Sneh Serene
by SNEH BUILDCON · Vishnunagar, Thane 421202Also near Manpada
What’s in the report? →Possession date of Sneh Serene (MahaRERA P51700030955): 30 October 2026, moved from 30 June 2025 (12 months later), and it has already passed. It has 143 homes, 68% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700030955, and currently active. Its completion date has moved from June 2025 to October 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700030955, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Sneh Serene?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sneh Serene has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA12062501551)
Reason the builder gave MahaRERA:
“It may be stated that presently around 85% work of the project is completed and for the completion of the construction of the building, it will take around 4-5 months. Thereafter, an application of occupancy certificate will be made within…” Read the full reason
“It may be stated that presently around 85% work of the project is completed and for the completion of the construction of the building, it will take around 4-5 months. Thereafter, an application of occupancy certificate will be made within 2-3 months from the date of completion of construction of building. After the said application is made, it is expected that the occupancy certificate will be issued 2-3 months by the local authority.”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sneh Serene’s extension records on MahaRERA (P51700030955), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sneh Serene
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700030955
- Status
- Registered and active
- Builder
- SNEH BUILDCON
- Location
- Vishnunagar, Thane · 421202
- Project type
- Residential / Group Housing
- Registered on
- 29 Sep 2021
- Completion date at registration
- June 2025
- Latest completion date
- October 2026
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 143
- Sold or booked
- 68%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Sneh Serene, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SNEH SERENE | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- SNEH SERENE: covers 22 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sneh Serene every 1–2 months.
Sneh Serene: buildings, flats and land, as filed on MahaRERA
- Buildings: SNEH SERENE (22 floors, 160 units)
- Car parking: 10 covered, 34 open
- Land: 2,140 sq m (about 0.5 acres) · sanctioned built-up 9,555 sq m
- Land, as filed: SURVEY NO 35/9, 35/10, 36/1, 36/2 AND 49/5/2
- Map: Get directions
The builder’s record and reviews
Sneh Makewell (a group of 6 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Sneh Serene →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sneh Serene: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sneh Serene
What is the possession date of Sneh Serene?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sneh Serene in Vishnunagar, Thane is 30 October 2026 — 12 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sneh Serene?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sneh Serene's builder has filed on MahaRERA, the official one, is 30 October 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sneh Serene extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "It may be stated that presently around 85% work of the project is completed and for the completion of the construction of the building, it will take around 4-5 months. Thereafter, an application of occupancy certificate will be made within 2-3 months from the date of completion of construction of building. After the said application is made, it is expected that the occupancy certificate will be issued 2-3 months by the local authority.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sneh Serene?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sneh Serene in Vishnunagar, Thane is P51700030955.
Is Sneh Serene registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene is registered as P51700030955 and its status is "Registered and active".
What is the current construction status of Sneh Serene? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SNEH SERENE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sneh Serene have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sneh Serene safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene is registered on MahaRERA as P51700030955, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sneh Serene?
Sneh Serene is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sneh Serene?
For a flat in Sneh Serene (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sneh Serene received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sneh Serene uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sneh Serene was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sneh Serene's possession date changes?
The latest dates are on Sneh Serene's MahaRERA page (P51700030955). GharKundli's Kundli Watch sends a free WhatsApp update on Sneh Serene every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sneh Serene have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene has one building filed: SNEH SERENE with 22 floors and 160 units.
How much parking does Sneh Serene have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered and 34 open car parking spaces for Sneh Serene.
How big is the land of Sneh Serene?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene stands on 2,140 sq m of land (about 0.5 acres), with 9,555 sq m of sanctioned built-up area.
What is the track record of Sneh Serene's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Makewell (a group of 6 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sneh Serene?
Google Maps has reviews of Sneh Serene written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sneh Serene?
Sneh Serene by SNEH BUILDCON is in Vishnunagar, Thane, pincode 421202 (near Manpada), Maharashtra, and is registered on MahaRERA as P51700030955, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 35/9, 35/10, 36/1, 36/2 AND 49/5/2. GharKundli lists all 226 MahaRERA projects in Vishnunagar (421202).
How many flats are in Sneh Serene, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene has 143 homes in 1 tower registered on MahaRERA, and 68% of them are sold or booked.
When was Sneh Serene registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sneh Serene was registered on MahaRERA on 29 September 2021. GharKundli did not find a title report on the land on file there.
Does Sneh Serene have any legal issues or court cases?
1 court case is listed for Sneh Serene on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Sneh Serene?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SNEH BUILDCON.
Check it yourself on MahaRERA
- How to check the possession date of Sneh Serene
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Vishnunagar (421202)
- Balaji Siddhivinayak Complex Building No. 1 B Wing
- Amar Elegance
- Majesty Heights
- Ram Janki
- Mangal Plaza
- Sai Narayan
- Shikhar Skyline
- Krishna Kunj
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.