Highland Sky Tower Damani B Building
by PROVIDENCE REALTY LLP · Naupada, Thane 400602Also near Panchpakhadi, Thane West, Bhaskar Colony
What’s in the report? →Possession date of Highland Sky Tower Damani B Building (MahaRERA P51700032859): 30 October 2027, moved from 30 April 2025 (26 months later). It has 150 homes, 11% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700032859, and currently active. Its completion date has moved from April 2025 to October 2027: 26 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700032859, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Highland Sky Tower Damani B Building?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Highland Sky Tower Damani B Building has moved
30 April 2025
Completion date given when the project was registered
30 April 2026
Extended at the builder's request (MahaRERA application EXT51700027461)
Reason the builder gave MahaRERA:
“Self-Explanatory Note on Reasons for Extension of Project HIGHLAND SKY TOWER DAMANI B BUILDING (P51700032859) 1) Financial Constraints:- We wish to inform you that we have transferred the credit facility from Bajaj Housing Finance Ltd.(NBFC…” Read the full reason
“Self-Explanatory Note on Reasons for Extension of Project HIGHLAND SKY TOWER DAMANI B BUILDING (P51700032859) 1) Financial Constraints:- We wish to inform you that we have transferred the credit facility from Bajaj Housing Finance Ltd.(NBFC) to State Bank of India (SBI) under the construction finance scheme. SBI issued the primary sanction letter dated 11th December 2023, which was subject to approval/ratification from the Charity Commissioner as the land belongs to the Charitable Trust. However, due to the approval process from the Charity Commissioner, which took over four months, the dis…”30 June 2027
Extended at the builder's request (MahaRERA application EA24062621506)
Reason the builder gave MahaRERA:
“We, Providence Realty LLP, the promoter of the project Highland Sky Tower Damani B Building (Registration No. P51700032859) under MahaRERA, hereby request an extension of time for completion of the project. We apologize for the delay in the…” Read the full reason
“We, Providence Realty LLP, the promoter of the project Highland Sky Tower Damani B Building (Registration No. P51700032859) under MahaRERA, hereby request an extension of time for completion of the project. We apologize for the delay in the completion of the project and the submission of this request. We respectfully submit that construction work has been carried out in full swing, with quality remaining our primary focus. We have ensured that construction standards are maintained without compromising quality for speed. However, the ongoing slowdown in the real estate sector has adversely a…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Highland Sky Tower Damani B Building’s extension records on MahaRERA (P51700032859), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Highland Sky Tower Damani B Building
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700032859
- Status
- Registered and active
- Builder
- PROVIDENCE REALTY LLP
- Location
- Naupada, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 2 Feb 2022
- Completion date at registration
- April 2025
- Latest completion date
- October 2027
- Delay so far
- 26 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 150
- Sold or booked
- 11%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Highland Sky Tower Damani B Building, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SKY TOWER DAMANI B BUILDING | 100% | 89.63% | 69.36% | 45.04% |
Commencement certificate (CC), as filed on MahaRERA
- SKY TOWER DAMANI B BUILDING: covers 33 (Basement+ Ground + 1st to 6th Podium + 25 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Highland Sky Tower Damani B Building every 1–2 months.
Highland Sky Tower Damani B Building: buildings, flats and land, as filed on MahaRERA
- Buildings: SKY TOWER DAMANI B BUILDING (33 floors, 150 units)
- Car parking: 150 covered
- Land: 8,559 sq m (about 2.1 acres) · sanctioned built-up 13,251 sq m · recreational space 1,773 sq m
- Boundaries filed include: LBS Marg
- Land, as filed: CTS No 15,47,48,49,59,63
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Providence Realty has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 14 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Highland Sky Tower Damani B Building →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Highland Sky Tower Damani B Building: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Highland Sky Tower Damani B Building
What is the possession date of Highland Sky Tower Damani B Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Highland Sky Tower Damani B Building in Naupada, Thane is 30 October 2027 — 26 months later than 30 April 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 26 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Highland Sky Tower Damani B Building?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Highland Sky Tower Damani B Building's builder has filed on MahaRERA, the official one, is 30 October 2027, already 26 months later than the 30 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Highland Sky Tower Damani B Building extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2026, giving the reason "Self-Explanatory Note on Reasons for Extension of Project HIGHLAND SKY TOWER DAMANI B BUILDING (P51700032859) 1) Financial Constraints:- We wish to inform you that we have transferred the credit facility from Bajaj Housing Finance Ltd.(NBFC) to State Bank of India (SBI) under the construction finance scheme. SBI issued the primary sanction letter dated 11th December 2023, which was subject to approval/ratification from the Charity Commissioner as the land belongs to the Charitable Trust. However, due to the approval process from the Charity Commissioner, which took over four months, the dis…"; to 30 June 2027, giving the reason "We, Providence Realty LLP, the promoter of the project Highland Sky Tower Damani B Building (Registration No. P51700032859) under MahaRERA, hereby request an extension of time for completion of the project. We apologize for the delay in the completion of the project and the submission of this request. We respectfully submit that construction work has been carried out in full swing, with quality remaining our primary focus. We have ensured that construction standards are maintained without compromising quality for speed. However, the ongoing slowdown in the real estate sector has adversely a…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Highland Sky Tower Damani B Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Highland Sky Tower Damani B Building in Naupada, Thane is P51700032859.
Is Highland Sky Tower Damani B Building registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building is registered as P51700032859 and its status is "Registered and active".
What is the current construction status of Highland Sky Tower Damani B Building? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SKY TOWER DAMANI B BUILDING is 89.63% done and internal work 69.36%. GharKundli's full report compares construction progress with the deadline.
Does Highland Sky Tower Damani B Building have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Highland Sky Tower Damani B Building safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building is registered on MahaRERA as P51700032859, its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Highland Sky Tower Damani B Building?
Highland Sky Tower Damani B Building is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Highland Sky Tower Damani B Building?
For a flat in Highland Sky Tower Damani B Building (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Highland Sky Tower Damani B Building received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Highland Sky Tower Damani B Building a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building is a redevelopment: 141 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Highland Sky Tower Damani B Building uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Highland Sky Tower Damani B Building was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Highland Sky Tower Damani B Building's possession date changes?
The latest dates are on Highland Sky Tower Damani B Building's MahaRERA page (P51700032859). GharKundli's Kundli Watch sends a free WhatsApp update on Highland Sky Tower Damani B Building every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Highland Sky Tower Damani B Building have?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building has one building filed: SKY TOWER DAMANI B BUILDING with 33 floors and 150 units.
How much parking does Highland Sky Tower Damani B Building have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 150 covered car parking spaces for Highland Sky Tower Damani B Building.
How big is the land of Highland Sky Tower Damani B Building?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building stands on 8,559 sq m of land (about 2.1 acres), with 13,251 sq m of sanctioned built-up area and 1,773 sq m of recreational open space.
What is the track record of Highland Sky Tower Damani B Building's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Providence Realty has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 14 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Highland Sky Tower Damani B Building?
Google Maps has reviews of Highland Sky Tower Damani B Building written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Highland Sky Tower Damani B Building?
Highland Sky Tower Damani B Building by PROVIDENCE REALTY LLP is in Naupada, Thane, pincode 400602 (near Panchpakhadi, Thane West, Bhaskar Colony), Maharashtra, and is registered on MahaRERA as P51700032859, per GharKundli's check of MahaRERA records. Its boundaries filed there include LBS Marg. Its land is filed as CTS No 15,47,48,49,59,63. GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in Highland Sky Tower Damani B Building, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building has 150 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.
When was Highland Sky Tower Damani B Building registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Highland Sky Tower Damani B Building was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.
Does Highland Sky Tower Damani B Building have any legal issues or court cases?
No court cases are listed for Highland Sky Tower Damani B Building on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Highland Sky Tower Damani B Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PROVIDENCE REALTY LLP, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Highland Sky Tower Damani B Building
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Naupada (400602)
- Asavari Co Op HSG Soc LTD
- The Lake Corner
- Platinum Square
- Parvati Niwas
- Rivanta
- Ekatva Crescent
- Pitruchhaya
- Navyug Co.Op.Hsg.Limited
Other projects by PROVIDENCE REALTY LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.