by Universal Infracon · Ulhasnagar, ThaneAlso near Ulhasnagar, Ambernath East

Possession date of Sai Vihar: 31 December 2025, moved from 30 June 2024 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700035140. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Sai Vihar?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Vihar has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 29 June 2025

    Extended at the builder's request (MahaRERA application EXT51700019230)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700028352)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements”

Source: Sai Vihar’s extension records on MahaRERA (P51700035140), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Vihar

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700035140
Status
Lapsed (registration period ended)
Builder
Universal Infracon
Location
Ulhasnagar, Thane · 421003
Project type
Residential / Group Housing
Registered on
10 May 2022
Completion date at registration
June 2024
Latest completion date
December 2025
Delay so far
18 months
Homes
28
Sold or booked
29%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sai Vihar, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sai Vihar100%100%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • Sai Vihar: covers 8 (Ground + Seven Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Vihar every month.

Sai Vihar: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sai Vihar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Vihar: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Vihar

What is the possession date of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Vihar in Ulhasnagar, Thane is 31 December 2025 — 18 months later than 30 June 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sai Vihar?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Vihar's builder has filed on MahaRERA, the official one, is 31 December 2025, already 18 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sai Vihar extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements".

What is the RERA number of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Vihar in Ulhasnagar, Thane is P51700035140.

Is Sai Vihar registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar is registered as P51700035140 and its status is "Lapsed (registration period ended)".

What is the construction status of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Sai Vihar is 100% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does Sai Vihar have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sai Vihar safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar is registered on MahaRERA as P51700035140, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Vihar's possession date changes?

The latest dates are on Sai Vihar's MahaRERA page (P51700035140). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Vihar every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Vihar have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar has one building filed: Sai Vihar with 9 floors and 28 units.

How big is the land of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar stands on 460 sq m of land (about 0.1 acres), with 1,081 sq m of sanctioned built-up area.

Where can I read reviews of Sai Vihar?

Google Maps has reviews of Sai Vihar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Vihar?

Sai Vihar by Universal Infracon is in Ulhasnagar, Thane (pincode 421003), near Ulhasnagar, Ambernath East, Maharashtra, and is registered on MahaRERA as P51700035140, per GharKundli's check of MahaRERA records.

How many homes are in Sai Vihar?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar has 28 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.

When was Sai Vihar registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vihar was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Vihar?

No court cases are listed for Sai Vihar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Universal Infracon.