Vidisha Shambhu Shankar Residency
by VIDISHA CONSTRUCTIONS · Bhadwad, Thane 421305Registered on MahaRERA as “SHAMBHU SHANKAR RESIDENCY”
What’s in the report? →Possession date of Vidisha Shambhu Shankar Residency (MahaRERA P51700046454): 20 April 2027, moved from 31 December 2024 (24 months later). It has 253 homes, 80% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700046454, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700046454, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vidisha Shambhu Shankar Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vidisha Shambhu Shankar Residency has moved
31 December 2024
Completion date given when the project was registered
20 December 2025
Extended at the builder's request (MahaRERA application EXT51700025666)
Reason the builder gave MahaRERA:
“SLOW SALES, INCREASED COST OF MATERIAL, SHORTAGE OF LABOUR. AS PER CIRCULAR NO 28 DATED 22/07/2021 51% CONSENT IS REQUIRED FOR EXTENSION UNDER SECTION 7(3) AND WE HAVE OBTAINED CONSENT OF 53.27% OF ALLOTTES WHICH IS MORE THAN REQUIRED PERCE…” Read the full reason
“SLOW SALES, INCREASED COST OF MATERIAL, SHORTAGE OF LABOUR. AS PER CIRCULAR NO 28 DATED 22/07/2021 51% CONSENT IS REQUIRED FOR EXTENSION UNDER SECTION 7(3) AND WE HAVE OBTAINED CONSENT OF 53.27% OF ALLOTTES WHICH IS MORE THAN REQUIRED PERCENTAGE, RESOLUTION IS ALREADY UPLOADED IN RESOLUTION TAB . SO PLESE PROCESS OUR APPLICATION AT THE EARLIEST. OUR CUSTOMER LOAN DISBURSEMENT IS PENDING ON THAT ACCOUNT. PLEASE PROCEED AND OBLIGE.”20 December 2026
Extended at the builder's request (MahaRERA application EA03122518516)
Reason the builder gave MahaRERA:
“Delays in the delivery of construction materials (e.g., steel, lumber, cement). Price volatility and shortages of key materials lead to project delays, as we wait for resources to arrive.There was a lack of skilled labour, especially in spe…” Read the full reason
“Delays in the delivery of construction materials (e.g., steel, lumber, cement). Price volatility and shortages of key materials lead to project delays, as we wait for resources to arrive.There was a lack of skilled labour, especially in specialized fields like electrical work,plumbing has slow down progress on construction sites. Labour shortages is the main reason during festive seasons, which create seasonal work fluctuations and sudden disruptions in project.”20 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vidisha Shambhu Shankar Residency’s extension records on MahaRERA (P51700046454), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vidisha Shambhu Shankar Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700046454
- Status
- Registered and active
- Builder
- VIDISHA CONSTRUCTIONS
- Location
- Bhadwad, Thane · 421305
- Project type
- Others
- Registered on
- 4 Aug 2022
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 253
- Sold or booked
- 80%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Vidisha Shambhu Shankar Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHAMBHU SHANKAR RESIDENCY | 100% | 100% | 80% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHAMBHU SHANKAR RESIDENCY: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vidisha Shambhu Shankar Residency every 1–2 months.
Vidisha Shambhu Shankar Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: SHAMBHU SHANKAR RESIDENCY (14 floors, 272 units)
- Car parking: 37 covered
- Land: 3,213 sq m (about 0.8 acres) · sanctioned built-up 12,850 sq m
- Land, as filed: SURVEY NO 69 HISSA NO 1/1
- Map: Get directions
The builder’s record and reviews
Vidisha Constructions has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 23 months late). No complaints on MahaRERA.
Read Google reviews of Vidisha Shambhu Shankar Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vidisha Shambhu Shankar Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vidisha Shambhu Shankar Residency
What is the possession date of Vidisha Shambhu Shankar Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vidisha Shambhu Shankar Residency in Bhadwad, Thane is 20 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vidisha Shambhu Shankar Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vidisha Shambhu Shankar Residency's builder has filed on MahaRERA, the official one, is 20 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vidisha Shambhu Shankar Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency's builder applied to MahaRERA to extend the completion date 2 times: to 20 December 2025, giving the reason "SLOW SALES, INCREASED COST OF MATERIAL, SHORTAGE OF LABOUR. AS PER CIRCULAR NO 28 DATED 22/07/2021 51% CONSENT IS REQUIRED FOR EXTENSION UNDER SECTION 7(3) AND WE HAVE OBTAINED CONSENT OF 53.27% OF ALLOTTES WHICH IS MORE THAN REQUIRED PERCENTAGE, RESOLUTION IS ALREADY UPLOADED IN RESOLUTION TAB . SO PLESE PROCESS OUR APPLICATION AT THE EARLIEST. OUR CUSTOMER LOAN DISBURSEMENT IS PENDING ON THAT ACCOUNT. PLEASE PROCEED AND OBLIGE."; to 20 December 2026, giving the reason "Delays in the delivery of construction materials (e.g., steel, lumber, cement). Price volatility and shortages of key materials lead to project delays, as we wait for resources to arrive.There was a lack of skilled labour, especially in specialized fields like electrical work,plumbing has slow down progress on construction sites. Labour shortages is the main reason during festive seasons, which create seasonal work fluctuations and sudden disruptions in project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vidisha Shambhu Shankar Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vidisha Shambhu Shankar Residency in Bhadwad, Thane is P51700046454.
Is Vidisha Shambhu Shankar Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency is registered as P51700046454 and its status is "Registered and active".
What is the current construction status of Vidisha Shambhu Shankar Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHAMBHU SHANKAR RESIDENCY is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does Vidisha Shambhu Shankar Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vidisha Shambhu Shankar Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency is registered on MahaRERA as P51700046454, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vidisha Shambhu Shankar Residency?
Vidisha Shambhu Shankar Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vidisha Shambhu Shankar Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vidisha Shambhu Shankar Residency: gharkundli.com/tools/property-cost-calculator
Has Vidisha Shambhu Shankar Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency is still under construction, with 20 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vidisha Shambhu Shankar Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vidisha Shambhu Shankar Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vidisha Shambhu Shankar Residency's possession date changes?
The latest dates are on Vidisha Shambhu Shankar Residency's MahaRERA page (P51700046454). GharKundli's Kundli Watch sends a free WhatsApp update on Vidisha Shambhu Shankar Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vidisha Shambhu Shankar Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency has one building filed: SHAMBHU SHANKAR RESIDENCY with 14 floors and 272 units.
How much parking does Vidisha Shambhu Shankar Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 37 covered car parking spaces for Vidisha Shambhu Shankar Residency.
How big is the land of Vidisha Shambhu Shankar Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency stands on 3,213 sq m of land (about 0.8 acres), with 12,850 sq m of sanctioned built-up area.
What is the track record of Vidisha Shambhu Shankar Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Constructions has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 23 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vidisha Shambhu Shankar Residency?
Google Maps has reviews of Vidisha Shambhu Shankar Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vidisha Shambhu Shankar Residency?
Vidisha Shambhu Shankar Residency by VIDISHA CONSTRUCTIONS is in Bhadwad, Thane, pincode 421305, Maharashtra, and is registered on MahaRERA as P51700046454, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 69 HISSA NO 1/1. GharKundli lists all 13 MahaRERA projects in Bhiwandi (421305).
How many flats are in Vidisha Shambhu Shankar Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency has 253 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.
When was Vidisha Shambhu Shankar Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shambhu Shankar Residency was registered on MahaRERA on 4 August 2022. GharKundli did not find a title report on the land on file there.
Does Vidisha Shambhu Shankar Residency have any legal issues or court cases?
No court cases are listed for Vidisha Shambhu Shankar Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vidisha Shambhu Shankar Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIDISHA CONSTRUCTIONS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vidisha Shambhu Shankar Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi (421305)
- Arihant City Phase-ii - N Building
- Arihant City Phase-ii - M Building
- L M Tower
- Arihant City Phase-ii - P Building
- Arihant City Phase-ii - A Building
- Arihant City Phase-ii - B Building
- Arihant City Phase-ii - C Building
- Arihant City Phase-ii - L Building
Other projects by VIDISHA CONSTRUCTIONS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.