SAI CHAMUNDA
by Saroj Bharat Desai · Vile Parle East, MumbaiAlso near Kurla West, Kurla East, Nehru Nagar
Possession date of SAI CHAMUNDA: 31 December 2026, moved from 30 December 2020 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008198, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI CHAMUNDA?
How the possession date of SAI CHAMUNDA has moved
30 December 2020
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51800008744)
Reason the builder gave MahaRERA: “DUE TO LEGAL LITIGATION AND COVID 19 PANDEMIC LOCKDOWN THE PROJECT WAS NOT ABLE TO GET COMPLETEDB AND WE ARE NOT ABLE TO PROVIDE THE POSSESSION TO OUR CLIENTS.”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800015327)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023 AND FURTHER DUE TO COURT CASES PENDING”
30 June 2026
Extended at the builder's request (MahaRERA application EXT51800025323)
Reason the builder gave MahaRERA:
“Original Proprietor of Sai Corporation Shri Bharat Pragji Desai Expired on 04.06.2023. hence we are applying in COP as well and Completing all the documents process asap, request you to please consider our request so we can smoothly complet…” Read the full reason
“Original Proprietor of Sai Corporation Shri Bharat Pragji Desai Expired on 04.06.2023. hence we are applying in COP as well and Completing all the documents process asap, request you to please consider our request so we can smoothly complete our project and handover all the sold flats to the allottess”31 December 2026
Extended at the builder's request (MahaRERA application EA09062621286)
Reason the builder gave MahaRERA:
“Dear Sir/Ma’am, I, Saroj Bharat Desai, hereby declare the following with respect to the project “SAI CHAMUNDA” bearing registration number P51800008198 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that…” Read the full reason
“Dear Sir/Ma’am, I, Saroj Bharat Desai, hereby declare the following with respect to the project “SAI CHAMUNDA” bearing registration number P51800008198 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupa…”
Source: SAI CHAMUNDA’s extension records on MahaRERA (P51800008198), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI CHAMUNDA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008198
- Status
- Registered and active
- Builder
- Saroj Bharat Desai
- Location
- Vile Parle East, Mumbai · 400070
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- December 2026
- Delay so far
- 72 months
- Homes
- 34
- Sold or booked
- 15%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAI CHAMUNDA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI CHAMUNDA | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- SAI CHAMUNDA: covers 10 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI CHAMUNDA every month.
SAI CHAMUNDA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 674 – 730 | 26 |
| 1 BHK | 499 | 8 |
- Buildings: SAI CHAMUNDA (10 floors, 34 units)
- Car parking: 18 covered, 19 open
- Land: 2,467 sq m (about 0.6 acres) · sanctioned built-up 1,367 sq m · recreational space 360 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Saroj Bharat Desai has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 64 months late). No complaints on MahaRERA.
Read Google reviews of SAI CHAMUNDA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI CHAMUNDA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI CHAMUNDA
What is the possession date of SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI CHAMUNDA in Vile Parle East, Mumbai is 31 December 2026 — 72 months later than 30 December 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAI CHAMUNDA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI CHAMUNDA's builder has filed on MahaRERA, the official one, is 31 December 2026, already 72 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI CHAMUNDA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2022, giving the reason "DUE TO LEGAL LITIGATION AND COVID 19 PANDEMIC LOCKDOWN THE PROJECT WAS NOT ABLE TO GET COMPLETEDB AND WE ARE NOT ABLE TO PROVIDE THE POSSESSION TO OUR CLIENTS."; to 31 December 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023 AND FURTHER DUE TO COURT CASES PENDING"; to 30 June 2026, giving the reason "Original Proprietor of Sai Corporation Shri Bharat Pragji Desai Expired on 04.06.2023. hence we are applying in COP as well and Completing all the documents process asap, request you to please consider our request so we can smoothly complete our project and handover all the sold flats to the allottess"; to 31 December 2026, giving the reason "Dear Sir/Ma’am, I, Saroj Bharat Desai, hereby declare the following with respect to the project “SAI CHAMUNDA” bearing registration number P51800008198 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupa…".
What is the RERA number of SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI CHAMUNDA in Vile Parle East, Mumbai is P51800008198.
Is SAI CHAMUNDA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA is registered as P51800008198 and its status is "Registered and active".
What is the construction status of SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI CHAMUNDA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SAI CHAMUNDA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAI CHAMUNDA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA is registered on MahaRERA as P51800008198, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI CHAMUNDA's possession date changes?
The latest dates are on SAI CHAMUNDA's MahaRERA page (P51800008198). GharKundli's Kundli Watch sends a free WhatsApp update on SAI CHAMUNDA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI CHAMUNDA have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA has one building filed: SAI CHAMUNDA with 10 floors and 34 units.
What are the flat sizes (carpet area) in SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAI CHAMUNDA: 2 BHK: 674 to 730 sq ft carpet (26 homes); 1 BHK: 499 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SAI CHAMUNDA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered and 19 open car parking spaces for SAI CHAMUNDA.
How big is the land of SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA stands on 2,467 sq m of land (about 0.6 acres), with 1,367 sq m of sanctioned built-up area and 360 sq m of recreational open space.
What is the track record of SAI CHAMUNDA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Saroj Bharat Desai has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 64 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAI CHAMUNDA?
Google Maps has reviews of SAI CHAMUNDA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI CHAMUNDA?
SAI CHAMUNDA by Saroj Bharat Desai is in Vile Parle East, Mumbai (pincode 400070), near Kurla West, Kurla East, Nehru Nagar, Maharashtra, and is registered on MahaRERA as P51800008198, per GharKundli's check of MahaRERA records.
How many homes are in SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA has 34 homes in 1 tower registered on MahaRERA, and 15% of them are sold or booked.
When was SAI CHAMUNDA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHAMUNDA was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI CHAMUNDA?
1 court case is listed for SAI CHAMUNDA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SAI CHAMUNDA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Saroj Bharat Desai, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI CHAMUNDA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Vile Parle East
- Pruthvi Symphony
- PARIMAL
- Sunbeam Emerald
- ZEE HAPPY VEENA
- Parleshwar Aangan
- Nirmaan Heena
- MOTI MADHAV
- Romell Espalier
Other projects by Saroj Bharat Desai
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.