PURUSHOTTAMNAYAN
by GAURAV ENTERPRISES · Kasarvadavali, ThaneAlso near Kavesar, owale, Borivali West
Possession date of PURUSHOTTAMNAYAN: 30 April 2029, moved from 30 December 2022 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700007793, and currently active. Its completion date has moved from December 2022 to April 2029: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PURUSHOTTAMNAYAN?
How the possession date of PURUSHOTTAMNAYAN has moved
30 December 2022
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EXT51700024923)
Reason the builder gave MahaRERA: “we have attached reason for extension in below attachments”
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PURUSHOTTAMNAYAN’s extension records on MahaRERA (P51700007793), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PURUSHOTTAMNAYAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700007793
- Status
- Registered and active
- Builder
- GAURAV ENTERPRISES
- Location
- Kasarvadavali, Thane · 400615
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2029
- Delay so far
- 72 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 180
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of PURUSHOTTAMNAYAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
| B | 100% | 100% | 72% | 72% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PURUSHOTTAMNAYAN every month.
PURUSHOTTAMNAYAN: buildings, flats and land, as filed on MahaRERA
- Buildings: A (3 floors) · B (24 floors)
- Land: 5,540 sq m (about 1.4 acres) · sanctioned built-up 7,278 sq m · recreational space 1,096 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PURUSHOTTAMNAYAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PURUSHOTTAMNAYAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PURUSHOTTAMNAYAN
What is the possession date of PURUSHOTTAMNAYAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PURUSHOTTAMNAYAN in Kasarvadavali, Thane is 30 April 2029 — 72 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PURUSHOTTAMNAYAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PURUSHOTTAMNAYAN's builder has filed on MahaRERA, the official one, is 30 April 2029, already 72 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PURUSHOTTAMNAYAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "we have attached reason for extension in below attachments". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PURUSHOTTAMNAYAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PURUSHOTTAMNAYAN in Kasarvadavali, Thane is P51700007793.
Is PURUSHOTTAMNAYAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN is registered as P51700007793 and its status is "Registered and active".
What is the construction status of PURUSHOTTAMNAYAN?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does PURUSHOTTAMNAYAN have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PURUSHOTTAMNAYAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN is registered on MahaRERA as P51700007793, its completion date has moved 72 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PURUSHOTTAMNAYAN's possession date changes?
The latest dates are on PURUSHOTTAMNAYAN's MahaRERA page (P51700007793). GharKundli's Kundli Watch sends a free WhatsApp update on PURUSHOTTAMNAYAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PURUSHOTTAMNAYAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN has 2 buildings filed: A with 3 floors; B with 24 floors.
How big is the land of PURUSHOTTAMNAYAN?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN stands on 5,540 sq m of land (about 1.4 acres), with 7,278 sq m of sanctioned built-up area and 1,096 sq m of recreational open space.
Where can I read reviews of PURUSHOTTAMNAYAN?
Google Maps has reviews of PURUSHOTTAMNAYAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PURUSHOTTAMNAYAN?
PURUSHOTTAMNAYAN by GAURAV ENTERPRISES is in Kasarvadavali, Thane (pincode 400615), near Kavesar, owale, Borivali West, Maharashtra, and is registered on MahaRERA as P51700007793, per GharKundli's check of MahaRERA records.
How many homes are in PURUSHOTTAMNAYAN?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN has 180 homes in 2 towers registered on MahaRERA.
When was PURUSHOTTAMNAYAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PURUSHOTTAMNAYAN was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PURUSHOTTAMNAYAN?
No court cases are listed for PURUSHOTTAMNAYAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PURUSHOTTAMNAYAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GAURAV ENTERPRISES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PURUSHOTTAMNAYAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 400615
- HORIZON EXOTICA
- HORIZON PALMS - III
- Mahavir Breeze Phase 1
- LAKESCAPE
- NIYATI LAKE CROWN
- Tokyo Bay Phase 2B
- ROSA SEPHORA
- OPUS
Other projects by GAURAV ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.