Skip to content
GharKundli

KAVYA PARK

by SHREE CONSTRUCTION COMPANY (Kavya) · Kasarvadavali, ThaneAlso near owale, Near Kanchan Pushpa, Mogharpada

Possession date of KAVYA PARK: 30 October 2027, moved from 30 June 2021 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700010575, and currently active. Its completion date has moved from June 2021 to October 2027: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 10 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about KAVYA PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KAVYA PARK has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51700010449)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51700013466)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 24 MONTHS”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EA22052501215)

    Reason the builder gave MahaRERA:
    “a Delay in Procuring ULC Order: The said Project was subject to Urban Land Ceiling (ULC) regulations and the process of procuring the necessary ULC order was time-consuming due to procedural formalities and approvals required from the conce…” Read the full reason“a Delay in Procuring ULC Order: The said Project was subject to Urban Land Ceiling (ULC) regulations and the process of procuring the necessary ULC order was time-consuming due to procedural formalities and approvals required from the concerned authorities. The alleged delay in obtaining this onder directly impacted the said Project's timeline”
  5. 30 June 2027

    Extended at the builder's request (MahaRERA application EA18022619896)

    Reason the builder gave MahaRERA:
    “We, SHREE CONSTRUCTION COMPANY, are the promoters of the real estate project known as "KAVYA PARK" bearing Maha RERA Registration No. P51700010575 are applying for an extension as:1) Certain permissions require revision and thus keeping in…” Read the full reason“We, SHREE CONSTRUCTION COMPANY, are the promoters of the real estate project known as "KAVYA PARK" bearing Maha RERA Registration No. P51700010575 are applying for an extension as:1) Certain permissions require revision and thus keeping in mind the timelines, an extension for completion of project has been applied for”
  6. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KAVYA PARK’s extension records on MahaRERA (P51700010575), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KAVYA PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 10 complaints, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700010575
Status
Registered and active
Builder
SHREE CONSTRUCTION COMPANY
Location
Kasarvadavali, Thane · 400615
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
June 2021
Latest completion date
October 2027
Delay so far
72 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
143
Sold or booked
80%
Towers
3
Complaints on MahaRERA
10
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of KAVYA PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAVYA PARK A WING100%66.67%13%8.5%
KAVYA PARK B WING100%67%21.07%6%
KAVYA PARK C WING100%58.34%14.93%8.5%

Commencement certificate (CC), as filed on MahaRERA

  • KAVYA PARK A WING: covers 13 floors
  • KAVYA PARK B WING: covers 14 floors
  • KAVYA PARK C WING: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KAVYA PARK every month.

KAVYA PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: KAVYA PARK A WING (14 floors, 58 units) · KAVYA PARK B WING (31 floors, 57 units) · KAVYA PARK C WING (15 floors, 58 units)
  • Car parking: 16 covered
  • Land: 4,680 sq m (about 1.2 acres) · sanctioned built-up 3,962 sq m · recreational space 658 sq m
  • Boundaries filed include: GOAN ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Kavya Mira Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 48 months late); 1 lapsed. 27 complaints on MahaRERA across 3 projects.

Read Google reviews of KAVYA PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KAVYA PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KAVYA PARK

What is the possession date of KAVYA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KAVYA PARK in Kasarvadavali, Thane is 30 October 2027 — 72 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for KAVYA PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KAVYA PARK's builder has filed on MahaRERA, the official one, is 30 October 2027, already 72 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KAVYA PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS"; to 31 December 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 24 MONTHS"; to 31 December 2025, giving the reason "a Delay in Procuring ULC Order: The said Project was subject to Urban Land Ceiling (ULC) regulations and the process of procuring the necessary ULC order was time-consuming due to procedural formalities and approvals required from the concerned authorities. The alleged delay in obtaining this onder directly impacted the said Project's timeline"; to 30 June 2027, giving the reason "We, SHREE CONSTRUCTION COMPANY, are the promoters of the real estate project known as "KAVYA PARK" bearing Maha RERA Registration No. P51700010575 are applying for an extension as:1) Certain permissions require revision and thus keeping in mind the timelines, an extension for completion of project has been applied for". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of KAVYA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KAVYA PARK in Kasarvadavali, Thane is P51700010575.

Is KAVYA PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK is registered as P51700010575 and its status is "Registered and active".

What is the construction status of KAVYA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 58.34% to 67% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does KAVYA PARK have complaints on MahaRERA?

10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is KAVYA PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK is registered on MahaRERA as P51700010575, its completion date has moved 72 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KAVYA PARK's possession date changes?

The latest dates are on KAVYA PARK's MahaRERA page (P51700010575). GharKundli's Kundli Watch sends a free WhatsApp update on KAVYA PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KAVYA PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK has 3 buildings filed: KAVYA PARK A WING with 14 floors and 58 units; KAVYA PARK B WING with 31 floors and 57 units; KAVYA PARK C WING with 15 floors and 58 units.

How much parking does KAVYA PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered car parking spaces for KAVYA PARK.

How big is the land of KAVYA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK stands on 4,680 sq m of land (about 1.2 acres), with 3,962 sq m of sanctioned built-up area and 658 sq m of recreational open space.

What is the track record of KAVYA PARK's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kavya Mira Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 48 months late); 1 lapsed. 27 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KAVYA PARK?

Google Maps has reviews of KAVYA PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KAVYA PARK?

KAVYA PARK by SHREE CONSTRUCTION COMPANY (Kavya) is in Kasarvadavali, Thane (pincode 400615), near owale, Near Kanchan Pushpa, Mogharpada, Maharashtra, and is registered on MahaRERA as P51700010575, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOAN ROAD.

How many homes are in KAVYA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK has 143 homes in 3 towers registered on MahaRERA, and 80% of them are sold or booked.

When was KAVYA PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KAVYA PARK was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KAVYA PARK?

No court cases are listed for KAVYA PARK on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of KAVYA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE CONSTRUCTION COMPANY, the company Kavya files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in pincode 400615

All 158 projects in Kasarvadavali (400615) →

Other projects by SHREE CONSTRUCTION COMPANY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.