MAKSKAP CENTRE
by DILIP ESTATE & TOWN PLANNERS PVT LTD · Sakinaka, MumbaiAlso near Andheri West, Ambivali West, Jogeshwari West
Possession: MAKSKAP CENTRE is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900009030. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MAKSKAP CENTRE?
How the possession date of MAKSKAP CENTRE has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51900003985)
Reason the builder gave MahaRERA: “Change in policies and guidelines of M. C. G. M. and interference by Owners family by way of complaints and disputes”
31 December 2022
Extended at the builder's request (MahaRERA application EXT51900012237)
Reason the builder gave MahaRERA:
“MAKHARIA FAMILY (CO-PROMOTERS & LANDOWNERS INTERNAL FAMILY DISPUTE) HAD MADE MANY FALSE COMPLAINTS TO MCGM AND CONCERNED AUTHORITIES ALONG WITH LEGAL DEPARTMENT OF MCGM. TO GET THE CLEAR SANCTIONS WHICH TOOK GREAT DEAL OF TIME FURTHER TO WH…” Read the full reason
“MAKHARIA FAMILY (CO-PROMOTERS & LANDOWNERS INTERNAL FAMILY DISPUTE) HAD MADE MANY FALSE COMPLAINTS TO MCGM AND CONCERNED AUTHORITIES ALONG WITH LEGAL DEPARTMENT OF MCGM. TO GET THE CLEAR SANCTIONS WHICH TOOK GREAT DEAL OF TIME FURTHER TO WHICH MCGM HAS BEEN DELAYING TO CLEAR & GIVE THE OC.”31 August 2024
Extended at the builder's request (MahaRERA application EXT51900013774)
Reason the builder gave MahaRERA:
“MAKHARIA FAMILY (CO PROMOTERS) & LAND OWNERS HAVE AN INTERNAL FAMILY DISPUTE WHICH STILL CONTINUES. A FEW OF THESE MEMBERS MADE MANY FALSE COMPLAINTS TO BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO LEGAL DEPARTMENT OF BMC TO GET…” Read the full reason
“MAKHARIA FAMILY (CO PROMOTERS) & LAND OWNERS HAVE AN INTERNAL FAMILY DISPUTE WHICH STILL CONTINUES. A FEW OF THESE MEMBERS MADE MANY FALSE COMPLAINTS TO BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO LEGAL DEPARTMENT OF BMC TO GET THE CLEAR SANCTIONS FOR FINAL OC APPROVAL WHICH IS STILL TAKING GREAT DEAL OF TIME. BMC HAS BEEN PROLONGING TO CLEAR & GIVE THE FINAL OC & BCC.”
Source: MAKSKAP CENTRE’s extension records on MahaRERA (P51900009030), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MAKSKAP CENTRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 1 court case, and how it ended
- Construction pace against the August 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900009030
- Status
- Completed
- Builder
- DILIP ESTATE & TOWN PLANNERS PVT LTD
- Location
- Sakinaka, Mumbai · 400053
- Project type
- Commercial
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- August 2024
- Delay so far
- 56 months
- Homes
- 35
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of MAKSKAP CENTRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MAKSKAP CENTRE | 100% | 100% | 95% | 98% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAKSKAP CENTRE every month.
MAKSKAP CENTRE: buildings, flats and land, as filed on MahaRERA
- Buildings: MAKSKAP CENTRE (8 floors)
- Land: 1,021 sq m (about 0.3 acres) · sanctioned built-up 1,940 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Gorkap Properties & Investments (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 50 months); 3 still being built, 3 past the promised date (typically 24 months late). 13 complaints on MahaRERA across 3 projects.
Read Google reviews of MAKSKAP CENTRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MAKSKAP CENTRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MAKSKAP CENTRE
What is the possession date of MAKSKAP CENTRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAKSKAP CENTRE in Sakinaka, Mumbai is 31 August 2024 — 56 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for MAKSKAP CENTRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MAKSKAP CENTRE's builder has filed on MahaRERA, the official one, is 31 August 2024, already 56 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MAKSKAP CENTRE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "Change in policies and guidelines of M. C. G. M. and interference by Owners family by way of complaints and disputes"; to 31 December 2022, giving the reason "MAKHARIA FAMILY (CO-PROMOTERS & LANDOWNERS INTERNAL FAMILY DISPUTE) HAD MADE MANY FALSE COMPLAINTS TO MCGM AND CONCERNED AUTHORITIES ALONG WITH LEGAL DEPARTMENT OF MCGM. TO GET THE CLEAR SANCTIONS WHICH TOOK GREAT DEAL OF TIME FURTHER TO WHICH MCGM HAS BEEN DELAYING TO CLEAR & GIVE THE OC."; to 31 August 2024, giving the reason "MAKHARIA FAMILY (CO PROMOTERS) & LAND OWNERS HAVE AN INTERNAL FAMILY DISPUTE WHICH STILL CONTINUES. A FEW OF THESE MEMBERS MADE MANY FALSE COMPLAINTS TO BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO LEGAL DEPARTMENT OF BMC TO GET THE CLEAR SANCTIONS FOR FINAL OC APPROVAL WHICH IS STILL TAKING GREAT DEAL OF TIME. BMC HAS BEEN PROLONGING TO CLEAR & GIVE THE FINAL OC & BCC.".
What is the RERA number of MAKSKAP CENTRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAKSKAP CENTRE in Sakinaka, Mumbai is P51900009030.
Is MAKSKAP CENTRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE is registered as P51900009030 and its status is "Completed".
What is the construction status of MAKSKAP CENTRE?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE's status on MahaRERA is "Completed". As filed by the builder, slab work on MAKSKAP CENTRE is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does MAKSKAP CENTRE have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MAKSKAP CENTRE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE is registered on MahaRERA as P51900009030, its MahaRERA status is "Completed", its completion date has moved 56 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MAKSKAP CENTRE's possession date changes?
The latest dates are on MAKSKAP CENTRE's MahaRERA page (P51900009030). GharKundli's Kundli Watch sends a free WhatsApp update on MAKSKAP CENTRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MAKSKAP CENTRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE has one building filed: MAKSKAP CENTRE with 8 floors.
How big is the land of MAKSKAP CENTRE?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE stands on 1,021 sq m of land (about 0.3 acres), with 1,940 sq m of sanctioned built-up area.
What is the track record of MAKSKAP CENTRE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gorkap Properties & Investments (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 50 months); 3 still being built, 3 past the promised date (typically 24 months late). 13 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MAKSKAP CENTRE?
Google Maps has reviews of MAKSKAP CENTRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MAKSKAP CENTRE?
MAKSKAP CENTRE by DILIP ESTATE & TOWN PLANNERS PVT LTD is in Sakinaka, Mumbai (pincode 400053), near Andheri West, Ambivali West, Jogeshwari West, Maharashtra, and is registered on MahaRERA as P51900009030, per GharKundli's check of MahaRERA records.
How many homes are in MAKSKAP CENTRE?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE has 35 homes in 1 tower registered on MahaRERA.
When was MAKSKAP CENTRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MAKSKAP CENTRE was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MAKSKAP CENTRE?
1 court case is listed for MAKSKAP CENTRE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MAKSKAP CENTRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DILIP ESTATE & TOWN PLANNERS PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MAKSKAP CENTRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Sakinaka
- CRESCENT WTC T2 PHASE II
- 72 CORP
- EXPRESS ENCLAVE
- Paramount
- RED ROSE CO-OPERATIVE HOUSING SOCIETY
- SBIEs Geetanjali CHSL
Other projects by DILIP ESTATE & TOWN PLANNERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.