by ROMELL REAL ESTATE PRIVATE LIMITED · Vile Parle East, Mumbai 400057Also near Vile Parle West, Vileparle East, Bandra West

What’s in the report? →

Possession date of Romell Espalier (MahaRERA P51800079081): 30 April 2031, moved from 31 December 2029 (12 months later). It has 133 homes (1 BHK, 2 BHK and 3 BHK, 471–894 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800079081, and currently active. Its completion date has moved from December 2029 to April 2031: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800079081, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Romell Espalier?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Romell Espalier has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 31 December 2030

    Extended at the builder's request (MahaRERA application EA27112518447)

    Reason the builder gave MahaRERA:
    “Prevailing site conditions and the pace of development, the project is still at the excavation stage. Further our project team have anticipated that project is likely to be finished by December,2030. Also promoter has not yet started sale o…” Read the full reason“Prevailing site conditions and the pace of development, the project is still at the excavation stage. Further our project team have anticipated that project is likely to be finished by December,2030. Also promoter has not yet started sale of flat for said project and not sold single unit till date. It has become evident that the construction cannot be completed within the presently approved timeline.”
  3. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Romell Espalier’s extension records on MahaRERA (P51800079081), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Romell Espalier

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800079081
Status
Registered and active
Builder
ROMELL REAL ESTATE PRIVATE LIMITED
Location
Vile Parle East, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
3 Feb 2025
Completion date at registration
December 2029
Latest completion date
April 2031
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
133
Sold or booked
0%
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of Romell Espalier, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing E0%0%0%0%
Wing D0%0%0%0%
Wing B0%0%0%0%
Wing A0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing E: covers Plinth
  • Wing D: covers Plinth
  • Wing B: covers Plinth
  • Wing A: covers Plinth

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Romell Espalier every 1–2 months.

Romell Espalier: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK607 – 88994
3 BHK882 – 89432
1 BHK471 – 4816
Other7591
  • Buildings: Wing E (17 floors, 24 units) · Wing D (16 floors, 51 units) · Wing B (15 floors, 39 units) · Wing A (15 floors, 19 units)
  • Car parking: 143 covered
  • Land: 3,303 sq m (about 0.8 acres) · sanctioned built-up 11,826 sq m · recreational space 446 sq m
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Romell Real Estate (a group of 5 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 21 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 10 months late). 4 complaints on MahaRERA across 3 projects.

Read Google reviews of Romell Espalier →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Romell Espalier: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Romell Espalier

What is the possession date of Romell Espalier?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Romell Espalier in Vile Parle East, Mumbai is 30 April 2031 — 12 months later than 31 December 2029, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Romell Espalier?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Romell Espalier's builder has filed on MahaRERA, the official one, is 30 April 2031, already 12 months later than the 31 December 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Romell Espalier extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "Prevailing site conditions and the pace of development, the project is still at the excavation stage. Further our project team have anticipated that project is likely to be finished by December,2030. Also promoter has not yet started sale of flat for said project and not sold single unit till date. It has become evident that the construction cannot be completed within the presently approved timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Romell Espalier?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Romell Espalier in Vile Parle East, Mumbai is P51800079081.

Is Romell Espalier registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier is registered as P51800079081 and its status is "Registered and active".

What is the current construction status of Romell Espalier? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Romell Espalier have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Romell Espalier safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier is registered on MahaRERA as P51800079081, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Romell Espalier?

Romell Espalier is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Romell Espalier are 471 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Romell Espalier?

For a flat in Romell Espalier (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Romell Espalier received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Romell Espalier uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Romell Espalier was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Romell Espalier's possession date changes?

The latest dates are on Romell Espalier's MahaRERA page (P51800079081). GharKundli's Kundli Watch sends a free WhatsApp update on Romell Espalier every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Romell Espalier have?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier has 4 buildings filed: Wing E with 17 floors and 24 units; Wing D with 16 floors and 51 units; Wing B with 15 floors and 39 units; Wing A with 15 floors and 19 units.

What are the flat sizes (carpet area) in Romell Espalier?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Romell Espalier: 2 BHK: 607 to 889 sq ft carpet (94 homes); 3 BHK: 882 to 894 sq ft carpet (32 homes); 1 BHK: 471 to 481 sq ft carpet (6 homes); Other: 759 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Romell Espalier have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 143 covered car parking spaces for Romell Espalier.

How big is the land of Romell Espalier?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier stands on 3,303 sq m of land (about 0.8 acres), with 11,826 sq m of sanctioned built-up area and 446 sq m of recreational open space.

What is the track record of Romell Espalier's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Real Estate (a group of 5 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 21 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 10 months late). 4 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Romell Espalier?

Google Maps has reviews of Romell Espalier written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Romell Espalier?

Romell Espalier by ROMELL REAL ESTATE PRIVATE LIMITED is in Vile Parle East, Mumbai, pincode 400057 (near Vile Parle West, Vileparle East, Bandra West), Maharashtra, and is registered on MahaRERA as P51800079081, per GharKundli's check of MahaRERA records. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Romell Espalier, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier has 133 homes in 4 towers registered on MahaRERA, and 0% of them are sold or booked.

When was Romell Espalier registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Romell Espalier was registered on MahaRERA on 3 February 2025. GharKundli did not find a title report on the land on file there.

Does Romell Espalier have any legal issues or court cases?

No court cases are listed for Romell Espalier on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Romell Espalier?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ROMELL REAL ESTATE PRIVATE LIMITED, which has 14 other projects registered on MahaRERA.

All projects with possession due in 2031 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Other projects by ROMELL REAL ESTATE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.