Rumah Bali Phase 5

by Puranik Rumah Bali Private Limited (Fortune) · Kanchan Pushp, Kavesar, Thane 400615Also near Owala, Kasarvadavali

What’s in the report? →

Possession date of Rumah Bali Phase 5 (MahaRERA PR1332022501317): 30 April 2036. It has 277 homes, 13% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1332022501317, and currently active. Its completion date is now April 2036, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1332022501317, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Rumah Bali Phase 5?

6 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Rumah Bali Phase 5 has moved

  1. 31 December 2035

    Completion date given when the project was registered

  2. 30 April 2036

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Rumah Bali Phase 5’s extension records on MahaRERA (PR1332022501317), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rumah Bali Phase 5

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 court cases, and how it ended
  • Construction pace against the April 2036 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
PR1332022501317
Status
Registered and active
Builder
Puranik Rumah Bali Private Limited
Location
Kanchan Pushp, Kavesar, Thane · 400615
Project type
Residential / Group Housing
Registered on
20 Oct 2025
Completion date at registration
December 2035
Latest completion date
April 2036
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
277
Sold or booked
13%
Towers
1
Complaints on MahaRERA
0
Court cases listed
6
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Rumah Bali Phase 5, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A5100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • A5: covers 39 floors

Latest CC order on MahaRERA: dated 10/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rumah Bali Phase 5 every 1–2 months.

Rumah Bali Phase 5: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 44 GharKundli has checked: 14 finished, all within the promised date; 27 still being built, none past the promised date yet; 3 lapsed. 327 complaints on MahaRERA across 29 projects.

Read Google reviews of Rumah Bali Phase 5 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rumah Bali Phase 5: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Rumah Bali Phase 5

What is the possession date of Rumah Bali Phase 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rumah Bali Phase 5 in Kanchan Pushp, Kavesar, Thane is 30 April 2036, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Rumah Bali Phase 5?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rumah Bali Phase 5's builder has filed on MahaRERA, the official one, is 30 April 2036, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Rumah Bali Phase 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rumah Bali Phase 5 in Kanchan Pushp, Kavesar, Thane is PR1332022501317.

Is Rumah Bali Phase 5 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 is registered as PR1332022501317 and its status is "Registered and active".

What is the current construction status of Rumah Bali Phase 5? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A5 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Rumah Bali Phase 5 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Rumah Bali Phase 5 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 is registered on MahaRERA as PR1332022501317, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Rumah Bali Phase 5?

Rumah Bali Phase 5 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Rumah Bali Phase 5?

For a flat in Rumah Bali Phase 5 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Rumah Bali Phase 5 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 is still under construction, with 30 April 2036 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Rumah Bali Phase 5 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rumah Bali Phase 5 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Rumah Bali Phase 5 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Rumah Bali Phase 3 (P51700015955, possession 30 Apr 2032); Rumah Bali Phase 4 (P51700046777, possession 30 Apr 2029); Rumah Bali Phase 6 (PR1333032501756, possession 30 Oct 2036). Check that your agreement names the registration of your own wing.

How can I get updates if Rumah Bali Phase 5's possession date changes?

The latest dates are on Rumah Bali Phase 5's MahaRERA page (PR1332022501317). GharKundli's Kundli Watch sends a free WhatsApp update on Rumah Bali Phase 5 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rumah Bali Phase 5 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 has one building filed: A5 with 39 floors and 277 units.

How much parking does Rumah Bali Phase 5 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 142 covered car parking spaces for Rumah Bali Phase 5.

How big is the land of Rumah Bali Phase 5?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 stands on 50,286 sq m of land (about 12.4 acres), with 17,565 sq m of sanctioned built-up area and 10,762 sq m of recreational open space.

What is the track record of Rumah Bali Phase 5's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 44 GharKundli has checked: 14 finished, all within the promised date; 27 still being built, none past the promised date yet; 3 lapsed. 327 complaints on MahaRERA across 29 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Rumah Bali Phase 5?

Google Maps has reviews of Rumah Bali Phase 5 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Rumah Bali Phase 5?

Rumah Bali Phase 5 by Puranik Rumah Bali Private Limited (Fortune) is in Kanchan Pushp, Kavesar, Thane, pincode 400615 (near Owala, Kasarvadavali), Maharashtra, and is registered on MahaRERA as PR1332022501317, per GharKundli's check of MahaRERA records. GharKundli lists all 158 MahaRERA projects in Kasarvadavali (400615).

How many flats are in Rumah Bali Phase 5, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 has 277 homes in 1 tower registered on MahaRERA, and 13% of them are sold or booked.

When was Rumah Bali Phase 5 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rumah Bali Phase 5 was registered on MahaRERA on 20 October 2025. GharKundli did not find a title report on the land on file there.

Does Rumah Bali Phase 5 have any legal issues or court cases?

6 court cases are listed for Rumah Bali Phase 5 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Rumah Bali Phase 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Puranik Rumah Bali Private Limited, the company Fortune files this project under, which has 1 other project registered on MahaRERA.

Other projects in Thane

All 158 projects in Kasarvadavali (400615) →

Other projects by Puranik Rumah Bali Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.