Prachi Om Trimurti Darshan

by PRACHI GROUP · Dombivli East, Thane 421201Also near Vishnunagar, ManpadaRegistered on MahaRERA as “OM TRIMURTI DARSHAN”

What’s in the report? →

Possession date of Prachi Om Trimurti Darshan (MahaRERA P51700053133): 30 August 2027, moved from 30 August 2026 (12 months later). It has 35 homes (1 BHK and 2 BHK, 447–598 sq ft carpet), 50% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700053133, and currently active.

Source: MahaRERA website — records for P51700053133, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Prachi Om Trimurti Darshan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Prachi Om Trimurti Darshan has moved

  1. 30 August 2026

    Completion date given when the project was registered

  2. 30 August 2027

    Extended at the builder's request (MahaRERA application EA10092622502)

    Reason the builder gave MahaRERA:
    “Financial constraints, supply chain disruptions and same was affecting booking and secondly, revised CC received on 24th June, 2026, we have applied for correction of project but process got delayed and extension period near to expire and w…” Read the full reason“Financial constraints, supply chain disruptions and same was affecting booking and secondly, revised CC received on 24th June, 2026, we have applied for correction of project but process got delayed and extension period near to expire and we are waiting to approve correction application and thereafter can file extension of project”

Source: Prachi Om Trimurti Darshan’s extension records on MahaRERA (P51700053133), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Prachi Om Trimurti Darshan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700053133
Status
Registered and active
Builder
PRACHI GROUP
Location
Dombivli East, Thane · 421201
Project type
Residential / Group Housing
Registered on
16 Oct 2023
Completion date at registration
August 2026
Latest completion date
August 2027
Delay so far
12 months
Homes
35
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Prachi Om Trimurti Darshan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OM TRIMURTI DARSHAN100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • OM TRIMURTI DARSHAN: covers 7 floors

Latest CC order on MahaRERA: dated 24/02/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prachi Om Trimurti Darshan every 1–2 months.

Prachi Om Trimurti Darshan: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK447 – 48028
2 BHK5987
  • Buildings: OM TRIMURTI DARSHAN (8 floors, 35 units)
  • Car parking: 17 open
  • Land: 835 sq m (about 0.2 acres) · sanctioned built-up 1,939 sq m
  • Land, as filed: S NO 36, H NO 1/R
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Prachi Om Trimurti Darshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prachi Om Trimurti Darshan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Prachi Om Trimurti Darshan

What is the possession date of Prachi Om Trimurti Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prachi Om Trimurti Darshan in Dombivli East, Thane is 30 August 2027 — 12 months later than 30 August 2026, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Prachi Om Trimurti Darshan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prachi Om Trimurti Darshan's builder has filed on MahaRERA, the official one, is 30 August 2027, already 12 months later than the 30 August 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Prachi Om Trimurti Darshan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan's builder applied to MahaRERA to extend the completion date once: to 30 August 2027, giving the reason "Financial constraints, supply chain disruptions and same was affecting booking and secondly, revised CC received on 24th June, 2026, we have applied for correction of project but process got delayed and extension period near to expire and we are waiting to approve correction application and thereafter can file extension of project".

What is the RERA number of Prachi Om Trimurti Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prachi Om Trimurti Darshan in Dombivli East, Thane is P51700053133.

Is Prachi Om Trimurti Darshan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan is registered as P51700053133 and its status is "Registered and active".

What is the current construction status of Prachi Om Trimurti Darshan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on OM TRIMURTI DARSHAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Prachi Om Trimurti Darshan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Prachi Om Trimurti Darshan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan is registered on MahaRERA as P51700053133, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Prachi Om Trimurti Darshan?

Prachi Om Trimurti Darshan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Prachi Om Trimurti Darshan?

For a flat in Prachi Om Trimurti Darshan (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Prachi Om Trimurti Darshan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan is still under construction, with 30 August 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Prachi Om Trimurti Darshan a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Prachi Om Trimurti Darshan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Prachi Om Trimurti Darshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Prachi Om Trimurti Darshan's possession date changes?

The latest dates are on Prachi Om Trimurti Darshan's MahaRERA page (P51700053133). GharKundli's Kundli Watch sends a free WhatsApp update on Prachi Om Trimurti Darshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prachi Om Trimurti Darshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan has one building filed: OM TRIMURTI DARSHAN with 8 floors and 35 units.

What are the flat sizes (carpet area) in Prachi Om Trimurti Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Prachi Om Trimurti Darshan: 1 BHK: 447 to 480 sq ft carpet (28 homes); 2 BHK: 598 sq ft carpet (7 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Prachi Om Trimurti Darshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 17 open car parking spaces for Prachi Om Trimurti Darshan.

How big is the land of Prachi Om Trimurti Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan stands on 835 sq m of land (about 0.2 acres), with 1,939 sq m of sanctioned built-up area.

What are the reviews of Prachi Om Trimurti Darshan?

Google Maps has reviews of Prachi Om Trimurti Darshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Prachi Om Trimurti Darshan?

Prachi Om Trimurti Darshan by PRACHI GROUP is in Dombivli East, Thane, pincode 421201 (near Vishnunagar, Manpada), Maharashtra, and is registered on MahaRERA as P51700053133, per GharKundli's check of MahaRERA records. Its land is filed as S NO 36, H NO 1/R. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Prachi Om Trimurti Darshan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan has 35 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was Prachi Om Trimurti Darshan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prachi Om Trimurti Darshan was registered on MahaRERA on 16 October 2023. GharKundli did not find a title report on the land on file there.

Does Prachi Om Trimurti Darshan have any legal issues or court cases?

No court cases are listed for Prachi Om Trimurti Darshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Prachi Om Trimurti Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRACHI GROUP.

All projects with possession due in 2027 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.