by SAI BALAJI ENTERPRISES · Kanchangaon, Thane 421201

What’s in the report? →

Possession date of Balaji Govind (MahaRERA P51700032267): 30 March 2027, moved from 31 December 2025 (11 months later). It has 218 homes (1 BHK and 2 BHK, 372–894 sq ft carpet), 52% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700032267, and currently active. Its completion date has moved from December 2025 to March 2027: 11 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700032267, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Balaji Govind?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Balaji Govind has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 November 2026

    Extended at the builder's request (MahaRERA application EA31122519187)

    Reason the builder gave MahaRERA:
    “1. The project was registered with the Maharashtra Real Estate Regulatory Authority in December 2021, with an estimated completion timeline up to 31/12/2025. 2. We hereby seek an extension of the project timeline up to 31/07/2026 under Sect…” Read the full reason“1. The project was registered with the Maharashtra Real Estate Regulatory Authority in December 2021, with an estimated completion timeline up to 31/12/2025. 2. We hereby seek an extension of the project timeline up to 31/07/2026 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. 3. The construction of the project has been completed, and the Occupancy Certificate has been obtained as of 10/03/2026. Possession has also been handed over to allottees. 4. All requisite NOCs have been duly submitted by the Promoter, and there are no pending compliances on the part of t…”
  3. 30 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Balaji Govind’s extension records on MahaRERA (P51700032267), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Balaji Govind

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700032267
Status
Registered and active
Builder
SAI BALAJI ENTERPRISES
Location
Kanchangaon, Thane · 421201
Project type
Residential / Group Housing
Registered on
22 Dec 2021
Completion date at registration
December 2025
Latest completion date
March 2027
Delay so far
11 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
218
Sold or booked
52%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Balaji Govind, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Balaji Govind-A wing100%100%100%100%
Balaji Govind -B wing100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Balaji Govind-A wing: covers 17 floors
  • Balaji Govind -B wing: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Balaji Govind every 1–2 months.

Balaji Govind: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK372 – 378114
2 BHK501 – 894104
Shops173 – 2267
  • Buildings: Balaji Govind-A wing (17 floors, 127 units) · Balaji Govind -B wing (16 floors, 98 units)
  • Land: 3,080 sq m (about 0.8 acres) · sanctioned built-up 8,956 sq m
  • Land, as filed: Survey No 30/2A PART,30/3A,30/3B,30/4,30/5,30/6
  • Map: Get directions

The builder’s record and reviews

Sai Balaji Enterprises (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Balaji Govind →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Balaji Govind: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Balaji Govind

What is the possession date of Balaji Govind?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Balaji Govind in Kanchangaon, Thane is 30 March 2027 — 11 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 11 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Balaji Govind?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Balaji Govind's builder has filed on MahaRERA, the official one, is 30 March 2027, already 11 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Balaji Govind extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "1. The project was registered with the Maharashtra Real Estate Regulatory Authority in December 2021, with an estimated completion timeline up to 31/12/2025. 2. We hereby seek an extension of the project timeline up to 31/07/2026 under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. 3. The construction of the project has been completed, and the Occupancy Certificate has been obtained as of 10/03/2026. Possession has also been handed over to allottees. 4. All requisite NOCs have been duly submitted by the Promoter, and there are no pending compliances on the part of t…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Balaji Govind?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Balaji Govind in Kanchangaon, Thane is P51700032267.

Is Balaji Govind registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind is registered as P51700032267 and its status is "Registered and active".

What is the current construction status of Balaji Govind? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Balaji Govind have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Balaji Govind safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind is registered on MahaRERA as P51700032267, its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Balaji Govind?

Balaji Govind is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Balaji Govind?

For a flat in Balaji Govind (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Balaji Govind received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind is still under construction, with 30 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Balaji Govind uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Balaji Govind was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Balaji Govind's possession date changes?

The latest dates are on Balaji Govind's MahaRERA page (P51700032267). GharKundli's Kundli Watch sends a free WhatsApp update on Balaji Govind every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Balaji Govind have?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind has 2 buildings filed: Balaji Govind-A wing with 17 floors and 127 units; Balaji Govind -B wing with 16 floors and 98 units.

What are the flat sizes (carpet area) in Balaji Govind?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Balaji Govind: 1 BHK: 372 to 378 sq ft carpet (114 homes); 2 BHK: 501 to 894 sq ft carpet (104 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Balaji Govind?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind stands on 3,080 sq m of land (about 0.8 acres), with 8,956 sq m of sanctioned built-up area.

What is the track record of Balaji Govind's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Balaji Enterprises (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Balaji Govind?

Google Maps has reviews of Balaji Govind written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Balaji Govind?

Balaji Govind by SAI BALAJI ENTERPRISES is in Kanchangaon, Thane, pincode 421201, Maharashtra, and is registered on MahaRERA as P51700032267, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 30/2A PART,30/3A,30/3B,30/4,30/5,30/6. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Balaji Govind, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind has 218 homes in 2 towers registered on MahaRERA, and 52% of them are sold or booked.

When was Balaji Govind registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Govind was registered on MahaRERA on 22 December 2021. GharKundli did not find a title report on the land on file there.

Does Balaji Govind have any legal issues or court cases?

No court cases are listed for Balaji Govind on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Balaji Govind?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI BALAJI ENTERPRISES, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Other projects by SAI BALAJI ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.