by AADHYA SKYVISTA · Vile Parle East, Mumbai 400057Also near Vile Parle West, Vileparle East, Bandra West

What’s in the report? →

Possession date of Moti Madhav (MahaRERA P51800055563): 30 September 2026, moved from 31 March 2026 (6 months later), and it has already passed. It has 11 homes (1 BHK, 2 BHK and 3 BHK, 316–1222 sq ft carpet), 50% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800055563. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800055563, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about Moti Madhav?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Moti Madhav has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA19032620275)

    Reason the builder gave MahaRERA:
    “1) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. 2) We experienced cautious approach adopted by prospective customer…” Read the full reason“1) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. 2) We experienced cautious approach adopted by prospective customers, many buyers are preferring to invest only after the receipt of the Occupation Certificate (OC) to ensure greater security and certainty. This shift in buyer sentiment has also contributed to slower bookings and delayed fund inflows. 3) The extension is mainly sought to complete the remaining finishing work and to obtain the Occupation Certificate (OC)…”

Source: Moti Madhav’s extension records on MahaRERA (P51800055563), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Moti Madhav

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800055563
Status
Lapsed (registration period ended)
Builder
AADHYA SKYVISTA
Location
Vile Parle East, Mumbai · 400057
Project type
Others
Registered on
2 Apr 2024
Completion date at registration
March 2026
Latest completion date
September 2026
Delay so far
6 months
Homes
11
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Moti Madhav, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MOTI MADHAV100%100%100%1000%

Commencement certificate (CC), as filed on MahaRERA

  • MOTI MADHAV: covers 1 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Moti Madhav every 1–2 months.

Moti Madhav: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK316 – 5196
3 BHK937 – 9513
Shops3341
Office Space2041
4 BHK1,2221
2 BHK7451

The builder’s record and reviews

Hasti Buildcon (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Moti Madhav →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Moti Madhav: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Moti Madhav

What is the possession date of Moti Madhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Moti Madhav in Vile Parle East, Mumbai is 30 September 2026 — 6 months later than 31 March 2026, the date given at registration. That date has already passed.

The date has already moved 6 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Moti Madhav?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Moti Madhav's builder has filed on MahaRERA, the official one, is 30 September 2026, already 6 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Moti Madhav extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "1) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. 2) We experienced cautious approach adopted by prospective customers, many buyers are preferring to invest only after the receipt of the Occupation Certificate (OC) to ensure greater security and certainty. This shift in buyer sentiment has also contributed to slower bookings and delayed fund inflows. 3) The extension is mainly sought to complete the remaining finishing work and to obtain the Occupation Certificate (OC)…".

What is the RERA number of Moti Madhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Moti Madhav in Vile Parle East, Mumbai is P51800055563.

Is Moti Madhav registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav is registered as P51800055563 and its status is "Lapsed (registration period ended)".

What is the current construction status of Moti Madhav? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MOTI MADHAV is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Moti Madhav have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Moti Madhav safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav is registered on MahaRERA as P51800055563, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Moti Madhav?

Moti Madhav isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Moti Madhav are 316 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Moti Madhav?

For a flat in Moti Madhav (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Moti Madhav received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Moti Madhav?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Moti Madhav a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav is a redevelopment: 7 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Moti Madhav uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Moti Madhav was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Moti Madhav's possession date changes?

The latest dates are on Moti Madhav's MahaRERA page (P51800055563). GharKundli's Kundli Watch sends a free WhatsApp update on Moti Madhav every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Moti Madhav have?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav has one building filed: MOTI MADHAV with 1 floors and 13 units.

What are the flat sizes (carpet area) in Moti Madhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Moti Madhav: 1 BHK: 316 to 519 sq ft carpet (6 homes); 3 BHK: 937 to 951 sq ft carpet (3 homes); 4 BHK: 1222 sq ft carpet (1 homes); 2 BHK: 745 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Moti Madhav?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav stands on 460 sq m of land (about 0.1 acres).

What is the track record of Moti Madhav's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Hasti Buildcon (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Moti Madhav?

Google Maps has reviews of Moti Madhav written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Moti Madhav?

Moti Madhav by AADHYA SKYVISTA is in Vile Parle East, Mumbai, pincode 400057 (near Vile Parle West, Vileparle East, Bandra West), Maharashtra, and is registered on MahaRERA as P51800055563, per GharKundli's check of MahaRERA records. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Moti Madhav, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav has 11 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was Moti Madhav registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Moti Madhav was registered on MahaRERA on 2 April 2024. GharKundli did not find a title report on the land on file there.

Does Moti Madhav have any legal issues or court cases?

No court cases are listed for Moti Madhav on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Moti Madhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AADHYA SKYVISTA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.