Regal Square PH 4 Tower 6 and 8
by DEV DRASHTI REALTY PRIVATE LIMITED · Near Chattrapati Shivaji Maharaj Stadium, Thane 421302Also near Bhiwandi, Bhadwad Village
What’s in the report? →Possession date of Regal Square PH 4 Tower 6 and 8 (MahaRERA P51700033625): 30 April 2028, moved from 31 December 2026 (12 months later). It has 260 homes (1 BHK and 2 BHK, 402–580 sq ft carpet), 4% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700033625, and currently active. Its completion date has moved from December 2026 to April 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700033625, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Regal Square PH 4 Tower 6 and 8?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Regal Square PH 4 Tower 6 and 8 has moved
31 December 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA16072621767)
Reason the builder gave MahaRERA:
“The project could not be completed within the original timeline due to the pendency of balance finishing works, internal and external services, statutory approvals and Occupancy Certificate. The Promoter has made substantial progress and re…” Read the full reason
“The project could not be completed within the original timeline due to the pendency of balance finishing works, internal and external services, statutory approvals and Occupancy Certificate. The Promoter has made substantial progress and requires additional time to complete the remaining works as per the revised PERT Chart and deliver the project by 31.12.2027”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Regal Square PH 4 Tower 6 and 8’s extension records on MahaRERA (P51700033625), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Regal Square PH 4 Tower 6 and 8
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700033625
- Status
- Registered and active
- Builder
- DEV DRASHTI REALTY PRIVATE LIMITED
- Location
- Near Chattrapati Shivaji Maharaj Stadium, Thane · 421302
- Project type
- Others
- Registered on
- 2 Mar 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2028
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 260
- Sold or booked
- 4%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Regal Square PH 4 Tower 6 and 8, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 6 | 100% | 100% | 100% | 0% |
| 8 | 100% | 60% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 6: covers 15 floors
- 8: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Regal Square PH 4 Tower 6 and 8 every 1–2 months.
Regal Square PH 4 Tower 6 and 8: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 402 – 418 | 229 |
| 2 BHK | 543 – 580 | 31 |
| Shops | 139 – 194 | 9 |
- Buildings: 6 (17 floors, 177 units) · 8 (17 floors, 92 units)
- Car parking: 27 covered
- Land: 1,102 sq m (about 0.3 acres) · sanctioned built-up 10,590 sq m
- Land, as filed: 5/2P, 5/2P, 5/1P/1
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Shri Hari Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Regal Square PH 4 Tower 6 and 8 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Regal Square PH 4 Tower 6 and 8: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Regal Square PH 4 Tower 6 and 8
What is the possession date of Regal Square PH 4 Tower 6 and 8?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Regal Square PH 4 Tower 6 and 8 in Near Chattrapati Shivaji Maharaj Stadium, Thane is 30 April 2028 — 12 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Regal Square PH 4 Tower 6 and 8?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Regal Square PH 4 Tower 6 and 8's builder has filed on MahaRERA, the official one, is 30 April 2028, already 12 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Regal Square PH 4 Tower 6 and 8 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The project could not be completed within the original timeline due to the pendency of balance finishing works, internal and external services, statutory approvals and Occupancy Certificate. The Promoter has made substantial progress and requires additional time to complete the remaining works as per the revised PERT Chart and deliver the project by 31.12.2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Regal Square PH 4 Tower 6 and 8?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Regal Square PH 4 Tower 6 and 8 in Near Chattrapati Shivaji Maharaj Stadium, Thane is P51700033625.
Is Regal Square PH 4 Tower 6 and 8 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 is registered as P51700033625 and its status is "Registered and active".
What is the current construction status of Regal Square PH 4 Tower 6 and 8? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 60% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Regal Square PH 4 Tower 6 and 8 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Regal Square PH 4 Tower 6 and 8 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 is registered on MahaRERA as P51700033625, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Regal Square PH 4 Tower 6 and 8?
Regal Square PH 4 Tower 6 and 8 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Regal Square PH 4 Tower 6 and 8?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Regal Square PH 4 Tower 6 and 8: gharkundli.com/tools/property-cost-calculator
Has Regal Square PH 4 Tower 6 and 8 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Regal Square PH 4 Tower 6 and 8 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Regal Square PH 4 Tower 6 and 8 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Regal Square PH 4 Tower 6 and 8's possession date changes?
The latest dates are on Regal Square PH 4 Tower 6 and 8's MahaRERA page (P51700033625). GharKundli's Kundli Watch sends a free WhatsApp update on Regal Square PH 4 Tower 6 and 8 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Regal Square PH 4 Tower 6 and 8 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 has 2 buildings filed: 6 with 17 floors and 177 units; 8 with 17 floors and 92 units.
What are the flat sizes (carpet area) in Regal Square PH 4 Tower 6 and 8?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Regal Square PH 4 Tower 6 and 8: 1 BHK: 402 to 418 sq ft carpet (229 homes); 2 BHK: 543 to 580 sq ft carpet (31 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Regal Square PH 4 Tower 6 and 8 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 27 covered car parking spaces for Regal Square PH 4 Tower 6 and 8.
How big is the land of Regal Square PH 4 Tower 6 and 8?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 stands on 1,102 sq m of land (about 0.3 acres), with 10,590 sq m of sanctioned built-up area.
What is the track record of Regal Square PH 4 Tower 6 and 8's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shri Hari Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Regal Square PH 4 Tower 6 and 8?
Google Maps has reviews of Regal Square PH 4 Tower 6 and 8 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Regal Square PH 4 Tower 6 and 8?
Regal Square PH 4 Tower 6 and 8 by DEV DRASHTI REALTY PRIVATE LIMITED is in Near Chattrapati Shivaji Maharaj Stadium, Thane, pincode 421302 (near Bhiwandi, Bhadwad Village), Maharashtra, and is registered on MahaRERA as P51700033625, per GharKundli's check of MahaRERA records. Its land is filed as 5/2P, 5/2P, 5/1P/1. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Regal Square PH 4 Tower 6 and 8, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 has 260 homes in 2 towers registered on MahaRERA, and 4% of them are sold or booked.
When was Regal Square PH 4 Tower 6 and 8 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Regal Square PH 4 Tower 6 and 8 was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.
Does Regal Square PH 4 Tower 6 and 8 have any legal issues or court cases?
1 court case is listed for Regal Square PH 4 Tower 6 and 8 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Regal Square PH 4 Tower 6 and 8?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DEV DRASHTI REALTY PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Regal Square PH 4 Tower 6 and 8
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Bhiwandi
- Kohinoor Uptown T1 & T6
- Ashoka Complex
- Sai Deep Residency
- Neelkanth Sadan
- The Pallazo
- Arihant City Phase-ii - K Building
- Royal Park
- Raghunath Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.