Skip to content
GharKundli

Raghunath Heights

by Khrushna Infrastructure Builders & Developers · Dandekarwadi, Thane

Possession date of Raghunath Heights: 30 April 2029, moved from 31 December 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700047773, and currently active. Its completion date has moved from December 2025 to April 2029: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Raghunath Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Raghunath Heights has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT51700019875)

    Reason the builder gave MahaRERA:
    “a) There are two wings in a project i.e., Raghunath Heights Wing – A and Raghunath Heights Wing - B. The construction of Raghunath Heights Wing – A is in process. b) The excavation work took more than expected as there was hard rock and we…” Read the full reason“a) There are two wings in a project i.e., Raghunath Heights Wing – A and Raghunath Heights Wing - B. The construction of Raghunath Heights Wing – A is in process. b) The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes considerably more time than the conventional methods. c) Construction of Raghunath Heights Wing - B is not started yet and we have not sold & not accepted bookings in the said wing. d)…”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Raghunath Heights’s extension records on MahaRERA (P51700047773), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Raghunath Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700047773
Status
Registered and active
Builder
Khrushna Infrastructure Builders & Developers
Location
Dandekarwadi, Thane · 421302
Project type
Others
Registered on
28 Nov 2022
Completion date at registration
December 2025
Latest completion date
April 2029
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
225
Sold or booked
13%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Raghunath Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Raghunath Heights Wing - A100%45%0%0%
Raghunath Heights Wing - B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Raghunath Heights Wing - A: covers 15 floors
  • Raghunath Heights Wing - B: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Raghunath Heights every month.

Raghunath Heights: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK330 – 380200
2 BHK470 – 48725
Shops132 – 1624
  • Buildings: Raghunath Heights Wing - A (15 floors, 128 units) · Raghunath Heights Wing - B (15 floors, 101 units)
  • Land: 4,050 sq m (about 1.0 acres) · sanctioned built-up 8,299 sq m · recreational space 4,050 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Raghunath Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Raghunath Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Raghunath Heights

What is the possession date of Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Raghunath Heights in Dandekarwadi, Thane is 30 April 2029 — 36 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Raghunath Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Raghunath Heights's builder has filed on MahaRERA, the official one, is 30 April 2029, already 36 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Raghunath Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "a) There are two wings in a project i.e., Raghunath Heights Wing – A and Raghunath Heights Wing - B. The construction of Raghunath Heights Wing – A is in process. b) The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes considerably more time than the conventional methods. c) Construction of Raghunath Heights Wing - B is not started yet and we have not sold & not accepted bookings in the said wing. d)…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Raghunath Heights in Dandekarwadi, Thane is P51700047773.

Is Raghunath Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights is registered as P51700047773 and its status is "Registered and active".

What is the construction status of Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 45% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Raghunath Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Raghunath Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights is registered on MahaRERA as P51700047773, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Raghunath Heights's possession date changes?

The latest dates are on Raghunath Heights's MahaRERA page (P51700047773). GharKundli's Kundli Watch sends a free WhatsApp update on Raghunath Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Raghunath Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights has 2 buildings filed: Raghunath Heights Wing - A with 15 floors and 128 units; Raghunath Heights Wing - B with 15 floors and 101 units.

What are the flat sizes (carpet area) in Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Raghunath Heights: 1 BHK: 330 to 380 sq ft carpet (200 homes); 2 BHK: 470 to 487 sq ft carpet (25 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights stands on 4,050 sq m of land (about 1.0 acres), with 8,299 sq m of sanctioned built-up area and 4,050 sq m of recreational open space.

Where can I read reviews of Raghunath Heights?

Google Maps has reviews of Raghunath Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Raghunath Heights?

Raghunath Heights by Khrushna Infrastructure Builders & Developers is in Dandekarwadi, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700047773, per GharKundli's check of MahaRERA records.

How many homes are in Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights has 225 homes in 2 towers registered on MahaRERA, and 13% of them are sold or booked.

When was Raghunath Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raghunath Heights was registered on MahaRERA on 28 November 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Raghunath Heights?

No court cases are listed for Raghunath Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Raghunath Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Khrushna Infrastructure Builders & Developers.

All projects with possession due in 2029 in Thane →

Other projects in pincode 421302

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.