Vinayak Commerz 54

by SHREE VINAYAK REALITY PRIVATE LIMITED · Santacruz West, Mumbai 400054Also near Santacruz East, Andheri, Vile Parle EastRegistered on MahaRERA as “COMMERZ 54”

What’s in the report? →

Possession date of Vinayak Commerz 54 (MahaRERA P51800020069): 30 October 2026, moved from 15 December 2022 (42 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800020069, and currently active. Its completion date has moved from December 2022 to October 2026: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800020069, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Vinayak Commerz 54?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vinayak Commerz 54 has moved

  1. 15 December 2022

    Completion date given when the project was registered

  2. 14 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013299)

    Reason the builder gave MahaRERA: “Due to Covid-19 and shortage labourers for certain period the project could not be completed in time”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800019465)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 54.76% allottees for purpose of extension of RERA registration period of the said project.”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA26082502442)

    Reason the builder gave MahaRERA:
    “We sincerely regret the delay in the completion of the project as well as in the submission of this extension request. The delay has occurred due to unforeseen and unavoidable circumstances, including procurement challenges, financial const…” Read the full reason“We sincerely regret the delay in the completion of the project as well as in the submission of this extension request. The delay has occurred due to unforeseen and unavoidable circumstances, including procurement challenges, financial constraints, and various site-related issues. A major contributing factor to the delay has been the prolonged due diligence and scrutiny process from the Brihanmumbai Municipal Corporation (BMC) and other concerned authorities. Although the CFO Final Plan has been sanctioned, our file is currently under review by the Scrutiny Department of BMC for final approv…”
  5. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vinayak Commerz 54’s extension records on MahaRERA (P51800020069), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vinayak Commerz 54

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800020069
Status
Registered and active
Builder
SHREE VINAYAK REALITY PRIVATE LIMITED
Location
Santacruz West, Mumbai · 400054
Project type
Commercial
Registered on
26 Mar 2019
Completion date at registration
December 2022
Latest completion date
October 2026
Delay so far
42 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
35%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Vinayak Commerz 54, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Commerz 54100%82.5%60%25%

Commencement certificate (CC), as filed on MahaRERA

  • Commerz 54: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vinayak Commerz 54 every 1–2 months.

Vinayak Commerz 54: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space292 – 766109
Other1,497 – 3,5002

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Vinayak Commerz 54 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vinayak Commerz 54: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vinayak Commerz 54

What is the possession date of Vinayak Commerz 54?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vinayak Commerz 54 in Santacruz West, Mumbai is 30 October 2026 — 42 months later than 15 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 42 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vinayak Commerz 54?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vinayak Commerz 54's builder has filed on MahaRERA, the official one, is 30 October 2026, already 42 months later than the 15 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vinayak Commerz 54 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54's builder applied to MahaRERA to extend the completion date 3 times: to 14 December 2023, giving the reason "Due to Covid-19 and shortage labourers for certain period the project could not be completed in time"; to 30 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 54.76% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2026, giving the reason "We sincerely regret the delay in the completion of the project as well as in the submission of this extension request. The delay has occurred due to unforeseen and unavoidable circumstances, including procurement challenges, financial constraints, and various site-related issues. A major contributing factor to the delay has been the prolonged due diligence and scrutiny process from the Brihanmumbai Municipal Corporation (BMC) and other concerned authorities. Although the CFO Final Plan has been sanctioned, our file is currently under review by the Scrutiny Department of BMC for final approv…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Vinayak Commerz 54?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vinayak Commerz 54 in Santacruz West, Mumbai is P51800020069.

Is Vinayak Commerz 54 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 is registered as P51800020069 and its status is "Registered and active".

What is the current construction status of Vinayak Commerz 54? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Commerz 54 is 82.5% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Vinayak Commerz 54 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vinayak Commerz 54 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 is registered on MahaRERA as P51800020069, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vinayak Commerz 54?

Vinayak Commerz 54 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vinayak Commerz 54?

For a flat in Vinayak Commerz 54 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Vinayak Commerz 54 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Vinayak Commerz 54 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vinayak Commerz 54 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vinayak Commerz 54's possession date changes?

The latest dates are on Vinayak Commerz 54's MahaRERA page (P51800020069). GharKundli's Kundli Watch sends a free WhatsApp update on Vinayak Commerz 54 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vinayak Commerz 54 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 has one building filed: Commerz 54 with 20 floors and 111 units.

How big is the land of Vinayak Commerz 54?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 stands on 910 sq m of land (about 0.2 acres).

What are the reviews of Vinayak Commerz 54?

Google Maps has reviews of Vinayak Commerz 54 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vinayak Commerz 54?

Vinayak Commerz 54 by SHREE VINAYAK REALITY PRIVATE LIMITED is in Santacruz West, Mumbai, pincode 400054 (near Santacruz East, Andheri, Vile Parle East), Maharashtra, and is registered on MahaRERA as P51800020069, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 22 23 CTS NO H 448. GharKundli lists all 128 MahaRERA projects in Santacruz West (400054).

How many flats are in Vinayak Commerz 54, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 has 0 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.

When was Vinayak Commerz 54 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Commerz 54 was registered on MahaRERA on 26 March 2019. GharKundli did not find a title report on the land on file there.

Does Vinayak Commerz 54 have any legal issues or court cases?

No court cases are listed for Vinayak Commerz 54 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vinayak Commerz 54?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE VINAYAK REALITY PRIVATE LIMITED.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Santacruz West (400054)

All 128 projects in Santacruz West (400054) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.