Vidisha Shiv Sai Awas

by VIDISHA CONSTRUCTIONS · Bhadwad Bhiwandi, Thane 421305Registered on MahaRERA as “SHIV SAI AWAS”

What’s in the report? →

Possession date of Vidisha Shiv Sai Awas (MahaRERA P51700031081): 20 April 2027, moved from 31 March 2024 (33 months later). It has 316 homes, 94% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031081, and currently active. Its completion date has moved from March 2024 to April 2027: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700031081, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vidisha Shiv Sai Awas?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vidisha Shiv Sai Awas has moved

  1. 31 March 2024

    Completion date given when the project was registered

  2. 20 March 2025

    Extended at the builder's request (MahaRERA application EXT51700018282)

    Reason the builder gave MahaRERA: “DUE TO SHORTAGE OF LABOUR, INCREAE IN COST OF CONSTRUCTION MATERIAL, SLOW SALES WE NEED EXTENSION TILL 20 MARCH 2025”
  3. 20 March 2026

    Extended at the builder's request (MahaRERA application EA17072502090)

    Reason the builder gave MahaRERA: “Due to slow booking of Flats at our project, Shortage of Labour/Manpower and lncrease rate of materials.”
  4. 20 December 2026

    Extended at the builder's request (MahaRERA application EA13062621361)

    Reason the builder gave MahaRERA: “FULL OCCUPATION CERTIFICATE IS RECEIVED AS ON DATED 09 APRIL 2026, CERTIFICATE NO. EE/BP/PMAY/A/MHADA/E-8776265/2026 FROM MHADA.”
  5. 20 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vidisha Shiv Sai Awas’s extension records on MahaRERA (P51700031081), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vidisha Shiv Sai Awas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700031081
Status
Registered and active
Builder
VIDISHA CONSTRUCTIONS
Location
Bhadwad Bhiwandi, Thane · 421305
Project type
Residential / Group Housing
Registered on
5 Oct 2021
Completion date at registration
March 2024
Latest completion date
April 2027
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
316
Sold or booked
94%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Vidisha Shiv Sai Awas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIV SAI AWAS BUILDING A100%100%100%100%
SHIV SAI AWAS BUILDING B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SHIV SAI AWAS BUILDING A: covers 15 floors
  • SHIV SAI AWAS BUILDING B: covers 15 floors

Latest CC order on MahaRERA: dated 12/06/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vidisha Shiv Sai Awas every 1–2 months.

Vidisha Shiv Sai Awas: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHIV SAI AWAS BUILDING A (15 floors, 166 units) · SHIV SAI AWAS BUILDING B (15 floors, 150 units)
  • Car parking: 26 covered, 6 open
  • Land: 5,117 sq m (about 1.3 acres) · sanctioned built-up 14,850 sq m · recreational space 450 sq m
  • Land, as filed: S.NO 5/1 S.NO 69/1/1 S,NO. 9
  • Map: Get directions

The builder’s record and reviews

Vidisha Constructions has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 23 months late). No complaints on MahaRERA.

Read Google reviews of Vidisha Shiv Sai Awas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vidisha Shiv Sai Awas: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vidisha Shiv Sai Awas

What is the possession date of Vidisha Shiv Sai Awas?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vidisha Shiv Sai Awas in Bhadwad Bhiwandi, Thane is 20 April 2027 — 33 months later than 31 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vidisha Shiv Sai Awas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vidisha Shiv Sai Awas's builder has filed on MahaRERA, the official one, is 20 April 2027, already 33 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vidisha Shiv Sai Awas extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas's builder applied to MahaRERA to extend the completion date 3 times: to 20 March 2025, giving the reason "DUE TO SHORTAGE OF LABOUR, INCREAE IN COST OF CONSTRUCTION MATERIAL, SLOW SALES WE NEED EXTENSION TILL 20 MARCH 2025"; to 20 March 2026, giving the reason "Due to slow booking of Flats at our project, Shortage of Labour/Manpower and lncrease rate of materials."; to 20 December 2026, giving the reason "FULL OCCUPATION CERTIFICATE IS RECEIVED AS ON DATED 09 APRIL 2026, CERTIFICATE NO. EE/BP/PMAY/A/MHADA/E-8776265/2026 FROM MHADA.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Vidisha Shiv Sai Awas?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vidisha Shiv Sai Awas in Bhadwad Bhiwandi, Thane is P51700031081.

Is Vidisha Shiv Sai Awas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas is registered as P51700031081 and its status is "Registered and active".

What is the current construction status of Vidisha Shiv Sai Awas? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Vidisha Shiv Sai Awas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vidisha Shiv Sai Awas safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas is registered on MahaRERA as P51700031081, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vidisha Shiv Sai Awas?

Vidisha Shiv Sai Awas is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vidisha Shiv Sai Awas?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vidisha Shiv Sai Awas: gharkundli.com/tools/property-cost-calculator

Has Vidisha Shiv Sai Awas received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas is still under construction, with 20 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Vidisha Shiv Sai Awas uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vidisha Shiv Sai Awas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vidisha Shiv Sai Awas's possession date changes?

The latest dates are on Vidisha Shiv Sai Awas's MahaRERA page (P51700031081). GharKundli's Kundli Watch sends a free WhatsApp update on Vidisha Shiv Sai Awas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vidisha Shiv Sai Awas have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas has 2 buildings filed: SHIV SAI AWAS BUILDING A with 15 floors and 166 units; SHIV SAI AWAS BUILDING B with 15 floors and 150 units.

How much parking does Vidisha Shiv Sai Awas have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered and 6 open car parking spaces for Vidisha Shiv Sai Awas.

How big is the land of Vidisha Shiv Sai Awas?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas stands on 5,117 sq m of land (about 1.3 acres), with 14,850 sq m of sanctioned built-up area and 450 sq m of recreational open space.

What is the track record of Vidisha Shiv Sai Awas's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Constructions has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 23 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vidisha Shiv Sai Awas?

Google Maps has reviews of Vidisha Shiv Sai Awas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vidisha Shiv Sai Awas?

Vidisha Shiv Sai Awas by VIDISHA CONSTRUCTIONS is in Bhadwad Bhiwandi, Thane, pincode 421305, Maharashtra, and is registered on MahaRERA as P51700031081, per GharKundli's check of MahaRERA records. Its land is filed as S.NO 5/1 S.NO 69/1/1 S,NO. 9. GharKundli lists all 13 MahaRERA projects in Bhiwandi (421305).

How many flats are in Vidisha Shiv Sai Awas, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas has 316 homes in 2 towers registered on MahaRERA, and 94% of them are sold or booked.

When was Vidisha Shiv Sai Awas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidisha Shiv Sai Awas was registered on MahaRERA on 5 October 2021. GharKundli did not find a title report on the land on file there.

Does Vidisha Shiv Sai Awas have any legal issues or court cases?

No court cases are listed for Vidisha Shiv Sai Awas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vidisha Shiv Sai Awas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIDISHA CONSTRUCTIONS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi

All 13 projects in Bhiwandi (421305) →

Other projects by VIDISHA CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.