Shreeji Neelkanth Sadan
by SHREEJI ENTERPRISES · Dandekarwadi, Thane 421302Also near Kamatghar, Bhiwandi, NaupadaRegistered on MahaRERA as “NEELKANTH SADAN”
What’s in the report? →Possession date of Shreeji Neelkanth Sadan (MahaRERA P51700047708): 30 July 2027, moved from 30 July 2026 (12 months later). It has 41 homes (2 BHK, 657 sq ft carpet), 41% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700047708, and currently active.
Source: MahaRERA website — records for P51700047708, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shreeji Neelkanth Sadan?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shreeji Neelkanth Sadan has moved
30 July 2026
Completion date given when the project was registered
30 July 2027
Extended at the builder's request (MahaRERA application EA11082622101)
Reason the builder gave MahaRERA: “DUE TO SHORTAGE OF FUNDS WORK COULD NOT BE COMPLETED ON TIME BUT NOW WORK IS ABOUT TO GET COMPLETE . SO WE NEED EXTENSION TILL 30.07.2027”
Source: Shreeji Neelkanth Sadan’s extension records on MahaRERA (P51700047708), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shreeji Neelkanth Sadan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700047708
- Status
- Registered and active
- Builder
- SHREEJI ENTERPRISES
- Location
- Dandekarwadi, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 21 Nov 2022
- Completion date at registration
- July 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- Homes
- 41
- Sold or booked
- 41%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Shreeji Neelkanth Sadan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NEELKANTH SADAN | 100% | 100% | 95% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- NEELKANTH SADAN: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreeji Neelkanth Sadan every 1–2 months.
Shreeji Neelkanth Sadan: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 657 | 41 |
- Buildings: NEELKANTH SADAN (37 floors, 41 units)
- Land: 1,185 sq m (about 0.3 acres) · sanctioned built-up 3,765 sq m
- Land, as filed: S.NO,206/A/3,206/A/4 AND 206/A/8
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shreeji Neelkanth Sadan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shreeji Neelkanth Sadan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shreeji Neelkanth Sadan
What is the possession date of Shreeji Neelkanth Sadan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreeji Neelkanth Sadan in Dandekarwadi, Thane is 30 July 2027 — 12 months later than 30 July 2026, the date given at registration.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shreeji Neelkanth Sadan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreeji Neelkanth Sadan's builder has filed on MahaRERA, the official one, is 30 July 2027, already 12 months later than the 30 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shreeji Neelkanth Sadan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan's builder applied to MahaRERA to extend the completion date once: to 30 July 2027, giving the reason "DUE TO SHORTAGE OF FUNDS WORK COULD NOT BE COMPLETED ON TIME BUT NOW WORK IS ABOUT TO GET COMPLETE . SO WE NEED EXTENSION TILL 30.07.2027".
What is the RERA number of Shreeji Neelkanth Sadan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreeji Neelkanth Sadan in Dandekarwadi, Thane is P51700047708.
Is Shreeji Neelkanth Sadan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan is registered as P51700047708 and its status is "Registered and active".
What is the current construction status of Shreeji Neelkanth Sadan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NEELKANTH SADAN is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Shreeji Neelkanth Sadan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shreeji Neelkanth Sadan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan is registered on MahaRERA as P51700047708, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shreeji Neelkanth Sadan?
Shreeji Neelkanth Sadan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shreeji Neelkanth Sadan?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shreeji Neelkanth Sadan: gharkundli.com/tools/property-cost-calculator
Has Shreeji Neelkanth Sadan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan is still under construction, with 30 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shreeji Neelkanth Sadan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreeji Neelkanth Sadan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shreeji Neelkanth Sadan's possession date changes?
The latest dates are on Shreeji Neelkanth Sadan's MahaRERA page (P51700047708). GharKundli's Kundli Watch sends a free WhatsApp update on Shreeji Neelkanth Sadan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shreeji Neelkanth Sadan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan has one building filed: NEELKANTH SADAN with 37 floors and 41 units.
What are the flat sizes (carpet area) in Shreeji Neelkanth Sadan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shreeji Neelkanth Sadan: 2 BHK: 657 sq ft carpet (41 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Shreeji Neelkanth Sadan?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan stands on 1,185 sq m of land (about 0.3 acres), with 3,765 sq m of sanctioned built-up area.
What are the reviews of Shreeji Neelkanth Sadan?
Google Maps has reviews of Shreeji Neelkanth Sadan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shreeji Neelkanth Sadan?
Shreeji Neelkanth Sadan by SHREEJI ENTERPRISES is in Dandekarwadi, Thane, pincode 421302 (near Kamatghar, Bhiwandi, Naupada), Maharashtra, and is registered on MahaRERA as P51700047708, per GharKundli's check of MahaRERA records. Its land is filed as S.NO,206/A/3,206/A/4 AND 206/A/8. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Shreeji Neelkanth Sadan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan has 41 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.
When was Shreeji Neelkanth Sadan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Neelkanth Sadan was registered on MahaRERA on 21 November 2022. GharKundli did not find a title report on the land on file there.
Does Shreeji Neelkanth Sadan have any legal issues or court cases?
No court cases are listed for Shreeji Neelkanth Sadan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shreeji Neelkanth Sadan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREEJI ENTERPRISES, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shreeji Neelkanth Sadan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi (421302)
- Ashoka Complex
- Kohinoor Uptown T1 & T6
- Arihant City Phase-ii - K Building
- Regal Square PH 4 Tower 6 and 8
- Royal Park
- Multani Residency
- Sai Deep Residency
- Raghunath Heights
Other projects by SHREEJI ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.