Mokashi Maitri Siddha Sadan

by Mokashi Jadhav & Associates · Vishnu nagar, Thane 421202Also near Dombivli West, Dombivli East, NavagaonRegistered on MahaRERA as “Maitri Siddha Sadan”

What’s in the report? →

Possession date of Mokashi Maitri Siddha Sadan (MahaRERA P51700033714): 31 January 2026, moved from 31 January 2025 (12 months later), and it has already passed. It has 17 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700033714. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700033714, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (January 2026) has passed.

What do you want to know about Mokashi Maitri Siddha Sadan?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mokashi Maitri Siddha Sadan has moved

  1. 31 January 2025

    Completion date given when the project was registered

  2. 31 January 2026

    Extended at the builder's request (MahaRERA application EXT51700028329)

    Reason the builder gave MahaRERA: “1) Covid Effect on Luxuries Project 2) Increase in sales unites in near by project radius 3) 0% sales till date (only 4 flat allotment to land owner as per DA)”

Source: Mokashi Maitri Siddha Sadan’s extension records on MahaRERA (P51700033714), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mokashi Maitri Siddha Sadan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700033714
Status
Lapsed (registration period ended)
Builder
Mokashi Jadhav & Associates
Location
Vishnu nagar, Thane · 421202
Project type
Residential / Group Housing
Registered on
8 Mar 2022
Completion date at registration
January 2025
Latest completion date
January 2026
Delay so far
12 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Mokashi Maitri Siddha Sadan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Maitri Siddha Sadan100%95%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mokashi Maitri Siddha Sadan every 1–2 months.

Mokashi Maitri Siddha Sadan: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mokashi Maitri Siddha Sadan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mokashi Maitri Siddha Sadan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mokashi Maitri Siddha Sadan

What is the possession date of Mokashi Maitri Siddha Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mokashi Maitri Siddha Sadan in Vishnu nagar, Thane is 31 January 2026 — 12 months later than 31 January 2025, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Mokashi Maitri Siddha Sadan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mokashi Maitri Siddha Sadan's builder has filed on MahaRERA, the official one, is 31 January 2026, already 12 months later than the 31 January 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mokashi Maitri Siddha Sadan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan's builder applied to MahaRERA to extend the completion date once: to 31 January 2026, giving the reason "1) Covid Effect on Luxuries Project 2) Increase in sales unites in near by project radius 3) 0% sales till date (only 4 flat allotment to land owner as per DA)".

What is the RERA number of Mokashi Maitri Siddha Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mokashi Maitri Siddha Sadan in Vishnu nagar, Thane is P51700033714.

Is Mokashi Maitri Siddha Sadan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan is registered as P51700033714 and its status is "Lapsed (registration period ended)".

What is the current construction status of Mokashi Maitri Siddha Sadan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Maitri Siddha Sadan is 95% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Mokashi Maitri Siddha Sadan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mokashi Maitri Siddha Sadan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan is registered on MahaRERA as P51700033714, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mokashi Maitri Siddha Sadan?

Mokashi Maitri Siddha Sadan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mokashi Maitri Siddha Sadan?

For a flat in Mokashi Maitri Siddha Sadan (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Mokashi Maitri Siddha Sadan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 January 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Mokashi Maitri Siddha Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 January 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Mokashi Maitri Siddha Sadan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mokashi Maitri Siddha Sadan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mokashi Maitri Siddha Sadan's possession date changes?

The latest dates are on Mokashi Maitri Siddha Sadan's MahaRERA page (P51700033714). GharKundli's Kundli Watch sends a free WhatsApp update on Mokashi Maitri Siddha Sadan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mokashi Maitri Siddha Sadan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan has one building filed: Maitri Siddha Sadan with 9 floors.

How big is the land of Mokashi Maitri Siddha Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan stands on 630 sq m of land (about 0.2 acres), with 1,698 sq m of sanctioned built-up area.

What are the reviews of Mokashi Maitri Siddha Sadan?

Google Maps has reviews of Mokashi Maitri Siddha Sadan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mokashi Maitri Siddha Sadan?

Mokashi Maitri Siddha Sadan by Mokashi Jadhav & Associates is in Vishnu nagar, Thane, pincode 421202 (near Dombivli West, Dombivli East, Navagaon), Maharashtra, and is registered on MahaRERA as P51700033714, per GharKundli's check of MahaRERA records. Its land is filed as CTS 2321 to 2325. GharKundli lists all 226 MahaRERA projects in Vishnunagar (421202).

How many flats are in Mokashi Maitri Siddha Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan has 17 homes in 1 tower registered on MahaRERA.

When was Mokashi Maitri Siddha Sadan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mokashi Maitri Siddha Sadan was registered on MahaRERA on 8 March 2022. GharKundli did not find a title report on the land on file there.

Does Mokashi Maitri Siddha Sadan have any legal issues or court cases?

No court cases are listed for Mokashi Maitri Siddha Sadan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Mokashi Maitri Siddha Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mokashi Jadhav & Associates.

All projects with possession due in 2026 in Thane →

Other projects in Vishnunagar (421202)

All 226 projects in Vishnunagar (421202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.