ROYAL PARK

by PENS BUILDERS & DEVELOPERS LLP · Temghar, ThaneAlso near Bhiwandi, Bhadwad

Possession date of ROYAL PARK: 30 April 2030, moved from 30 June 2027 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700048809, and currently active. Its completion date has moved from June 2027 to April 2030: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ROYAL PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ROYAL PARK has moved

  1. 30 June 2027

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EA05082502304)

    Reason the builder gave MahaRERA:
    “1. A construction stay was imposed by Bhiwandi Nizampura City Municipal Corporation (BNCMC) owing to the proposed MRTS Line – 5 alignment. 2. We have now obtained the requisite No Objection Certificate (NOC) from the Mumbai Metropolitan Reg…” Read the full reason“1. A construction stay was imposed by Bhiwandi Nizampura City Municipal Corporation (BNCMC) owing to the proposed MRTS Line – 5 alignment. 2. We have now obtained the requisite No Objection Certificate (NOC) from the Mumbai Metropolitan Region Development Authority (MMRDA), which resolves the issue.”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ROYAL PARK’s extension records on MahaRERA (P51700048809), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ROYAL PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700048809
Status
Registered and active
Builder
PENS BUILDERS & DEVELOPERS LLP
Location
Temghar, Thane · 421302
Project type
Residential / Group Housing
Registered on
19 Jan 2023
Completion date at registration
June 2027
Latest completion date
April 2030
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
124
Sold or booked
11%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of ROYAL PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%11%0%0%
B100%31.59%0%0%
C0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • A: covers 7 floors
  • B: covers 7 floors
  • C: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ROYAL PARK every month.

ROYAL PARK: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK319 – 321110
2 BHK543 – 64414
Shops119 – 45212
  • Buildings: A (7 floors, 66 units) · B (7 floors, 60 units) · C (2 floors, 10 units)
  • Car parking: 3 covered, 43 open
  • Land: 7,514 sq m (about 1.9 acres) · sanctioned built-up 8,055 sq m · recreational space 754 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ROYAL PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ROYAL PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ROYAL PARK

What is the possession date of ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ROYAL PARK in Temghar, Thane is 30 April 2030 — 30 months later than 30 June 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ROYAL PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ROYAL PARK's builder has filed on MahaRERA, the official one, is 30 April 2030, already 30 months later than the 30 June 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ROYAL PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "1. A construction stay was imposed by Bhiwandi Nizampura City Municipal Corporation (BNCMC) owing to the proposed MRTS Line – 5 alignment. 2. We have now obtained the requisite No Objection Certificate (NOC) from the Mumbai Metropolitan Region Development Authority (MMRDA), which resolves the issue.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ROYAL PARK in Temghar, Thane is P51700048809.

Is ROYAL PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK is registered as P51700048809 and its status is "Registered and active".

What is the construction status of ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 31.59% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does ROYAL PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is ROYAL PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK is registered on MahaRERA as P51700048809, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ROYAL PARK's possession date changes?

The latest dates are on ROYAL PARK's MahaRERA page (P51700048809). GharKundli's Kundli Watch sends a free WhatsApp update on ROYAL PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ROYAL PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK has 3 buildings filed: A with 7 floors and 66 units; B with 7 floors and 60 units; C with 2 floors and 10 units.

What are the flat sizes (carpet area) in ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ROYAL PARK: 1 BHK: 319 to 321 sq ft carpet (110 homes); 2 BHK: 543 to 644 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does ROYAL PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 3 covered and 43 open car parking spaces for ROYAL PARK.

How big is the land of ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK stands on 7,514 sq m of land (about 1.9 acres), with 8,055 sq m of sanctioned built-up area and 754 sq m of recreational open space.

Where can I read reviews of ROYAL PARK?

Google Maps has reviews of ROYAL PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ROYAL PARK?

ROYAL PARK by PENS BUILDERS & DEVELOPERS LLP is in Temghar, Thane (pincode 421302), near Bhiwandi, Bhadwad, Maharashtra, and is registered on MahaRERA as P51700048809, per GharKundli's check of MahaRERA records.

How many homes are in ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK has 124 homes in 3 towers registered on MahaRERA, and 11% of them are sold or booked.

When was ROYAL PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL PARK was registered on MahaRERA on 19 January 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on ROYAL PARK?

No court cases are listed for ROYAL PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ROYAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PENS BUILDERS & DEVELOPERS LLP.

All projects with possession due in 2030 in Thane →

Other projects in Temghar

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.