by Laabh Samruddhi Enterprises · Kasarvadavli, ThaneAlso near owale, Near Kanchan Pushpa, Mogharpada

Possession date of WHITE HOUSE: 30 December 2025. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700004612. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about WHITE HOUSE?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on WHITE HOUSE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700004612
Status
Lapsed (registration period ended)
Builder
Laabh Samruddhi Enterprises
Location
Kasarvadavli, Thane · 400615
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
December 2025
Latest completion date
December 2025
Homes
135
Towers
2
Complaints on MahaRERA
2
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of WHITE HOUSE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A and A1100%12%0%0%
BUILDING B0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on WHITE HOUSE every month.

WHITE HOUSE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Laabh Builders And Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 2 lapsed. 7 complaints on MahaRERA across 3 projects.

Read Google reviews of WHITE HOUSE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

WHITE HOUSE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about WHITE HOUSE

What is the possession date of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for WHITE HOUSE in Kasarvadavli, Thane is 30 December 2025. That date has already passed.

Is the builder's possession date different from the MahaRERA date for WHITE HOUSE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date WHITE HOUSE's builder has filed on MahaRERA, the official one, is 30 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of WHITE HOUSE in Kasarvadavli, Thane is P51700004612.

Is WHITE HOUSE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE is registered as P51700004612 and its status is "Lapsed (registration period ended)".

What is the construction status of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 12% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does WHITE HOUSE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is WHITE HOUSE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE is registered on MahaRERA as P51700004612, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if WHITE HOUSE's possession date changes?

The latest dates are on WHITE HOUSE's MahaRERA page (P51700004612). GharKundli's Kundli Watch sends a free WhatsApp update on WHITE HOUSE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does WHITE HOUSE have?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE has 2 buildings filed: A and A1 with 20 floors; BUILDING B with 6 floors.

How big is the land of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE stands on 2,590 sq m of land (about 0.6 acres), with 5,303 sq m of sanctioned built-up area and 336 sq m of recreational open space.

What is the track record of WHITE HOUSE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Laabh Builders And Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 2 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of WHITE HOUSE?

Google Maps has reviews of WHITE HOUSE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is WHITE HOUSE?

WHITE HOUSE by Laabh Samruddhi Enterprises is in Kasarvadavli, Thane (pincode 400615), near owale, Near Kanchan Pushpa, Mogharpada, Maharashtra, and is registered on MahaRERA as P51700004612, per GharKundli's check of MahaRERA records.

How many homes are in WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE has 135 homes in 2 towers registered on MahaRERA.

When was WHITE HOUSE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), WHITE HOUSE was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on WHITE HOUSE?

No court cases are listed for WHITE HOUSE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Laabh Samruddhi Enterprises.

Other projects in pincode 400615