Ritz Tower C

by VIKAS HARAKCHAND JAIN · Shree Complex Phase III, Thane 421301

What’s in the report? →

Possession date of Ritz Tower C (MahaRERA P51700047718): 30 January 2028, moved from 30 September 2026 (12 months later). It has 200 homes, 86% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700047718, and currently active. Its completion date has moved from September 2026 to January 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700047718, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ritz Tower C?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ritz Tower C has moved

  1. 30 September 2026

    Completion date given when the project was registered

  2. 30 September 2027

    Extended at the builder's request (MahaRERA application EA08072621698)

    Reason the builder gave MahaRERA: “As per order of the Hon'ble Chairman (MahaRERA) Dated 04/08/2026, we request you kindly to grant us extension till 30/09/2027.”
  3. 30 January 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ritz Tower C’s extension records on MahaRERA (P51700047718), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ritz Tower C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700047718
Status
Registered and active
Builder
VIKAS HARAKCHAND JAIN
Location
Shree Complex Phase III, Thane · 421301
Project type
Residential / Group Housing
Registered on
21 Nov 2022
Completion date at registration
September 2026
Latest completion date
January 2028
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
200
Sold or booked
86%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
15

Construction progress of Ritz Tower C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TOWER C - TYPE C100%100%75%15%

Commencement certificate (CC), as filed on MahaRERA

  • TOWER C - TYPE C: covers G+27

Latest CC order on MahaRERA: dated 28/02/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ritz Tower C every 1–2 months.

Ritz Tower C: buildings, flats and land, as filed on MahaRERA

  • Buildings: TOWER C - TYPE C (28 floors, 200 units)
  • Car parking: 130 covered
  • Land: 20,672 sq m (about 5.1 acres) · sanctioned built-up 15,198 sq m · recreational space 1,561 sq m
  • Boundaries filed include: VISHAL BHOIR CHOWK
  • Land, as filed: 6/1/3, 6/2, 39/1/1 (PART), 39/5
  • Map: Get directions

The builder’s record and reviews

Vikas Harakchand Jain has 19 projects on MahaRERA since 2020, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 16 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Ritz Tower C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ritz Tower C: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ritz Tower C

What is the possession date of Ritz Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ritz Tower C in Shree Complex Phase III, Thane is 30 January 2028 — 12 months later than 30 September 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ritz Tower C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ritz Tower C's builder has filed on MahaRERA, the official one, is 30 January 2028, already 12 months later than the 30 September 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ritz Tower C extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "As per order of the Hon'ble Chairman (MahaRERA) Dated 04/08/2026, we request you kindly to grant us extension till 30/09/2027.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ritz Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ritz Tower C in Shree Complex Phase III, Thane is P51700047718.

Is Ritz Tower C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C is registered as P51700047718 and its status is "Registered and active".

What is the current construction status of Ritz Tower C? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TOWER C - TYPE C is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does Ritz Tower C have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ritz Tower C safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C is registered on MahaRERA as P51700047718, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ritz Tower C?

Ritz Tower C is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ritz Tower C?

For a flat in Ritz Tower C (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ritz Tower C received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C is still under construction, with 30 January 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Ritz Tower C a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C is a redevelopment: 96 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Ritz Tower C uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ritz Tower C was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ritz Tower C's possession date changes?

The latest dates are on Ritz Tower C's MahaRERA page (P51700047718). GharKundli's Kundli Watch sends a free WhatsApp update on Ritz Tower C every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ritz Tower C have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C has one building filed: TOWER C - TYPE C with 28 floors and 200 units.

How much parking does Ritz Tower C have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 130 covered car parking spaces for Ritz Tower C.

How big is the land of Ritz Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C stands on 20,672 sq m of land (about 5.1 acres), with 15,198 sq m of sanctioned built-up area and 1,561 sq m of recreational open space.

What is the track record of Ritz Tower C's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Harakchand Jain has 19 projects on MahaRERA since 2020, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 16 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ritz Tower C?

Google Maps has reviews of Ritz Tower C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ritz Tower C?

Ritz Tower C by VIKAS HARAKCHAND JAIN is in Shree Complex Phase III, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700047718, per GharKundli's check of MahaRERA records. Its boundaries filed there include VISHAL BHOIR CHOWK. Its land is filed as 6/1/3, 6/2, 39/1/1 (PART), 39/5. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Ritz Tower C, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C has 200 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was Ritz Tower C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritz Tower C was registered on MahaRERA on 21 November 2022. GharKundli did not find a title report on the land on file there.

Does Ritz Tower C have any legal issues or court cases?

No court cases are listed for Ritz Tower C on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Ritz Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIKAS HARAKCHAND JAIN, which has 15 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Kalyan

All 582 projects in Kalyan (421301) →

Other projects by VIKAS HARAKCHAND JAIN

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.