SATGURU SERENITY
by UTSAV DEVELOPERS · Dadar West, MumbaiAlso near Shivaji Park, Matunga, Mahim
Possession date of SATGURU SERENITY: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900055946, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SATGURU SERENITY?
How the possession date of SATGURU SERENITY has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SATGURU SERENITY’s extension records on MahaRERA (P51900055946), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SATGURU SERENITY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900055946
- Status
- Registered and active
- Builder
- UTSAV DEVELOPERS
- Location
- Dadar West, Mumbai · 400028
- Project type
- Others
- Registered on
- 2 May 2024
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 71
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SATGURU SERENITY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SATGURU SERENITY | 95% | 100% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SATGURU SERENITY every month.
SATGURU SERENITY: buildings, flats and land, as filed on MahaRERA
- Buildings: SATGURU SERENITY (15 floors)
- Land: 685 sq m (about 0.2 acres) · sanctioned built-up 2,987 sq m
- Boundaries filed include: R K VAIDYA MARG
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SATGURU SERENITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SATGURU SERENITY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SATGURU SERENITY
What is the possession date of SATGURU SERENITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SATGURU SERENITY in Dadar West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SATGURU SERENITY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SATGURU SERENITY's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SATGURU SERENITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SATGURU SERENITY in Dadar West, Mumbai is P51900055946.
Is SATGURU SERENITY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY is registered as P51900055946 and its status is "Registered and active".
What is the construction status of SATGURU SERENITY?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SATGURU SERENITY is 100% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SATGURU SERENITY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SATGURU SERENITY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY is registered on MahaRERA as P51900055946, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SATGURU SERENITY's possession date changes?
The latest dates are on SATGURU SERENITY's MahaRERA page (P51900055946). GharKundli's Kundli Watch sends a free WhatsApp update on SATGURU SERENITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SATGURU SERENITY have?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY has one building filed: SATGURU SERENITY with 15 floors.
How big is the land of SATGURU SERENITY?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY stands on 685 sq m of land (about 0.2 acres), with 2,987 sq m of sanctioned built-up area.
Where can I read reviews of SATGURU SERENITY?
Google Maps has reviews of SATGURU SERENITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SATGURU SERENITY?
SATGURU SERENITY by UTSAV DEVELOPERS is in Dadar West, Mumbai (pincode 400028), near Shivaji Park, Matunga, Mahim, Maharashtra, and is registered on MahaRERA as P51900055946, per GharKundli's check of MahaRERA records. Its boundaries filed there include R K VAIDYA MARG.
How many homes are in SATGURU SERENITY?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY has 71 homes in 1 tower registered on MahaRERA.
When was SATGURU SERENITY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SATGURU SERENITY was registered on MahaRERA on 2 May 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on SATGURU SERENITY?
No court cases are listed for SATGURU SERENITY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SATGURU SERENITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UTSAV DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SATGURU SERENITY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Dadar West
- ARYAVRAT PROJECT
- YASH TRINITY
- Sigma Garnet
- AHILYA
- VASANT PRABHA
- BUILDARCH SAKURA
- SAI ARADHYA
- SAMARTHA HEIGHTS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.