Tokyo Bay Phase - 2A
by Puranik Tokyo Bay Private Limited (Fortune) · Near Aarambh Project, ThaneAlso near owale, Kasarvadavli, Near Kanchan Pushpa
Possession date of Tokyo Bay Phase - 2A: 31 May 2025, moved from 30 December 2024 (5 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700000520. Status: Lapsed (registration period ended). 59 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (May 2025) has passed.
What do you want to know about Tokyo Bay Phase - 2A?
How the possession date of Tokyo Bay Phase - 2A has moved
30 December 2024
Completion date given when the project was registered
31 May 2025
Extended at the builder's request (MahaRERA application EXT51700024856)
Reason the builder gave MahaRERA:
“1. DELAY DUE TO GOVT. ORDERS: Environment Clearance Application was made on 20/11/2018 (construction of 26th Flr. to 35th Fl.) and permission was granted on 15/1/2020 (13 months delay). Letter dtd. 18/5/2020 by Conservator of Forest and Dir…” Read the full reason
“1. DELAY DUE TO GOVT. ORDERS: Environment Clearance Application was made on 20/11/2018 (construction of 26th Flr. to 35th Fl.) and permission was granted on 15/1/2020 (13 months delay). Letter dtd. 18/5/2020 by Conservator of Forest and Dir. Sanjay Gandhi National Park (SGNP) To Principal Secretary Urban Devp. Dept. leading to such as ‘stop work’ notices, withholding of certificates by Municipal Corporations. Accordingly Principal Secretary of Environment Department issued Letter dtd. 30/6/2020 to Commissioner, TMC. TMC by letters dtd. 23/9/2020, 11/11/2020 and 6/5/2021 sought guidance from…”
Source: Tokyo Bay Phase - 2A’s extension records on MahaRERA (P51700000520), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tokyo Bay Phase - 2A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 59 complaints and 5 court cases, and how it ended
- Construction pace against the May 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Tokyo Bay Phase - 1P51700000618 · possession 30 Oct 2023
- Tokyo Bay Phase 2BPR1332022500196 · possession 30 Apr 2036
- Tokyo Bay Phase - 2CP51700020265 · possession 28 Feb 2027
- MahaRERA registration
- P51700000520
- Status
- Lapsed (registration period ended)
- Builder
- Puranik Tokyo Bay Private Limited
- Location
- Near Aarambh Project, Thane · 400615
- Project type
- Residential / Group Housing
- Registered on
- 18 Jul 2017
- Completion date at registration
- December 2024
- Latest completion date
- May 2025
- Delay so far
- 5 months
- Homes
- 230
- Sold or booked
- 97%
- Towers
- 2
- Complaints on MahaRERA
- 59
- Court cases listed
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Tokyo Bay Phase - 2A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building 2-Taizo | 100% | 100% | 100% | 90% |
| Building 3-Zuisen | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tokyo Bay Phase - 2A every month.
Tokyo Bay Phase - 2A: buildings, flats and land, as filed on MahaRERA
- Buildings: Building 2-Taizo (38 floors) · Building 3-Zuisen (38 floors)
- Land: 6,899 sq m (about 1.7 acres) · sanctioned built-up 19,138 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 28 GharKundli has checked: 6 finished, all within the promised date; 20 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects.
Read Google reviews of Tokyo Bay Phase - 2A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tokyo Bay Phase - 2A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Tokyo Bay Phase - 2A
What is the possession date of Tokyo Bay Phase - 2A?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tokyo Bay Phase - 2A in Near Aarambh Project, Thane is 31 May 2025 — 5 months later than 30 December 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Tokyo Bay Phase - 2A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tokyo Bay Phase - 2A's builder has filed on MahaRERA, the official one, is 31 May 2025, already 5 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tokyo Bay Phase - 2A extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A's builder applied to MahaRERA to extend the completion date once: to 31 May 2025, giving the reason "1. DELAY DUE TO GOVT. ORDERS: Environment Clearance Application was made on 20/11/2018 (construction of 26th Flr. to 35th Fl.) and permission was granted on 15/1/2020 (13 months delay). Letter dtd. 18/5/2020 by Conservator of Forest and Dir. Sanjay Gandhi National Park (SGNP) To Principal Secretary Urban Devp. Dept. leading to such as ‘stop work’ notices, withholding of certificates by Municipal Corporations. Accordingly Principal Secretary of Environment Department issued Letter dtd. 30/6/2020 to Commissioner, TMC. TMC by letters dtd. 23/9/2020, 11/11/2020 and 6/5/2021 sought guidance from…".
What is the RERA number of Tokyo Bay Phase - 2A?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tokyo Bay Phase - 2A in Near Aarambh Project, Thane is P51700000520.
Is Tokyo Bay Phase - 2A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A is registered as P51700000520 and its status is "Lapsed (registration period ended)".
What is the construction status of Tokyo Bay Phase - 2A?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Tokyo Bay Phase - 2A have complaints on MahaRERA?
59 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Tokyo Bay Phase - 2A safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A is registered on MahaRERA as P51700000520, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 5 months since registration and 59 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Tokyo Bay Phase - 2A have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Tokyo Bay Phase - 1 (P51700000618, possession 30 Oct 2023); Tokyo Bay Phase 2B (PR1332022500196, possession 30 Apr 2036); Tokyo Bay Phase - 2C (P51700020265, possession 28 Feb 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Tokyo Bay Phase - 2A's possession date changes?
The latest dates are on Tokyo Bay Phase - 2A's MahaRERA page (P51700000520). GharKundli's Kundli Watch sends a free WhatsApp update on Tokyo Bay Phase - 2A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tokyo Bay Phase - 2A have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A has 2 buildings filed: Building 2-Taizo with 38 floors; Building 3-Zuisen with 38 floors.
How big is the land of Tokyo Bay Phase - 2A?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A stands on 6,899 sq m of land (about 1.7 acres), with 19,138 sq m of sanctioned built-up area.
What is the track record of Tokyo Bay Phase - 2A's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 28 GharKundli has checked: 6 finished, all within the promised date; 20 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Tokyo Bay Phase - 2A?
Google Maps has reviews of Tokyo Bay Phase - 2A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 59 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Tokyo Bay Phase - 2A?
Tokyo Bay Phase - 2A by Puranik Tokyo Bay Private Limited (Fortune) is in Near Aarambh Project, Thane (pincode 400615), near owale, Kasarvadavli, Near Kanchan Pushpa, Maharashtra, and is registered on MahaRERA as P51700000520, per GharKundli's check of MahaRERA records.
How many homes are in Tokyo Bay Phase - 2A?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A has 230 homes in 2 towers registered on MahaRERA, and 97% of them are sold or booked.
When was Tokyo Bay Phase - 2A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tokyo Bay Phase - 2A was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Tokyo Bay Phase - 2A?
5 court cases are listed for Tokyo Bay Phase - 2A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Tokyo Bay Phase - 2A?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Puranik Tokyo Bay Private Limited, the company Fortune files this project under, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tokyo Bay Phase - 2A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- Tokyo Bay Phase - 2C
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- Panache
- LOTUS
- ASAVARI CO OP HSG SOC LTD
Other projects by Puranik Tokyo Bay Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.