by RUDRA DEVELOPERS · Mouje Belavali Badlapur West, Thane

Registered on MahaRERA under P51700046028, and currently active. Its completion date has moved from November 2023 to April 2027, 41 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on VASUNDHARA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700046028
Status
Registered and active
Builder
RUDRA DEVELOPERS
Location
Mouje Belavali Badlapur West, Thane · 421503
Project type
Mixed
Registered on
15 Jun 2022
Completion date at registration
November 2023
Latest completion date
April 2027
Delay so far
41 months
Homes
117
Sold or booked
2%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Kundli Watch

VASUNDHARA: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about VASUNDHARA

Is VASUNDHARA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VASUNDHARA is registered as P51700046028 and its status is "Registered and active".

Where is VASUNDHARA?

VASUNDHARA by RUDRA DEVELOPERS is in Mouje Belavali Badlapur West, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700046028, per GharKundli's check of MahaRERA records.

When is possession of VASUNDHARA due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VASUNDHARA in Mouje Belavali Badlapur West, Thane is 30 April 2027 — 41 months later than 30 November 2023, the date given at registration.

Does VASUNDHARA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of VASUNDHARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUDRA DEVELOPERS, which has 11 other projects registered on MahaRERA.

Other projects in pincode 421503

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.