Hariom Jannak Residency
by HARIOM DEVELOPERS · Opp. Vithalwadi Police station, Thane 421004Registered on MahaRERA as “JANNAK RESIDENCY”
What’s in the report? →Possession date of Hariom Jannak Residency (MahaRERA P51700055689): 31 March 2027, moved from 31 March 2026 (12 months later). It has 47 homes (1 BHK, 2 BHK and Shops, 386–1117 sq ft carpet), 79% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055689, and currently active.
Source: MahaRERA website — records for P51700055689, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Hariom Jannak Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hariom Jannak Residency has moved
31 March 2026
Completion date given when the project was registered
31 July 2026
Extended at the builder's request
31 March 2027
Extended at the builder's request (MahaRERA application EA16092638931)
Reason the builder gave MahaRERA:
“The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over spee…” Read the full reason
“The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.The prime reason for the delay is slow pace of sales during the initial stage of the project. The pace of sales was lower than expected which made management of the cashflows difficult thing. Without sufficient funds due to poor cash flow, we struggled to me…”
Source: Hariom Jannak Residency’s extension records on MahaRERA (P51700055689), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hariom Jannak Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700055689
- Status
- Registered and active
- Builder
- HARIOM DEVELOPERS
- Location
- Opp. Vithalwadi Police station, Thane · 421004
- Project type
- Others
- Registered on
- 8 Apr 2024
- Completion date at registration
- March 2026
- Latest completion date
- March 2027
- Delay so far
- 12 months
- Homes
- 47
- Sold or booked
- 79%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Hariom Jannak Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JANNAK RESIDENCY | 100% | 100% | 60% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- JANNAK RESIDENCY: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hariom Jannak Residency every 1–2 months.
Hariom Jannak Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 498 – 583 | 24 |
| 1 BHK | 386 – 394 | 18 |
| Shops | 632 – 1,117 | 5 |
- Buildings: JANNAK RESIDENCY (8 floors, 47 units)
- Car parking: 22 covered
- Land: 707 sq m (about 0.2 acres) · sanctioned built-up 2,634 sq m
- Boundaries filed include: ROAND AND AMBEDKAR CHOWK
- Land, as filed: 17481, 17482, 17483, 17484, 17485, 17486(B), 17486(C), 17486(D), 17486(E), 17486(F)
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Hariom Jannak Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hariom Jannak Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hariom Jannak Residency
What is the possession date of Hariom Jannak Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hariom Jannak Residency in Opp. Vithalwadi Police station, Thane is 31 March 2027 — 12 months later than 31 March 2026, the date given at registration.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Hariom Jannak Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hariom Jannak Residency's builder has filed on MahaRERA, the official one, is 31 March 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hariom Jannak Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2026; to 31 March 2027, giving the reason "The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.The prime reason for the delay is slow pace of sales during the initial stage of the project. The pace of sales was lower than expected which made management of the cashflows difficult thing. Without sufficient funds due to poor cash flow, we struggled to me…".
What is the RERA number of Hariom Jannak Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hariom Jannak Residency in Opp. Vithalwadi Police station, Thane is P51700055689.
Is Hariom Jannak Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency is registered as P51700055689 and its status is "Registered and active".
What is the current construction status of Hariom Jannak Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on JANNAK RESIDENCY is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does Hariom Jannak Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hariom Jannak Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency is registered on MahaRERA as P51700055689, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hariom Jannak Residency?
Hariom Jannak Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hariom Jannak Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Hariom Jannak Residency: gharkundli.com/tools/property-cost-calculator
Has Hariom Jannak Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency is still under construction, with 31 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Hariom Jannak Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hariom Jannak Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hariom Jannak Residency's possession date changes?
The latest dates are on Hariom Jannak Residency's MahaRERA page (P51700055689). GharKundli's Kundli Watch sends a free WhatsApp update on Hariom Jannak Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hariom Jannak Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency has one building filed: JANNAK RESIDENCY with 8 floors and 47 units.
What are the flat sizes (carpet area) in Hariom Jannak Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Hariom Jannak Residency: 2 BHK: 498 to 583 sq ft carpet (24 homes); 1 BHK: 386 to 394 sq ft carpet (18 homes); Shops: 632 to 1117 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Hariom Jannak Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for Hariom Jannak Residency.
How big is the land of Hariom Jannak Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency stands on 707 sq m of land (about 0.2 acres), with 2,634 sq m of sanctioned built-up area.
What are the reviews of Hariom Jannak Residency?
Google Maps has reviews of Hariom Jannak Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hariom Jannak Residency?
Hariom Jannak Residency by HARIOM DEVELOPERS is in Opp. Vithalwadi Police station, Thane, pincode 421004, Maharashtra, and is registered on MahaRERA as P51700055689, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROAND AND AMBEDKAR CHOWK. Its land is filed as 17481, 17482, 17483, 17484, 17485, 17486(B), 17486(C), 17486(D), 17486(E), 17486(F). GharKundli lists all 68 MahaRERA projects in Ulhasnagar (421004).
How many flats are in Hariom Jannak Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency has 47 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.
When was Hariom Jannak Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hariom Jannak Residency was registered on MahaRERA on 8 April 2024. GharKundli did not find a title report on the land on file there.
Does Hariom Jannak Residency have any legal issues or court cases?
No court cases are listed for Hariom Jannak Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Hariom Jannak Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HARIOM DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Hariom Jannak Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ulhasnagar
- Sai World Legend Phase II
- La Harmony
- Vimal Raj Residency
- Yash Apartment
- Mahadev Heights
- Seagreen Rudra
- Global Heights
- Devi Heights
Other projects by HARIOM DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.