Bellissimo Matunga -Tower 4 and Tower 5

by Lodha Developers Limited · Sion, Mumbai 400022Also near Bandra East, Dharavi, Vidyanagari

What’s in the report? →

Possession date of Bellissimo Matunga -Tower 4 and Tower 5 (MahaRERA P51900078502): 31 March 2030. It has 290 homes (2 BHK, 3 BHK and 4 BHK, 303–2344 sq ft carpet), 49% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900078502, and currently active.

Source: MahaRERA website — records for P51900078502, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Bellissimo Matunga -Tower 4 and Tower 5?

2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Bellissimo Matunga -Tower 4 and Tower 5

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the March 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900078502
Status
Registered and active
Builder
Lodha Developers Limited
Location
Sion, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
19 Dec 2024
Completion date at registration
March 2030
Homes
290
Sold or booked
49%
Towers
2
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Bellissimo Matunga -Tower 4 and Tower 5, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
T4-Building No 40%0%0%0%
T5-Building No 40%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • T4-Building No 4: covers Plinth Level
  • T5-Building No 4: covers Plinth Level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bellissimo Matunga -Tower 4 and Tower 5 every 1–2 months.

Bellissimo Matunga -Tower 4 and Tower 5: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other303 – 2,344161
2 BHK75362
3 BHK1,17262
4 BHK1,4085
  • Buildings: T4-Building No 4 (39 floors, 141 units) · T5-Building No 4 (39 floors, 149 units)
  • Land: 2,527 sq m (about 0.6 acres) · sanctioned built-up 25,974 sq m · recreational space 123 sq m
  • Land, as filed: C.S.No.6 Part,7 Part,41 Part
  • Map: Get directions

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.

Read Google reviews of Bellissimo Matunga -Tower 4 and Tower 5 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bellissimo Matunga -Tower 4 and Tower 5: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Bellissimo Matunga -Tower 4 and Tower 5

What is the possession date of Bellissimo Matunga -Tower 4 and Tower 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bellissimo Matunga -Tower 4 and Tower 5 in Sion, Mumbai is 31 March 2030.

Is the builder's possession date different from the MahaRERA date for Bellissimo Matunga -Tower 4 and Tower 5?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bellissimo Matunga -Tower 4 and Tower 5's builder has filed on MahaRERA, the official one, is 31 March 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Bellissimo Matunga -Tower 4 and Tower 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bellissimo Matunga -Tower 4 and Tower 5 in Sion, Mumbai is P51900078502.

Is Bellissimo Matunga -Tower 4 and Tower 5 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 is registered as P51900078502 and its status is "Registered and active".

What is the current construction status of Bellissimo Matunga -Tower 4 and Tower 5? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Bellissimo Matunga -Tower 4 and Tower 5 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Bellissimo Matunga -Tower 4 and Tower 5 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 is registered on MahaRERA as P51900078502, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Bellissimo Matunga -Tower 4 and Tower 5?

Bellissimo Matunga -Tower 4 and Tower 5 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Bellissimo Matunga -Tower 4 and Tower 5 are 303 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Bellissimo Matunga -Tower 4 and Tower 5?

For a flat in Bellissimo Matunga -Tower 4 and Tower 5 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Bellissimo Matunga -Tower 4 and Tower 5 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 is still under construction, with 31 March 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Bellissimo Matunga -Tower 4 and Tower 5 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Bellissimo Matunga -Tower 4 and Tower 5 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Bellissimo Matunga -Tower 4 and Tower 5's possession date changes?

The latest dates are on Bellissimo Matunga -Tower 4 and Tower 5's MahaRERA page (P51900078502). GharKundli's Kundli Watch sends a free WhatsApp update on Bellissimo Matunga -Tower 4 and Tower 5 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bellissimo Matunga -Tower 4 and Tower 5 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 has 2 buildings filed: T4-Building No 4 with 39 floors and 141 units; T5-Building No 4 with 39 floors and 149 units.

What are the flat sizes (carpet area) in Bellissimo Matunga -Tower 4 and Tower 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Bellissimo Matunga -Tower 4 and Tower 5: Other: 303 to 2344 sq ft carpet (161 homes); 2 BHK: 753 sq ft carpet (62 homes); 3 BHK: 1172 sq ft carpet (62 homes); 4 BHK: 1408 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Bellissimo Matunga -Tower 4 and Tower 5?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 stands on 2,527 sq m of land (about 0.6 acres), with 25,974 sq m of sanctioned built-up area and 123 sq m of recreational open space.

What is the track record of Bellissimo Matunga -Tower 4 and Tower 5's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Bellissimo Matunga -Tower 4 and Tower 5?

Google Maps has reviews of Bellissimo Matunga -Tower 4 and Tower 5 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Bellissimo Matunga -Tower 4 and Tower 5?

Bellissimo Matunga -Tower 4 and Tower 5 by Lodha Developers Limited is in Sion, Mumbai, pincode 400022 (near Bandra East, Dharavi, Vidyanagari), Maharashtra, and is registered on MahaRERA as P51900078502, per GharKundli's check of MahaRERA records. Its land is filed as C.S.No.6 Part,7 Part,41 Part. GharKundli lists all 98 MahaRERA projects in Sion (400022).

How many flats are in Bellissimo Matunga -Tower 4 and Tower 5, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 has 290 homes in 2 towers registered on MahaRERA, and 49% of them are sold or booked.

When was Bellissimo Matunga -Tower 4 and Tower 5 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Bellissimo Matunga -Tower 4 and Tower 5 was registered on MahaRERA on 19 December 2024. GharKundli did not find a title report on the land on file there.

Does Bellissimo Matunga -Tower 4 and Tower 5 have any legal issues or court cases?

2 court cases are listed for Bellissimo Matunga -Tower 4 and Tower 5 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Bellissimo Matunga -Tower 4 and Tower 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai City →

Other projects in Sion (400022)

All 98 projects in Sion (400022) →

Other projects by Lodha Developers Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.