SAT ANUPA CHS PHASE 1

by DISHA CONSTRUCTION · Juhu, MumbaiAlso near Vile Parle West, Andheri West, vileparle

Possession: SAT ANUPA CHS PHASE 1 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800001640. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAT ANUPA CHS PHASE 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAT ANUPA CHS PHASE 1 has moved

  1. 31 March 2020

    Completion date given when the project was registered

  2. 30 March 2021

    Extended at the builder's request (MahaRERA application EXT51800002393)

    Reason the builder gave MahaRERA: “DUE TO CHANGE OF DCR TO NEW DCPR, TRANSITION POLICY, DATE OF APPLICABILITY OF NEW DCPR, APPROVAL AS PER NEW DCPR FOR BALANCE PORTION OF DEVELOPMENT ETC”
  3. 30 March 2022

    Revised completion date on MahaRERA

Source: SAT ANUPA CHS PHASE 1’s extension records on MahaRERA (P51800001640), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAT ANUPA CHS PHASE 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the March 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800001640
Status
Completed
Builder
DISHA CONSTRUCTION
Location
Juhu, Mumbai · 400049
Project type
Residential / Group Housing
Registered on
29 Jul 2017
Completion date at registration
March 2020
Latest completion date
March 2022
Delay so far
24 months
Homes
9
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of SAT ANUPA CHS PHASE 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAT ANUPA CHS PHASE 1100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAT ANUPA CHS PHASE 1 every month.

SAT ANUPA CHS PHASE 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Disha Construction has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 23 months); 1 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SAT ANUPA CHS PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAT ANUPA CHS PHASE 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAT ANUPA CHS PHASE 1

What is the possession date of SAT ANUPA CHS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAT ANUPA CHS PHASE 1 in Juhu, Mumbai is 30 March 2022 — 24 months later than 31 March 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAT ANUPA CHS PHASE 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAT ANUPA CHS PHASE 1's builder has filed on MahaRERA, the official one, is 30 March 2022, already 24 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAT ANUPA CHS PHASE 1 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1's builder applied to MahaRERA to extend the completion date once: to 30 March 2021, giving the reason "DUE TO CHANGE OF DCR TO NEW DCPR, TRANSITION POLICY, DATE OF APPLICABILITY OF NEW DCPR, APPROVAL AS PER NEW DCPR FOR BALANCE PORTION OF DEVELOPMENT ETC".

What is the RERA number of SAT ANUPA CHS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAT ANUPA CHS PHASE 1 in Juhu, Mumbai is P51800001640.

Is SAT ANUPA CHS PHASE 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1 is registered as P51800001640 and its status is "Completed".

What is the construction status of SAT ANUPA CHS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1's status on MahaRERA is "Completed". As filed by the builder, slab work on SAT ANUPA CHS PHASE 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAT ANUPA CHS PHASE 1 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAT ANUPA CHS PHASE 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1 is registered on MahaRERA as P51800001640, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAT ANUPA CHS PHASE 1's possession date changes?

The latest dates are on SAT ANUPA CHS PHASE 1's MahaRERA page (P51800001640). GharKundli's Kundli Watch sends a free WhatsApp update on SAT ANUPA CHS PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAT ANUPA CHS PHASE 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1 has one building filed: SAT ANUPA CHS PHASE 1 with 13 floors.

How big is the land of SAT ANUPA CHS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1 stands on 861 sq m of land (about 0.2 acres), with 2,320 sq m of sanctioned built-up area.

What is the track record of SAT ANUPA CHS PHASE 1's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Disha Construction has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 23 months); 1 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAT ANUPA CHS PHASE 1?

Google Maps has reviews of SAT ANUPA CHS PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAT ANUPA CHS PHASE 1?

SAT ANUPA CHS PHASE 1 by DISHA CONSTRUCTION is in Juhu, Mumbai (pincode 400049), near Vile Parle West, Andheri West, vileparle, Maharashtra, and is registered on MahaRERA as P51800001640, per GharKundli's check of MahaRERA records.

How many homes are in SAT ANUPA CHS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1 has 9 homes in 1 tower registered on MahaRERA.

When was SAT ANUPA CHS PHASE 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAT ANUPA CHS PHASE 1 was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAT ANUPA CHS PHASE 1?

No court cases are listed for SAT ANUPA CHS PHASE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAT ANUPA CHS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DISHA CONSTRUCTION, which has 4 other projects registered on MahaRERA.