Skip to content
GharKundli

Balaji Siddhivinayak Complex Building No. 1 B Wing

by M/s Onkareshwar Developers · Gaondevi - Dombivli West, Thane

Possession date of Balaji Siddhivinayak Complex Building No. 1 B Wing: 30 September 2026, moved from 30 December 2025 (9 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700018430. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about Balaji Siddhivinayak Complex Building No. 1 B Wing?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Balaji Siddhivinayak Complex Building No. 1 B Wing has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA23062621484)

    Reason the builder gave MahaRERA:
    “The project was registered with the Maharashtra Real Estate Regulatory Authority in November 2018, with an estimated completion timeline up to 30/12/2025. We hereby seek an extension of the project timeline up to 30/09/2026 under Section 7(…” Read the full reason“The project was registered with the Maharashtra Real Estate Regulatory Authority in November 2018, with an estimated completion timeline up to 30/12/2025. We hereby seek an extension of the project timeline up to 30/09/2026 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The construction of the project has been completed, and the Occupancy Certificate has been obtained as of 25/02/2026. Possession has also been handed over to allottees. All requisite NOCs have been duly submitted by the Promoter, and there are no pending compliances on the part of the Promoter.…”

Source: Balaji Siddhivinayak Complex Building No. 1 B Wing’s extension records on MahaRERA (P51700018430), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Balaji Siddhivinayak Complex Building No. 1 B Wing

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700018430
Status
Lapsed (registration period ended)
Builder
M/s Onkareshwar Developers
Location
Gaondevi - Dombivli West, Thane · 421202
Project type
Residential / Group Housing
Registered on
1 Nov 2018
Completion date at registration
December 2025
Latest completion date
September 2026
Delay so far
9 months
Homes
168
Sold or booked
95%
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Balaji Siddhivinayak Complex Building No. 1 B Wing, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Balaji Siddhivinayak Complex Building No 1 B Wing100%100%97%97%

Commencement certificate (CC), as filed on MahaRERA

  • Balaji Siddhivinayak Complex Building No 1 B Wing: covers 25 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Balaji Siddhivinayak Complex Building No. 1 B Wing every month.

Balaji Siddhivinayak Complex Building No. 1 B Wing: buildings, flats and land, as filed on MahaRERA

  • Buildings: Balaji Siddhivinayak Complex Building No 1 B Wing (26 floors, 168 units)
  • Land: 4,610 sq m (about 1.1 acres) · sanctioned built-up 503 sq m
  • Boundaries filed include: Anmol Nagari Complex

The builder’s record and reviews

Sai Balaji Enterprises (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Balaji Siddhivinayak Complex Building No. 1 B Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Balaji Siddhivinayak Complex Building No. 1 B Wing: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Balaji Siddhivinayak Complex Building No. 1 B Wing

What is the possession date of Balaji Siddhivinayak Complex Building No. 1 B Wing?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Balaji Siddhivinayak Complex Building No. 1 B Wing in Gaondevi - Dombivli West, Thane is 30 September 2026 — 9 months later than 30 December 2025, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Balaji Siddhivinayak Complex Building No. 1 B Wing?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Balaji Siddhivinayak Complex Building No. 1 B Wing's builder has filed on MahaRERA, the official one, is 30 September 2026, already 9 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Balaji Siddhivinayak Complex Building No. 1 B Wing extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "The project was registered with the Maharashtra Real Estate Regulatory Authority in November 2018, with an estimated completion timeline up to 30/12/2025. We hereby seek an extension of the project timeline up to 30/09/2026 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The construction of the project has been completed, and the Occupancy Certificate has been obtained as of 25/02/2026. Possession has also been handed over to allottees. All requisite NOCs have been duly submitted by the Promoter, and there are no pending compliances on the part of the Promoter.…".

What is the RERA number of Balaji Siddhivinayak Complex Building No. 1 B Wing?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Balaji Siddhivinayak Complex Building No. 1 B Wing in Gaondevi - Dombivli West, Thane is P51700018430.

Is Balaji Siddhivinayak Complex Building No. 1 B Wing registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing is registered as P51700018430 and its status is "Lapsed (registration period ended)".

What is the construction status of Balaji Siddhivinayak Complex Building No. 1 B Wing?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Balaji Siddhivinayak Complex Building No 1 B Wing is 100% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.

Does Balaji Siddhivinayak Complex Building No. 1 B Wing have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Balaji Siddhivinayak Complex Building No. 1 B Wing safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing is registered on MahaRERA as P51700018430, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 9 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Balaji Siddhivinayak Complex Building No. 1 B Wing's possession date changes?

The latest dates are on Balaji Siddhivinayak Complex Building No. 1 B Wing's MahaRERA page (P51700018430). GharKundli's Kundli Watch sends a free WhatsApp update on Balaji Siddhivinayak Complex Building No. 1 B Wing every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Balaji Siddhivinayak Complex Building No. 1 B Wing have?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing has one building filed: Balaji Siddhivinayak Complex Building No 1 B Wing with 26 floors and 168 units.

How big is the land of Balaji Siddhivinayak Complex Building No. 1 B Wing?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing stands on 4,610 sq m of land (about 1.1 acres), with 503 sq m of sanctioned built-up area.

What is the track record of Balaji Siddhivinayak Complex Building No. 1 B Wing's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Balaji Enterprises (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Balaji Siddhivinayak Complex Building No. 1 B Wing?

Google Maps has reviews of Balaji Siddhivinayak Complex Building No. 1 B Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Balaji Siddhivinayak Complex Building No. 1 B Wing?

Balaji Siddhivinayak Complex Building No. 1 B Wing by M/s Onkareshwar Developers is in Gaondevi - Dombivli West, Thane (pincode 421202), Maharashtra, and is registered on MahaRERA as P51700018430, per GharKundli's check of MahaRERA records. Its boundaries filed there include Anmol Nagari Complex.

How many homes are in Balaji Siddhivinayak Complex Building No. 1 B Wing?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing has 168 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.

When was Balaji Siddhivinayak Complex Building No. 1 B Wing registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Siddhivinayak Complex Building No. 1 B Wing was registered on MahaRERA on 1 November 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Balaji Siddhivinayak Complex Building No. 1 B Wing?

1 court case is listed for Balaji Siddhivinayak Complex Building No. 1 B Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Balaji Siddhivinayak Complex Building No. 1 B Wing?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Onkareshwar Developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Kalyan

All 226 projects in Vishnunagar (421202) →

Other projects by M/s Onkareshwar Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.