DELTA GREENVILLE - ASTER

by DELTA SYNERGY LLP · Kasarvadavali, Thane

Registered on MahaRERA under P51700078827, and currently active. Its completion date has moved from January 2031 to May 2031, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on DELTA GREENVILLE - ASTER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700078827
Status
Registered and active
Builder
DELTA SYNERGY LLP
Location
Kasarvadavali, Thane · 400615
Project type
Residential / Group Housing
Registered on
13 Jan 2025
Completion date at registration
January 2031
Latest completion date
May 2031
Delay so far
4 months
Homes
188
Sold or booked
14%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

DELTA GREENVILLE - ASTER: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about DELTA GREENVILLE - ASTER

Is DELTA GREENVILLE - ASTER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DELTA GREENVILLE - ASTER is registered as P51700078827 and its status is "Registered and active".

Where is DELTA GREENVILLE - ASTER?

DELTA GREENVILLE - ASTER by DELTA SYNERGY LLP is in Kasarvadavali, Thane (pincode 400615), Maharashtra, and is registered on MahaRERA as P51700078827, per GharKundli's check of MahaRERA records.

When is possession of DELTA GREENVILLE - ASTER due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DELTA GREENVILLE - ASTER in Kasarvadavali, Thane is 31 May 2031 — 4 months later than 31 January 2031, the date given at registration.

Does DELTA GREENVILLE - ASTER have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of DELTA GREENVILLE - ASTER?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DELTA SYNERGY LLP, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400615

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.