IKIGAI Phase 2
by Puranik Tokyo Bay Private Limited · Village Owale, Taluka and District Thane, Thane
Registered on MahaRERA under P51700051124, and currently active. Its completion date has moved from December 2030 to April 2031, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on IKIGAI Phase 2
Ready · October 2026 · 81 filings read
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700051124
- Status
- Registered and active
- Builder
- Puranik Tokyo Bay Private Limited
- Location
- Village Owale, Taluka and District Thane, Thane · 400615
- Project type
- Residential / Group Housing
- Registered on
- 30 May 2023
- Completion date at registration
- December 2030
- Latest completion date
- April 2031
- Delay so far
- 4 months
- Homes
- 305
- Sold or booked
- 66%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Yes
- Latest construction certificate
- 30 Jun 2026
- Builder's other MahaRERA projects
- 5
Kundli Watch
IKIGAI Phase 2: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about IKIGAI Phase 2
Is IKIGAI Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), IKIGAI Phase 2 is registered as P51700051124 and its status is "Registered and active".
Where is IKIGAI Phase 2?
IKIGAI Phase 2 by Puranik Tokyo Bay Private Limited is in Village Owale, Taluka and District Thane, Thane (pincode 400615), Maharashtra, and is registered on MahaRERA as P51700051124, per GharKundli's check of MahaRERA records.
When is possession of IKIGAI Phase 2 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for IKIGAI Phase 2 in Village Owale, Taluka and District Thane, Thane is 30 April 2031 — 4 months later than 31 December 2030, the date given at registration.
Does IKIGAI Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of IKIGAI Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Puranik Tokyo Bay Private Limited, which has 5 other projects registered on MahaRERA.
Other projects in pincode 400615
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.