Possession date of M.K Heritage: 31 December 2030, moved from 30 December 2022 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800014952, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about M.K Heritage?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of M.K Heritage has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2026

    Extended at the builder's request (MahaRERA application EXT51800017387)

    Reason the builder gave MahaRERA:
    “Due to non availability of manpower and material we were unable to complete the project as per the promised date therefore we would request you to please grant us the extension up to 31-12-2026 and we will try to complete the project before…” Read the full reason“Due to non availability of manpower and material we were unable to complete the project as per the promised date therefore we would request you to please grant us the extension up to 31-12-2026 and we will try to complete the project before the given timeline.”
  3. 31 December 2030

    Extended at the builder's request (MahaRERA application EA04082622017)

    Reason the builder gave MahaRERA:
    “We, Shaista Majid Khan, the promoter of the project M.K Heritage (Registration No. P51800014952) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely regret the delay in the comp…” Read the full reason“We, Shaista Majid Khan, the promoter of the project M.K Heritage (Registration No. P51800014952) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely regret the delay in the completion of the project and the delayed submission of this extension request. The primary reason for the delay is the severe financial constraints faced by the project due to the absence of any unit sales since the commencement of the project. As no residential or commercial units have been sold to date, the project has not generated the expected cash flow…”

Source: M.K Heritage’s extension records on MahaRERA (P51800014952), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on M.K Heritage

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 16 court cases, and how it ended
  • Construction pace against the December 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014952
Status
Registered and active
Builder
SHAISTA MAJID KHAN
Location
Andheri, Mumbai · 400054
Project type
Residential / Group Housing
Registered on
15 Jan 2018
Completion date at registration
December 2022
Latest completion date
December 2030
Delay so far
96 months
Homes
14
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
16
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of M.K Heritage, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
M K Heritage100%45%40%40%

Commencement certificate (CC), as filed on MahaRERA

  • M K Heritage: covers C.C. up to top of 4th floor level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on M.K Heritage every month.

M.K Heritage: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK450 – 48411
2 BHK7023
Shops4731

The builder’s record and reviews

Shaista Majid Khan has 4 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 18 months late). No complaints on MahaRERA.

Read Google reviews of M.K Heritage →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

M.K Heritage: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about M.K Heritage

What is the possession date of M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for M.K Heritage in Andheri, Mumbai is 31 December 2030 — 96 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for M.K Heritage?

Builders and listing sites often quote an earlier "target" date for handover. The completion date M.K Heritage's builder has filed on MahaRERA, the official one, is 31 December 2030, already 96 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of M.K Heritage extended?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2026, giving the reason "Due to non availability of manpower and material we were unable to complete the project as per the promised date therefore we would request you to please grant us the extension up to 31-12-2026 and we will try to complete the project before the given timeline."; to 31 December 2030, giving the reason "We, Shaista Majid Khan, the promoter of the project M.K Heritage (Registration No. P51800014952) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely regret the delay in the completion of the project and the delayed submission of this extension request. The primary reason for the delay is the severe financial constraints faced by the project due to the absence of any unit sales since the commencement of the project. As no residential or commercial units have been sold to date, the project has not generated the expected cash flow…".

What is the RERA number of M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of M.K Heritage in Andheri, Mumbai is P51800014952.

Is M.K Heritage registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage is registered as P51800014952 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: quarterly reports not filed. MahaRERA has put this project in abeyance for not filing its quarterly progress reports (January 2018). Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the construction status of M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage's status on MahaRERA is "Registered and active". As filed by the builder, slab work on M K Heritage is 45% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does M.K Heritage have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is M.K Heritage safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage is registered on MahaRERA as P51800014952, its completion date has moved 96 months since registration, no complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: quarterly reports not filed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if M.K Heritage's possession date changes?

The latest dates are on M.K Heritage's MahaRERA page (P51800014952). GharKundli's Kundli Watch sends a free WhatsApp update on M.K Heritage every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does M.K Heritage have?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage has one building filed: M K Heritage with 16 floors and 15 units.

What are the flat sizes (carpet area) in M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for M.K Heritage: 1 BHK: 450 to 484 sq ft carpet (11 homes); 2 BHK: 702 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage stands on 789 sq m of land (about 0.2 acres), with 853 sq m of sanctioned built-up area.

What is the track record of M.K Heritage's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shaista Majid Khan has 4 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of M.K Heritage?

Google Maps has reviews of M.K Heritage written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is M.K Heritage?

M.K Heritage by SHAISTA MAJID KHAN is in Andheri, Mumbai (pincode 400054), near Santacruz West, Khar west, Santacruz East, Maharashtra, and is registered on MahaRERA as P51800014952, per GharKundli's check of MahaRERA records. Its boundaries filed there include Swami Vivekanand Road.

How many homes are in M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage has 14 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was M.K Heritage registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), M.K Heritage was registered on MahaRERA on 15 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on M.K Heritage?

16 court cases are listed for M.K Heritage on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of M.K Heritage?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAISTA MAJID KHAN, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Andheri

All 128 projects in Santacruz West (400054) →

Other projects by SHAISTA MAJID KHAN

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.