Sai Deep Residency
by KISHOR RATAN CHAUDHARY · Village Kamatghar, Thane 421302
What’s in the report? →Possession date of Sai Deep Residency (MahaRERA P51700051285): 30 April 2027, moved from 31 December 2024 (24 months later). It has 30 homes (1 BHK, 348–418 sq ft carpet), 91% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700051285, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700051285, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sai Deep Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sai Deep Residency has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EA02072501929)
Reason the builder gave MahaRERA: “Project is almost complete and only 20% work is left, application for Occupation certificate is in process”
31 December 2026
Extended at the builder's request (MahaRERA application EA12052620941)
Reason the builder gave MahaRERA: “OCCUPATION CERTIFICATE IS OBTAINED AFTER DATE MENTIONED IN RERA CERTIFICATE AND APPLICATION FOR CORRECTION IS REQUIRED TO BE MADE AS PER OCCUPATION CERTIFICATE OBTAINED”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sai Deep Residency’s extension records on MahaRERA (P51700051285), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sai Deep Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700051285
- Status
- Registered and active
- Builder
- KISHOR RATAN CHAUDHARY
- Location
- Village Kamatghar, Thane · 421302
- Project type
- Others
- Registered on
- 8 Jun 2023
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sai Deep Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI DEEP RESIDENCY | 100% | 100% | 90% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAI DEEP RESIDENCY: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Deep Residency every 1–2 months.
Sai Deep Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 348 – 418 | 30 |
| Shops | 132 – 164 | 4 |
- Buildings: SAI DEEP RESIDENCY (4 floors, 34 units)
- Car parking: 15 covered
- Land: 889 sq m (about 0.2 acres) · sanctioned built-up 1,468 sq m
- Boundaries filed include: HANUMAN MANDIR, DEEP COMPLEX ONE
- Land, as filed: SURVEY NO 49/8/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sai Deep Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sai Deep Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sai Deep Residency
What is the possession date of Sai Deep Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Deep Residency in Village Kamatghar, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sai Deep Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Deep Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sai Deep Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Project is almost complete and only 20% work is left, application for Occupation certificate is in process"; to 31 December 2026, giving the reason "OCCUPATION CERTIFICATE IS OBTAINED AFTER DATE MENTIONED IN RERA CERTIFICATE AND APPLICATION FOR CORRECTION IS REQUIRED TO BE MADE AS PER OCCUPATION CERTIFICATE OBTAINED". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sai Deep Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Deep Residency in Village Kamatghar, Thane is P51700051285.
Is Sai Deep Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency is registered as P51700051285 and its status is "Registered and active".
What is the current construction status of Sai Deep Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI DEEP RESIDENCY is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Sai Deep Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sai Deep Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency is registered on MahaRERA as P51700051285, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sai Deep Residency?
Sai Deep Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sai Deep Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sai Deep Residency: gharkundli.com/tools/property-cost-calculator
Has Sai Deep Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sai Deep Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sai Deep Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sai Deep Residency's possession date changes?
The latest dates are on Sai Deep Residency's MahaRERA page (P51700051285). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Deep Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sai Deep Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency has one building filed: SAI DEEP RESIDENCY with 4 floors and 34 units.
What are the flat sizes (carpet area) in Sai Deep Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sai Deep Residency: 1 BHK: 348 to 418 sq ft carpet (30 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Sai Deep Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for Sai Deep Residency.
How big is the land of Sai Deep Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency stands on 889 sq m of land (about 0.2 acres), with 1,468 sq m of sanctioned built-up area.
What are the reviews of Sai Deep Residency?
Google Maps has reviews of Sai Deep Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sai Deep Residency?
Sai Deep Residency by KISHOR RATAN CHAUDHARY is in Village Kamatghar, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700051285, per GharKundli's check of MahaRERA records. Its boundaries filed there include HANUMAN MANDIR, DEEP COMPLEX ONE. Its land is filed as SURVEY NO 49/8/2. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Sai Deep Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency has 30 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was Sai Deep Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Deep Residency was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.
Does Sai Deep Residency have any legal issues or court cases?
No court cases are listed for Sai Deep Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sai Deep Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KISHOR RATAN CHAUDHARY.
Check it yourself on MahaRERA
- How to check the possession date of Sai Deep Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi
- Ashoka Complex
- Kohinoor Uptown T1 & T6
- Neelkanth Sadan
- Regal Square PH 4 Tower 6 and 8
- The Pallazo
- Arihant City Phase-ii - K Building
- Royal Park
- Raghunath Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.