IKIGAI - Phase 1

by Puranik Tokyo Bay Private Limited (Fortune) · Ghodbunder Road, ThaneAlso near owale, Borivali West, Kasarvadavli

Possession date of IKIGAI - Phase 1: 30 April 2032. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700006605, and currently active. Its completion date is now April 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about IKIGAI - Phase 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of IKIGAI - Phase 1 has moved

  1. 30 December 2031

    Completion date given when the project was registered

  2. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: IKIGAI - Phase 1’s extension records on MahaRERA (P51700006605), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on IKIGAI - Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 1 court case, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700006605
Status
Registered and active
Builder
Puranik Tokyo Bay Private Limited
Location
Ghodbunder Road, Thane · 400615
Project type
Others
Registered on
14 Aug 2017
Completion date at registration
December 2031
Latest completion date
April 2032
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
623
Sold or booked
88%
Towers
2
Complaints on MahaRERA
7
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of IKIGAI - Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A1 - Hana100%1%0%0%
Building A2 - Ayami100%1%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on IKIGAI - Phase 1 every month.

IKIGAI - Phase 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building A1 - Hana (43 floors) · Building A2 - Ayami (43 floors)
  • Land: 900 sq m (about 0.2 acres) · sanctioned built-up 22,576 sq m · recreational space 663 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 28 GharKundli has checked: 6 finished, all within the promised date; 20 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects.

Read Google reviews of IKIGAI - Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

IKIGAI - Phase 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about IKIGAI - Phase 1

What is the possession date of IKIGAI - Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for IKIGAI - Phase 1 in Ghodbunder Road, Thane is 30 April 2032, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for IKIGAI - Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date IKIGAI - Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of IKIGAI - Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of IKIGAI - Phase 1 in Ghodbunder Road, Thane is P51700006605.

Is IKIGAI - Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1 is registered as P51700006605 and its status is "Registered and active".

What is the construction status of IKIGAI - Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 1% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does IKIGAI - Phase 1 have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is IKIGAI - Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1 is registered on MahaRERA as P51700006605, its completion date has not been moved by the builder and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does IKIGAI - Phase 1 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: IKIGAI Phase 2 (P51700051124, possession 30 Apr 2031). Check that your agreement names the registration of your own wing.

How can I get updates if IKIGAI - Phase 1's possession date changes?

The latest dates are on IKIGAI - Phase 1's MahaRERA page (P51700006605). GharKundli's Kundli Watch sends a free WhatsApp update on IKIGAI - Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does IKIGAI - Phase 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1 has 2 buildings filed: Building A1 - Hana with 43 floors; Building A2 - Ayami with 43 floors.

How big is the land of IKIGAI - Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1 stands on 900 sq m of land (about 0.2 acres), with 22,576 sq m of sanctioned built-up area and 663 sq m of recreational open space.

What is the track record of IKIGAI - Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 28 GharKundli has checked: 6 finished, all within the promised date; 20 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of IKIGAI - Phase 1?

Google Maps has reviews of IKIGAI - Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is IKIGAI - Phase 1?

IKIGAI - Phase 1 by Puranik Tokyo Bay Private Limited (Fortune) is in Ghodbunder Road, Thane (pincode 400615), near owale, Borivali West, Kasarvadavli, Maharashtra, and is registered on MahaRERA as P51700006605, per GharKundli's check of MahaRERA records.

How many homes are in IKIGAI - Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1 has 623 homes in 2 towers registered on MahaRERA, and 88% of them are sold or booked.

When was IKIGAI - Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), IKIGAI - Phase 1 was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on IKIGAI - Phase 1?

1 court case is listed for IKIGAI - Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of IKIGAI - Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Puranik Tokyo Bay Private Limited, the company Fortune files this project under, which has 5 other projects registered on MahaRERA.

Other projects in pincode 400615

All 158 projects in Kasarvadavali (400615) →

Other projects by Puranik Tokyo Bay Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.