GharKundli

DILKAP GRANDEUR

by DILIP ESTATE & TOWN PLANNERS PVT LTD · Powai, MumbaiAlso near Ballard Estate, Nahar Amrit Shakti, Chandivali

Possession date of DILKAP GRANDEUR: 30 November 2026, moved from 30 June 2023 (37 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900006119, and currently active. Its completion date has moved from June 2023 to November 2026: 37 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DILKAP GRANDEUR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DILKAP GRANDEUR has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51900016990)

    Reason the builder gave MahaRERA:
    “Long pending permissions and amendments have been sought from the concerned departments which took time for due diligence. More than 90% Commencement Certificate has been recently procured and super structure is underway. Complete construct…” Read the full reason“Long pending permissions and amendments have been sought from the concerned departments which took time for due diligence. More than 90% Commencement Certificate has been recently procured and super structure is underway. Complete construction including finishing and other permissions for getting Occupation Certificate will require an extension period up to 12 months.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900024331)

    Reason the builder gave MahaRERA:
    “95% of super structure is complete with internal finishings ongoing including lifts etc. Part Occupation Certificate application will be underway. Complete process and due diligence with permissions from various authorities will take its du…” Read the full reason“95% of super structure is complete with internal finishings ongoing including lifts etc. Part Occupation Certificate application will be underway. Complete process and due diligence with permissions from various authorities will take its due course.”
  4. 31 July 2026

    Extended at the builder's request (MahaRERA application EA26082502448)

    Reason the builder gave MahaRERA:
    “A major contributing factor to the delay has been the prolonged due diligence and scrutiny process from the Brihanmumbai Municipal Corporation (BMC) and other concerned authorities. Although the CFO Final Plan has been sanctioned, our file…” Read the full reason“A major contributing factor to the delay has been the prolonged due diligence and scrutiny process from the Brihanmumbai Municipal Corporation (BMC) and other concerned authorities. Although the CFO Final Plan has been sanctioned, our file is currently under review by the Scrutiny Department of BMC for final approval. Unfortunately, this process has been significantly delayed despite our repeated follow-ups, leading to considerable setbacks in our execution timelines”
  5. 30 November 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DILKAP GRANDEUR’s extension records on MahaRERA (P51900006119), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DILKAP GRANDEUR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900006119
Status
Registered and active
Builder
DILIP ESTATE & TOWN PLANNERS PVT LTD
Location
Powai, Mumbai · 400076
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
June 2023
Latest completion date
November 2026
Delay so far
37 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
67%
Towers
1
Complaints on MahaRERA
9
Court cases listed
0
Appeals at the tribunal
6
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of DILKAP GRANDEUR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DILKAP GRANDEUR100%100%91%10%

Commencement certificate (CC), as filed on MahaRERA

  • DILKAP GRANDEUR: covers Ground+16 floor (A wing), Ground+16 floor (C wing)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DILKAP GRANDEUR every month.

DILKAP GRANDEUR: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,275 – 1,43524
4 BHK2,305 – 2,65016
Other2,340 – 2,3502
  • Buildings: DILKAP GRANDEUR (34 floors, 42 units)
  • Land: 3,853 sq m (about 1.0 acres) · sanctioned built-up 4,473 sq m · recreational space 769 sq m
  • Boundaries filed include: CANARA BANK QUATERS
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Gorkap Properties & Investments (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 50 months); 3 still being built, 3 past the promised date (typically 24 months late). 13 complaints on MahaRERA across 3 projects.

Read Google reviews of DILKAP GRANDEUR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DILKAP GRANDEUR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DILKAP GRANDEUR

What is the possession date of DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DILKAP GRANDEUR in Powai, Mumbai is 30 November 2026 — 37 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DILKAP GRANDEUR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DILKAP GRANDEUR's builder has filed on MahaRERA, the official one, is 30 November 2026, already 37 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DILKAP GRANDEUR extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2024, giving the reason "Long pending permissions and amendments have been sought from the concerned departments which took time for due diligence. More than 90% Commencement Certificate has been recently procured and super structure is underway. Complete construction including finishing and other permissions for getting Occupation Certificate will require an extension period up to 12 months."; to 30 June 2025, giving the reason "95% of super structure is complete with internal finishings ongoing including lifts etc. Part Occupation Certificate application will be underway. Complete process and due diligence with permissions from various authorities will take its due course."; to 31 July 2026, giving the reason "A major contributing factor to the delay has been the prolonged due diligence and scrutiny process from the Brihanmumbai Municipal Corporation (BMC) and other concerned authorities. Although the CFO Final Plan has been sanctioned, our file is currently under review by the Scrutiny Department of BMC for final approval. Unfortunately, this process has been significantly delayed despite our repeated follow-ups, leading to considerable setbacks in our execution timelines". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DILKAP GRANDEUR in Powai, Mumbai is P51900006119.

Is DILKAP GRANDEUR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR is registered as P51900006119 and its status is "Registered and active".

What is the construction status of DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DILKAP GRANDEUR is 100% done and internal work 91%. GharKundli's full report compares construction progress with the deadline.

Does DILKAP GRANDEUR have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is DILKAP GRANDEUR safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR is registered on MahaRERA as P51900006119, its completion date has moved 37 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DILKAP GRANDEUR's possession date changes?

The latest dates are on DILKAP GRANDEUR's MahaRERA page (P51900006119). GharKundli's Kundli Watch sends a free WhatsApp update on DILKAP GRANDEUR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DILKAP GRANDEUR have?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR has one building filed: DILKAP GRANDEUR with 34 floors and 42 units.

What are the flat sizes (carpet area) in DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DILKAP GRANDEUR: 3 BHK: 1275 to 1435 sq ft carpet (24 homes); 4 BHK: 2305 to 2650 sq ft carpet (16 homes); Other: 2340 to 2350 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR stands on 3,853 sq m of land (about 1.0 acres), with 4,473 sq m of sanctioned built-up area and 769 sq m of recreational open space.

What is the track record of DILKAP GRANDEUR's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Gorkap Properties & Investments (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 50 months); 3 still being built, 3 past the promised date (typically 24 months late). 13 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DILKAP GRANDEUR?

Google Maps has reviews of DILKAP GRANDEUR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DILKAP GRANDEUR?

DILKAP GRANDEUR by DILIP ESTATE & TOWN PLANNERS PVT LTD is in Powai, Mumbai (pincode 400076), near Ballard Estate, Nahar Amrit Shakti, Chandivali, Maharashtra, and is registered on MahaRERA as P51900006119, per GharKundli's check of MahaRERA records. Its boundaries filed there include CANARA BANK QUATERS.

How many homes are in DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR has 42 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.

When was DILKAP GRANDEUR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP GRANDEUR was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on DILKAP GRANDEUR?

No court cases are listed for DILKAP GRANDEUR on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of DILKAP GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DILIP ESTATE & TOWN PLANNERS PVT LTD, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400076

All 49 projects in Powai (400076) →

Other projects by DILIP ESTATE & TOWN PLANNERS PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.