the promised date; 13 still being built, none past the promised date yet; 2 lapsed. 59 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vihang Commercial Building 10?
Google Maps has reviews of Vihang Commercial Building 10 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vihang Commercial Building 10?
Vihang Commercial Building 10 by VIHANG INFRASTRUCTURE PVT LTD is in Ovale Village, Thane, pincode 400615 (near Near Kanchan Pushpa, Ghodbunder Road, Vadavali & Owale), Maharashtra, and is registered on MahaRERA as P51700046036, per GharKundli's check of MahaRERA records. GharKundli lists all 158 MahaRERA projects in Kasarvadavali (400615).
How many flats are in Vihang Commercial Building 10, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 has 0 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Vihang Commercial Building 10 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Commercial Building 10 was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.
Does Vihang Commercial Building 10 have any legal issues or court cases?
9 court cases are listed for Vihang Commercial Building 10 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Vihang Commercial Building 10?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIHANG INFRASTRUCTURE PVT LTD, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vihang Commercial Building 10
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Mauli Krupa
- Gurukrupa Nityam
- Lotus
- Urban Reserve Wing B
- Asavari Co Op HSG Soc LTD
- Panache
Other projects by VIHANG INFRASTRUCTURE PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.