by QAVI CONSTRUCTION PVT. LTD. · Shahapur, Thane 421601Registered on MahaRERA as “MODEL TOWN”

What’s in the report? →

Possession date of Qavi Model Town (MahaRERA P51700033833): 31 December 2026, moved from 8 February 2026 (10 months later). It has 112 homes, 41% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700033833, and currently active.

Source: MahaRERA website — records for P51700033833, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Qavi Model Town?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Qavi Model Town has moved

  1. 8 February 2026

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA28012619603)

    Reason the builder gave MahaRERA: “1) Delay in government approvals We have received Part Occupancy so we have given possession on basis of part occupancy.”

Source: Qavi Model Town’s extension records on MahaRERA (P51700033833), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Qavi Model Town

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700033833
Status
Registered and active
Builder
QAVI CONSTRUCTION PVT. LTD.
Location
Shahapur, Thane · 421601
Project type
Residential / Group Housing
Registered on
8 Mar 2022
Completion date at registration
February 2026
Latest completion date
December 2026
Delay so far
10 months
Homes
112
Sold or booked
41%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Qavi Model Town, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C TYPE JASMIN BLDG100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • C TYPE JASMIN BLDG: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Qavi Model Town every 1–2 months.

Qavi Model Town: buildings, flats and land, as filed on MahaRERA

  • Buildings: C TYPE JASMIN BLDG (8 floors, 122 units)
  • Car parking: 65 covered, 26 open
  • Land: 6,311 sq m (about 1.6 acres) · sanctioned built-up 6,791 sq m · recreational space 7,667 sq m
  • Land, as filed: 464/1 464/2 467/A(PT)
  • Map: Get directions

The builder’s record and reviews

Qavi Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA.

Read Google reviews of Qavi Model Town →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Qavi Model Town: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Qavi Model Town

What is the possession date of Qavi Model Town?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Qavi Model Town in Shahapur, Thane is 31 December 2026 — 10 months later than 8 February 2026, the date given at registration.

The date has already moved 10 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Qavi Model Town?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Qavi Model Town's builder has filed on MahaRERA, the official one, is 31 December 2026, already 10 months later than the 8 February 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Qavi Model Town extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "1) Delay in government approvals We have received Part Occupancy so we have given possession on basis of part occupancy.".

What is the RERA number of Qavi Model Town?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Qavi Model Town in Shahapur, Thane is P51700033833.

Is Qavi Model Town registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town is registered as P51700033833 and its status is "Registered and active".

What is the current construction status of Qavi Model Town? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town's status on MahaRERA is "Registered and active". As filed by the builder, slab work on C TYPE JASMIN BLDG is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Qavi Model Town have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Qavi Model Town safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town is registered on MahaRERA as P51700033833, its completion date has moved 10 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Qavi Model Town?

Qavi Model Town is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Qavi Model Town?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Qavi Model Town: gharkundli.com/tools/property-cost-calculator

Has Qavi Model Town received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Qavi Model Town uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Qavi Model Town was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Qavi Model Town's possession date changes?

The latest dates are on Qavi Model Town's MahaRERA page (P51700033833). GharKundli's Kundli Watch sends a free WhatsApp update on Qavi Model Town every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Qavi Model Town have?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town has one building filed: C TYPE JASMIN BLDG with 8 floors and 122 units.

How much parking does Qavi Model Town have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 65 covered and 26 open car parking spaces for Qavi Model Town.

How big is the land of Qavi Model Town?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town stands on 6,311 sq m of land (about 1.6 acres), with 6,791 sq m of sanctioned built-up area and 7,667 sq m of recreational open space.

What is the track record of Qavi Model Town's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Qavi Model Town?

Google Maps has reviews of Qavi Model Town written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Qavi Model Town?

Qavi Model Town by QAVI CONSTRUCTION PVT. LTD. is in Shahapur, Thane, pincode 421601, Maharashtra, and is registered on MahaRERA as P51700033833, per GharKundli's check of MahaRERA records. Its land is filed as 464/1 464/2 467/A(PT). GharKundli lists all 184 MahaRERA projects in Shahapur (421601).

How many flats are in Qavi Model Town, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town has 112 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.

When was Qavi Model Town registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Qavi Model Town was registered on MahaRERA on 8 March 2022. GharKundli did not find a title report on the land on file there.

Does Qavi Model Town have any legal issues or court cases?

No court cases are listed for Qavi Model Town on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Qavi Model Town?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is QAVI CONSTRUCTION PVT. LTD., which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Shahapur (421601)

All 184 projects in Shahapur (421601) →

Other projects by QAVI CONSTRUCTION PVT. LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.