M K Residency
by SHAISTA MAJID KHAN · Budh Colony Kurla West, Mumbai 400070Also near Nehru Nagar, Rajawadi
What’s in the report? →Possession date of M K Residency (MahaRERA P51800023938): 30 April 2029, moved from 30 December 2023 (60 months later). It has 150 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800023938, and currently active. Its completion date has moved from December 2023 to April 2029: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800023938, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about M K Residency?
12 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of M K Residency has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800017545)
Reason the builder gave MahaRERA: “Due to encroachment on road set back area which is to be handed over to BMC has been removed by SRA and the development of road is under process which is going to take few months.”
31 December 2028
Extended at the builder's request (MahaRERA application EXT51800028357)
Reason the builder gave MahaRERA: “we will complete the project by 31st December 2028”
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: M K Residency’s extension records on MahaRERA (P51800023938), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on M K Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 12 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800023938
- Status
- Registered and active
- Builder
- SHAISTA MAJID KHAN
- Location
- Budh Colony Kurla West, Mumbai · 400070
- Project type
- Residential / Group Housing
- Registered on
- 14 Jan 2020
- Completion date at registration
- December 2023
- Latest completion date
- April 2029
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 150
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 12
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of M K Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| M K RESIDENCY - A TO G WING | 100% | 95% | 93% | 92% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on M K Residency every 1–2 months.
M K Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: M K RESIDENCY - A TO G WING (10 floors)
- Land: 2,794 sq m (about 0.7 acres) · sanctioned built-up 6,112 sq m
- Boundaries filed include: Kurla Pipe Road, Anjuman Islam High School, B G Barve Marg
- Land, as filed: CTS No -464 pt , 465
- Map: Get directions
The builder’s record and reviews
Shaista Majid Khan has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of M K Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
M K Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about M K Residency
What is the possession date of M K Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for M K Residency in Budh Colony Kurla West, Mumbai is 30 April 2029 — 60 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 60 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for M K Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date M K Residency's builder has filed on MahaRERA, the official one, is 30 April 2029, already 60 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of M K Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "Due to encroachment on road set back area which is to be handed over to BMC has been removed by SRA and the development of road is under process which is going to take few months."; to 31 December 2028, giving the reason "we will complete the project by 31st December 2028". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of M K Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of M K Residency in Budh Colony Kurla West, Mumbai is P51800023938.
Is M K Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency is registered as P51800023938 and its status is "Registered and active".
What is the current construction status of M K Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on M K RESIDENCY - A TO G WING is 95% done and internal work 93%. GharKundli's full report compares construction progress with the deadline.
Does M K Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is M K Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency is registered on MahaRERA as P51800023938, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in M K Residency?
M K Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in M K Residency?
For a flat in M K Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has M K Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has M K Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for M K Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if M K Residency's possession date changes?
The latest dates are on M K Residency's MahaRERA page (P51800023938). GharKundli's Kundli Watch sends a free WhatsApp update on M K Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does M K Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency has one building filed: M K RESIDENCY - A TO G WING with 10 floors.
How big is the land of M K Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency stands on 2,794 sq m of land (about 0.7 acres), with 6,112 sq m of sanctioned built-up area.
What is the track record of M K Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shaista Majid Khan has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of M K Residency?
Google Maps has reviews of M K Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of M K Residency?
M K Residency by SHAISTA MAJID KHAN is in Budh Colony Kurla West, Mumbai, pincode 400070 (near Nehru Nagar, Rajawadi), Maharashtra, and is registered on MahaRERA as P51800023938, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kurla Pipe Road, Anjuman Islam High School, B G Barve Marg. Its land is filed as CTS No -464 pt , 465. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).
How many flats are in M K Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency has 150 homes in 1 tower registered on MahaRERA.
When was M K Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), M K Residency was registered on MahaRERA on 14 January 2020. GharKundli did not find a title report on the land on file there.
Does M K Residency have any legal issues or court cases?
12 court cases are listed for M K Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of M K Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAISTA MAJID KHAN, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of M K Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Kurla West (400070)
- Jai Shreeram Prasanna CHSL
- Dadamiya’s Man'souza Height
- Kalyan Kutir Co-operative Housing Society Limited
- Taiba Residency
- Anupam Villa CHSL
- Sai Chamunda
- Twin Galaxy
- Deraiya Luxurio
Other projects by SHAISTA MAJID KHAN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.