by TALL CONSTRUCTIONS · Temghar, Thane 421302Also near Bhiwandi, Bhadwad

What’s in the report? →

Possession date of Tall Residency (MahaRERA P51700013609): 30 April 2029, moved from 22 June 2021 (90 months later). It has 49 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700013609, and currently active. Its completion date has moved from June 2021 to April 2029: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700013609, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Tall Residency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Tall Residency has moved

  1. 22 June 2021

    Completion date given when the project was registered

  2. 21 June 2022

    Extended at the builder's request (MahaRERA application EXT51700009855)

    Reason the builder gave MahaRERA:
    “Sir/Madam, I, Prashant J. Chaudhari, partner of M/s. Tall Constructions have a Project Named ‘TALL RESIDNECY’ registered under MahaRera vide no. P51700013609, request you to grant extension of time period under RERA. Sir/Madam, due to Natio…” Read the full reason“Sir/Madam, I, Prashant J. Chaudhari, partner of M/s. Tall Constructions have a Project Named ‘TALL RESIDNECY’ registered under MahaRera vide no. P51700013609, request you to grant extension of time period under RERA. Sir/Madam, due to Nation-vide impact of Covid-19 we were unable to complete the project within stipulated time period. Till now only 60% work has been completed on current date. And further we have applied for change in project for adding additional floors (upto 14th Floors Current project of 6 floors) in the building. And due to slack in market there are no bookings from custo…”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51700013598)

    Reason the builder gave MahaRERA: “Resp. Sir we apply for extenstion as our plan can be revised and additional floors can be added. and for the same customers have given consent. so please grant us extension till 31/12/2024.”
  4. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT51700025827)

    Reason the builder gave MahaRERA:
    “Dear Sir/Madam, We, at M/s. Tall Constructions, the promoter of the project "Tall Residency," would like to bring to your attention the current status of the project and request an extension for the registration under MahaRERA. The construc…” Read the full reason“Dear Sir/Madam, We, at M/s. Tall Constructions, the promoter of the project "Tall Residency," would like to bring to your attention the current status of the project and request an extension for the registration under MahaRERA. The construction of the project has not been completed, and we wish to expand our building also, for this we had discussed the matter with existing customers/Allottees also, they have readlily agreed as we have taken part completion of the project, which will not harm their interest. They have given consent of the same. As the previous Covid Impact there was very slo…”
  5. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Tall Residency’s extension records on MahaRERA (P51700013609), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tall Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700013609
Status
Registered and active
Builder
TALL CONSTRUCTIONS
Location
Temghar, Thane · 421302
Project type
Residential / Group Housing
Registered on
16 Oct 2017
Completion date at registration
June 2021
Latest completion date
April 2029
Delay so far
90 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
49
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Tall Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TALL RESIDENCY A WING75%7%5%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tall Residency every 1–2 months.

Tall Residency: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Tall Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tall Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Tall Residency

What is the possession date of Tall Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tall Residency in Temghar, Thane is 30 April 2029 — 90 months later than 22 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 90 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Tall Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tall Residency's builder has filed on MahaRERA, the official one, is 30 April 2029, already 90 months later than the 22 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Tall Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency's builder applied to MahaRERA to extend the completion date 3 times: to 21 June 2022, giving the reason "Sir/Madam, I, Prashant J. Chaudhari, partner of M/s. Tall Constructions have a Project Named ‘TALL RESIDNECY’ registered under MahaRera vide no. P51700013609, request you to grant extension of time period under RERA. Sir/Madam, due to Nation-vide impact of Covid-19 we were unable to complete the project within stipulated time period. Till now only 60% work has been completed on current date. And further we have applied for change in project for adding additional floors (upto 14th Floors Current project of 6 floors) in the building. And due to slack in market there are no bookings from custo…"; to 31 December 2024, giving the reason "Resp. Sir we apply for extenstion as our plan can be revised and additional floors can be added. and for the same customers have given consent. so please grant us extension till 31/12/2024."; to 31 December 2028, giving the reason "Dear Sir/Madam, We, at M/s. Tall Constructions, the promoter of the project "Tall Residency," would like to bring to your attention the current status of the project and request an extension for the registration under MahaRERA. The construction of the project has not been completed, and we wish to expand our building also, for this we had discussed the matter with existing customers/Allottees also, they have readlily agreed as we have taken part completion of the project, which will not harm their interest. They have given consent of the same. As the previous Covid Impact there was very slo…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Tall Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tall Residency in Temghar, Thane is P51700013609.

Is Tall Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency is registered as P51700013609 and its status is "Registered and active".

What is the current construction status of Tall Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TALL RESIDENCY A WING is 7% done and internal work 5%. GharKundli's full report compares construction progress with the deadline.

Does Tall Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Tall Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency is registered on MahaRERA as P51700013609, its completion date has moved 90 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Tall Residency?

Tall Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Tall Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Tall Residency: gharkundli.com/tools/property-cost-calculator

Has Tall Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Tall Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tall Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Tall Residency's possession date changes?

The latest dates are on Tall Residency's MahaRERA page (P51700013609). GharKundli's Kundli Watch sends a free WhatsApp update on Tall Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tall Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency has one building filed: TALL RESIDENCY A WING with 14 floors.

How big is the land of Tall Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency stands on 2,468 sq m of land (about 0.6 acres), with 2,689 sq m of sanctioned built-up area and 1,962 sq m of recreational open space.

What are the reviews of Tall Residency?

Google Maps has reviews of Tall Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Tall Residency?

Tall Residency by TALL CONSTRUCTIONS is in Temghar, Thane, pincode 421302 (near Bhiwandi, Bhadwad), Maharashtra, and is registered on MahaRERA as P51700013609, per GharKundli's check of MahaRERA records. Its land is filed as 9/9 8. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Tall Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency has 49 homes in 1 tower registered on MahaRERA.

When was Tall Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tall Residency was registered on MahaRERA on 16 October 2017. GharKundli did not find a title report on the land on file there.

Does Tall Residency have any legal issues or court cases?

No court cases are listed for Tall Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Tall Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TALL CONSTRUCTIONS.

All projects with possession due in 2029 in Thane →

Other projects in Bhiwandi (421302)

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.