Luxur Devi Heights
by LUXUR AND LAVISH HOMES · Prem Nagar Tekdi, Thane 421005Also near ulhasnagar, Sambhaji Chowk, Netaji ChowkRegistered on MahaRERA as “DEVI HEIGHTS”
What’s in the report? →Possession date of Luxur Devi Heights (MahaRERA P51700034179): 30 October 2027, moved from 30 June 2026 (12 months later). It has 119 homes, 13% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700034179, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700034179, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Luxur Devi Heights?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Luxur Devi Heights has moved
30 June 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA17062621405)
Reason the builder gave MahaRERA:
“The primary reason for the project's delay stems from unforeseen challenges and delays in the procurement of finances from banking partners. Initially, the promoters planned to invest up to ₹5 Crores of their own funds. However, due to dela…” Read the full reason
“The primary reason for the project's delay stems from unforeseen challenges and delays in the procurement of finances from banking partners. Initially, the promoters planned to invest up to ₹5 Crores of their own funds. However, due to delayed bank disbursements, the financial requirements escalated significantly. To prevent the project from stalling, the promoters proactively infused additional capital, investing close to ₹25 Crores, as reflected in the CA Certificate (Form 3) dated April 25, 2026. With these financial hurdles now resolved, the construction is advancing at full force. The…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Luxur Devi Heights’s extension records on MahaRERA (P51700034179), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Luxur Devi Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700034179
- Status
- Registered and active
- Builder
- LUXUR AND LAVISH HOMES
- Location
- Prem Nagar Tekdi, Thane · 421005
- Project type
- Residential / Group Housing
- Registered on
- 25 Mar 2022
- Completion date at registration
- June 2026
- Latest completion date
- October 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 119
- Sold or booked
- 13%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Luxur Devi Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DEVI HEIGHTS WING-A | 100% | 100% | 100% | 45% |
| DEVI HEIGHTS WING-B | 100% | 100% | 100% | 45% |
Commencement certificate (CC), as filed on MahaRERA
- DEVI HEIGHTS WING-A: covers 21 floors
- DEVI HEIGHTS WING-B: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Luxur Devi Heights every 1–2 months.
Luxur Devi Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: DEVI HEIGHTS WING-A (21 floors, 62 units) · DEVI HEIGHTS WING-B (19 floors, 57 units)
- Car parking: 102 covered, 13 open
- Land: 3,571 sq m (about 0.9 acres) · sanctioned built-up 12,854 sq m
- Land, as filed: CHALTA NO 86 87 AND 88 CHALTA NO 242 243/A 243/1 SHEET NO 46 & 47 CTS NO 25978-B 25988-B 25899 25990 25991-B 25992-B 30869 30870 ULHASNAGAR-421005 DIST-THANE
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Luxur Devi Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Luxur Devi Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Luxur Devi Heights
What is the possession date of Luxur Devi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Luxur Devi Heights in Prem Nagar Tekdi, Thane is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Luxur Devi Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Luxur Devi Heights's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Luxur Devi Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "The primary reason for the project's delay stems from unforeseen challenges and delays in the procurement of finances from banking partners. Initially, the promoters planned to invest up to ₹5 Crores of their own funds. However, due to delayed bank disbursements, the financial requirements escalated significantly. To prevent the project from stalling, the promoters proactively infused additional capital, investing close to ₹25 Crores, as reflected in the CA Certificate (Form 3) dated April 25, 2026. With these financial hurdles now resolved, the construction is advancing at full force. The…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Luxur Devi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Luxur Devi Heights in Prem Nagar Tekdi, Thane is P51700034179.
Is Luxur Devi Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights is registered as P51700034179 and its status is "Registered and active".
What is the current construction status of Luxur Devi Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Luxur Devi Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Luxur Devi Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights is registered on MahaRERA as P51700034179, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Luxur Devi Heights?
Luxur Devi Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Luxur Devi Heights?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Luxur Devi Heights: gharkundli.com/tools/property-cost-calculator
Has Luxur Devi Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Luxur Devi Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Luxur Devi Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Luxur Devi Heights's possession date changes?
The latest dates are on Luxur Devi Heights's MahaRERA page (P51700034179). GharKundli's Kundli Watch sends a free WhatsApp update on Luxur Devi Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Luxur Devi Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights has 2 buildings filed: DEVI HEIGHTS WING-A with 21 floors and 62 units; DEVI HEIGHTS WING-B with 19 floors and 57 units.
How much parking does Luxur Devi Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 102 covered and 13 open car parking spaces for Luxur Devi Heights.
How big is the land of Luxur Devi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights stands on 3,571 sq m of land (about 0.9 acres), with 12,854 sq m of sanctioned built-up area.
What are the reviews of Luxur Devi Heights?
Google Maps has reviews of Luxur Devi Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Luxur Devi Heights?
Luxur Devi Heights by LUXUR AND LAVISH HOMES is in Prem Nagar Tekdi, Thane, pincode 421005 (near ulhasnagar, Sambhaji Chowk, Netaji Chowk), Maharashtra, and is registered on MahaRERA as P51700034179, per GharKundli's check of MahaRERA records. Its land is filed as CHALTA NO 86 87 AND 88 CHALTA NO 242 243/A 243/1 SHEET NO 46 & 47 CTS NO 25978-B 25988-B 25899 25990 25991-B 25992-B 30869 30870 ULHASNAGAR-421005 DIST-THANE. GharKundli lists all 20 MahaRERA projects in 421005 (421005).
How many flats are in Luxur Devi Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights has 119 homes in 2 towers registered on MahaRERA, and 13% of them are sold or booked.
When was Luxur Devi Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxur Devi Heights was registered on MahaRERA on 25 March 2022. GharKundli did not find a title report on the land on file there.
Does Luxur Devi Heights have any legal issues or court cases?
No court cases are listed for Luxur Devi Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Luxur Devi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LUXUR AND LAVISH HOMES.
Check it yourself on MahaRERA
- How to check the possession date of Luxur Devi Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ulhasnagar
- Krishna Kunj
- Jannak Residency
- Sai World Legend Phase II
- La Harmony
- Vimal Raj Residency
- Yash Apartment
- Mahadev Heights
- Seagreen Rudra
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.