Possession date of K L VALERIA: 30 January 2027, moved from 30 September 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800050591, and currently active. Its completion date has moved from September 2025 to January 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about K L VALERIA?
How the possession date of K L VALERIA has moved
30 September 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA05082502307)
Reason the builder gave MahaRERA:
“The need for extension arises due to unforeseen delays in the correction of the plot area, caused by discrepancies between various official records including the TP Remarks, PRC, and City Survey Plan. Detailed Explanatory Note along with su…” Read the full reason
“The need for extension arises due to unforeseen delays in the correction of the plot area, caused by discrepancies between various official records including the TP Remarks, PRC, and City Survey Plan. Detailed Explanatory Note along with supporting documents are attached”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: K L VALERIA’s extension records on MahaRERA (P51800050591), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on K L VALERIA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800050591
- Status
- Registered and active
- Builder
- K L HOUSING LLP
- Location
- Santacruz West, Mumbai · 400049
- Project type
- Others
- Registered on
- 21 Apr 2023
- Completion date at registration
- September 2025
- Latest completion date
- January 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 15
- Sold or booked
- 67%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of K L VALERIA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| K L VALERIA | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- K L VALERIA: covers 8 floors
Latest CC order on MahaRERA: dated 03/07/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on K L VALERIA every month.
K L VALERIA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 876 – 2,206 | 5 |
| 1 BHK | 445 | 4 |
| 2 BHK | 661 – 689 | 4 |
| 4 BHK | 2,041 – 2,206 | 2 |
| Shops | 3,940 | 1 |
- Buildings: K L VALERIA (13 floors, 16 units)
- Land: 657 sq m (about 0.2 acres) · sanctioned built-up 1,807 sq m
- Boundaries filed include: JUHU TARA ROAD
The builder’s record and reviews
K L Housing has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 20 months); 1 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA.
Read Google reviews of K L VALERIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
K L VALERIA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about K L VALERIA
What is the possession date of K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for K L VALERIA in Santacruz West, Mumbai is 30 January 2027 — 12 months later than 30 September 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for K L VALERIA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date K L VALERIA's builder has filed on MahaRERA, the official one, is 30 January 2027, already 12 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of K L VALERIA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "The need for extension arises due to unforeseen delays in the correction of the plot area, caused by discrepancies between various official records including the TP Remarks, PRC, and City Survey Plan. Detailed Explanatory Note along with supporting documents are attached". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of K L VALERIA in Santacruz West, Mumbai is P51800050591.
Is K L VALERIA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA is registered as P51800050591 and its status is "Registered and active".
What is the construction status of K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on K L VALERIA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does K L VALERIA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is K L VALERIA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA is registered on MahaRERA as P51800050591, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if K L VALERIA's possession date changes?
The latest dates are on K L VALERIA's MahaRERA page (P51800050591). GharKundli's Kundli Watch sends a free WhatsApp update on K L VALERIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does K L VALERIA have?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA has one building filed: K L VALERIA with 13 floors and 16 units.
What are the flat sizes (carpet area) in K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for K L VALERIA: 3 BHK: 876 to 2206 sq ft carpet (5 homes); 1 BHK: 445 sq ft carpet (4 homes); 2 BHK: 661 to 689 sq ft carpet (4 homes); 4 BHK: 2041 to 2206 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA stands on 657 sq m of land (about 0.2 acres), with 1,807 sq m of sanctioned built-up area.
What is the track record of K L VALERIA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), K L Housing has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 20 months); 1 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of K L VALERIA?
Google Maps has reviews of K L VALERIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is K L VALERIA?
K L VALERIA by K L HOUSING LLP is in Santacruz West, Mumbai (pincode 400049), Maharashtra, and is registered on MahaRERA as P51800050591, per GharKundli's check of MahaRERA records. Its boundaries filed there include JUHU TARA ROAD.
How many homes are in K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA has 15 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.
When was K L VALERIA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), K L VALERIA was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on K L VALERIA?
No court cases are listed for K L VALERIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of K L VALERIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K L HOUSING LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of K L VALERIA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Santacruz West
- MANTRI PRERANA
- COMMERZ 54
- CYRILYN
- OM PALACE
- SMRUTI BY RANGOLI DEVELOPERS
- AATMAY
- JAY KRUPA SADAN BY SHREE HARI REALTY
- WINDERMERE
Other projects by K L HOUSING LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.