Skip to content
GharKundli

VED HEIGHTS

by PRAFUL NARENDRA DESHMUKH · Shivaji Nagar, NagpurAlso near Bajaj Nagar, Ambazari, Khare Town Dharampeth

Possession date of VED HEIGHTS: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500014030, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VED HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VED HEIGHTS has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT50500017053)

    Reason the builder gave MahaRERA:
    “1) After the impact of the pandemic, the increasing prices of the construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projects. We suf…” Read the full reason“1) After the impact of the pandemic, the increasing prices of the construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projects. We suffering from delays in terms of the number of days it takes for the arrival of the Construction Material on the project site after placing the order for the same. 2) Also, our Construction activities slowed down has slowed down due to an acute shortage of workers such as masons, earth workers, carpenters, plumbers and others. Except for a few, most of the…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA20072621807)

    Reason the builder gave MahaRERA:
    “Our project was earlier granted an extension of 2 years, from 30/12/2022 to 31/12/2024, due to the adverse impact of the pandemic and financial constraints. We had simultaneously applied revised construction permissions for additional const…” Read the full reason“Our project was earlier granted an extension of 2 years, from 30/12/2022 to 31/12/2024, due to the adverse impact of the pandemic and financial constraints. We had simultaneously applied revised construction permissions for additional construction area, including 3 extra floors on 03-02-2023 to utilize the remaining FSI. The revised sanction plan for these extra floors was finally approved by Nagpur Municipal Corporation on 08/07/2024. Thisdelay in approval for revised plan consumed valuable 17 months out of 24 months, ie 75% of the extended time to complete the project. The Part Occupancy…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VED HEIGHTS’s extension records on MahaRERA (P50500014030), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VED HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500014030
Status
Registered and active
Builder
PRAFUL NARENDRA DESHMUKH
Location
Shivaji Nagar, Nagpur · 440010
Project type
Residential / Group Housing
Registered on
7 Nov 2017
Completion date at registration
December 2022
Latest completion date
April 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
26
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VED HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VED HEIGHTS100%100%100%99%

Commencement certificate (CC), as filed on MahaRERA

  • VED HEIGHTS: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VED HEIGHTS every month.

VED HEIGHTS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VED HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VED HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VED HEIGHTS

What is the possession date of VED HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VED HEIGHTS in Shivaji Nagar, Nagpur is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VED HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VED HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VED HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "1) After the impact of the pandemic, the increasing prices of the construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projects. We suffering from delays in terms of the number of days it takes for the arrival of the Construction Material on the project site after placing the order for the same. 2) Also, our Construction activities slowed down has slowed down due to an acute shortage of workers such as masons, earth workers, carpenters, plumbers and others. Except for a few, most of the…"; to 31 December 2026, giving the reason "Our project was earlier granted an extension of 2 years, from 30/12/2022 to 31/12/2024, due to the adverse impact of the pandemic and financial constraints. We had simultaneously applied revised construction permissions for additional construction area, including 3 extra floors on 03-02-2023 to utilize the remaining FSI. The revised sanction plan for these extra floors was finally approved by Nagpur Municipal Corporation on 08/07/2024. Thisdelay in approval for revised plan consumed valuable 17 months out of 24 months, ie 75% of the extended time to complete the project. The Part Occupancy…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VED HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VED HEIGHTS in Shivaji Nagar, Nagpur is P50500014030.

Is VED HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS is registered as P50500014030 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: completion date lapsed. MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the construction status of VED HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VED HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does VED HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VED HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS is registered on MahaRERA as P50500014030, its completion date has moved 48 months since registration, no complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: completion date lapsed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VED HEIGHTS's possession date changes?

The latest dates are on VED HEIGHTS's MahaRERA page (P50500014030). GharKundli's Kundli Watch sends a free WhatsApp update on VED HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VED HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS has one building filed: VED HEIGHTS with 12 floors and 26 units.

How big is the land of VED HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS stands on 1,337 sq m of land (about 0.3 acres), with 1,791 sq m of sanctioned built-up area.

Where can I read reviews of VED HEIGHTS?

Google Maps has reviews of VED HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VED HEIGHTS?

VED HEIGHTS by PRAFUL NARENDRA DESHMUKH is in Shivaji Nagar, Nagpur (pincode 440010), near Bajaj Nagar, Ambazari, Khare Town Dharampeth, Maharashtra, and is registered on MahaRERA as P50500014030, per GharKundli's check of MahaRERA records.

How many homes are in VED HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS has 26 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was VED HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VED HEIGHTS was registered on MahaRERA on 7 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VED HEIGHTS?

No court cases are listed for VED HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VED HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRAFUL NARENDRA DESHMUKH.

All projects with possession due in 2027 in Nagpur →

Other projects in Shivaji Nagar

All 75 projects in Shankar Nagar (440010) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.