MahaRERA projects in Santacruz West, Mumbai Suburban (400054)

According to GharKundli's check of MahaRERA records, 112 housing projects are registered in pincode 400054 (Santacruz West, Mumbai Suburban). 57 are still being built, 20 with possession due by the end of 2027. For 71, the completion date on MahaRERA is later than the one first promised. 14 have at least one complaint filed on MahaRERA.

Pincode 400054 also covers: Santacruz, Andheri, Bandra, G Ward, Santa Cruz West, West, Santacruz Central.

“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.

ProjectMahaRERA statusPossession due (MahaRERA)First promisedComplaints
COMMERZ 54
SHREE VINAYAK REALITY PRIVATE LIMITED
Active30 Oct 2026passed15 Dec 20220
Artteza
SUNVISION ESTATES
Active30 Nov 202631 May 20244
Rustomjee Paramount - Wing F
KEYSTONE REALTORS LIMITED (Rustomjee)
Active30 Dec 202630 Dec 20250
ORCHID VASUNDHARA
ORCHID BUILTCON PVT. LTD.
Active31 Dec 2026same0
Ruparel Panache
Ruparel Infra & Realty Pvt Ltd
Active31 Dec 202631 Dec 20250
Sheetal Inder Mohini
D.G.S LAND DEVELOPERS (INDIA) PRIVATE LIMITED
Active31 Dec 2026same1
Pearl 2
Pearl Building No -2 Co -Operative Housing Society Limited
Active30 Mar 202731 Jul 20192
CYRILYN
DOUGLAS CYRIL GUDINHO
Active30 Apr 202731 Dec 20260
JAY KRUPA SADAN BY SHREE HARI REALTY
SHREE HARI REALTY
Active30 Apr 202731 Dec 20260
SHIV LAJ
NAVKARMIK INFRA & DEVELOPMENT PRIVATE LIMITED
Active30 Apr 202731 Dec 20260
Transcon Ramdev Plaza
Transcon Iconica Private Limited
Active30 Apr 202730 Dec 202314
DLH DAWN
Dev Land & Housing Pvt Ltd
Active31 May 202731 Jan 20270
REDEVELOPMENT OF SHINING STAR CHSL
PRANAV CONSTRUCTIONS LIMITED
Active10 Jul 202710 Mar 20270
REDEVELOPEMENT OF SAMRAT CHSL
PRANAV CONSTRUCTIONS LIMITED
Active18 Aug 202718 Apr 20270
ALLIANCE SEA BREEZE
ALLIANCE CITY DEVELOPERS REALTORS PVT LTD
Active30 Aug 202730 Apr 20270
OM PALACE
UMIYA BUILDERS
Active31 Aug 202715 Jul 20220
Amara
Aum Serenity
Active20 Sep 202720 May 20270
FAIRFIELD BY S RAHEJA
S RAHEJA SPACES LLP
Active30 Oct 202730 Jun 20270
AUM AURA
M/S AUM SERENITY
Active15 Nov 202715 Jul 20270
MANTRI PRERANA
PENTAGON PREMISES PRIVATE LIMITED
Active31 Dec 2027same0
REDEVELOPMENT OF PEARL PALACE
PRANAV CONSTRUCTIONS LIMITED
Active14 Jan 202814 Sep 20270
GATEWAY RESIDENTIAL
LUCRATIVE TRADING LLP
Active30 Jan 202830 Sep 20270
Omkar Prive
Jasmina Constructions Pvt. Ltd.
Active29 Feb 2028same0
GARDEN CREST
VBHDC BANGALORE VALUE HOMES PRIVATE LIMITED
Active30 Apr 202831 Dec 20270
GOGHARI MANSION
RANGOLI DEVELOPERS
Active30 Apr 202831 Dec 20270
KRISHNA RESIDENCY
RANGOLI DEVELOPERS
Active30 Apr 202831 Dec 20270
MOHINI ENGINEERS AND CONTRACTORS
HARIS GULABRAI CHAWLA
Active30 Apr 202831 Dec 20270
Nanak Niwas
Roodraksh Probuilder And Infracon Pvt Ltd
Active30 Apr 202831 Dec 20270
PSK ALTAIR 77
JAYDEEP DEVELOPERS
Active30 Apr 202831 Dec 20270
SUNBEAM
UMMANG LIFESPACES LLP
Active30 Apr 202831 Dec 20270
THE ADHIRAJ
SAGAR MANOJ GORADIA
Active30 Apr 202831 Dec 20270
Santacruz Aster Co-Op Housing Society Limited
Vira Platinum LLP
Active31 Jul 202831 Mar 20280
Josville
MEGHNA INFRACON INFRASTRUCTURE LIMITED
Active30 Sep 202831 May 20280
SARAS AVENUE
SARAS REALTY BUILDCON LLP
Active30 Oct 202830 Jun 20280
THE PRESIDENCE
KUMAR VIBE PROPERTIES PRIVATE LIMITED
Active30 Jan 202930 Sep 20280
Vascon Orchids
Vascon Engineers Ltd
Active30 Jan 202930 Sep 20280
VAAYU
AUM DEVELOPERS REALTY
Active27 Apr 202927 Dec 20280
54 Park Lane
L NAGPAL BUILDCON LLP
Active30 Apr 202931 Dec 20280
AATMAY
APV DEVELOPERS
Active30 Apr 202931 Dec 20270
Options World
DND Realty Limited Liability Partnership
Active30 Apr 202931 Dec 20280
VILLA FELSTEAD
WEISSHORN REALTY PRIVATE LIMITED
Active30 Apr 202931 Dec 20280
SMRUTI BY RANGOLI DEVELOPERS
RANGOLI DEVELOPERS
Active31 May 202931 Jan 20290
MUKTA
A P PROPERTIES
Active31 Jul 202931 Mar 20290
PRIYADARSHINI CHSL
PRANAV CONSTRUCTIONS LIMITED
Active17 Sep 202917 May 20291
PEARL QUEEN
PEARL QUEEN COOPERATIVE HOUSING SOCIETY LIMITED
Active30 Oct 202930 Jun 20290
ARKADE SAPPHIRE
ARKADE DEVELOPERS LIMITED
Active30 Jan 203030 Sep 20290
PCPL STELLAR CREST
PRANAV CONSTRUCTIONS LIMITED
Active10 Feb 203010 Oct 20290
Aurum Solenne
Aurum (Platz) Goregaon Private Limited
Active30 Apr 203031 Dec 20290
DMK Business Hub
LAXMI LEELA HOMESPACE LLP
Active30 Apr 203031 Dec 20290
PLATINUM STELLAR
PLATINUMCORP ELEGANT RESIDENCES PRIVATE LIMITED
Active30 Apr 203031 Dec 20290

62 more projects

  1. The Monterra · 31 May 2030
  2. Vascon Onyx Residences · 30 Jun 2030
  3. M.K Heritage · 31 Dec 2030
  4. Shri Vikas Co-Operative Housing Society Limited · 31 Dec 2030
  5. Armaan · 30 Apr 2031
  6. Krishna Coniq · 30 Apr 2031
  7. AVIARA · 30 Apr 2032
  8. CARTIER · completed
  9. SORRENTO · completed
  10. UNIQUE ELITA · completed
  11. 64 Greens · completed
  12. GALAXY PINNACLE · completed
  13. KISMET CHSL · completed
  14. Two Roses · completed
  15. SHAPOORJI PALLONJI THE DESIGNATE · completed
  16. NEW LAXMI CHHAYA · completed
  17. ORION WEST · completed
  18. Krishna Curve · completed
  19. MANAS RANGOLI RESIDENCY · completed
  20. Shikhar · completed
  21. Kalpataru Imperia · completed
  22. Acharat Baug · completed
  23. SANTACRUZ ANURAG MANDIR CHSL · completed
  24. 81 Crest Wing A · completed
  25. 81 Crest Wing B · completed
  26. COSMOS · completed
  27. PLATINA · completed
  28. SEQUOIA · completed
  29. K L Victoria · completed
  30. INDRA DHANUSH · completed
  31. MONARCH WEST VIEW · completed
  32. Supreme Elysia · completed
  33. MAYFAIR GNYANADEEP · completed
  34. TRITON · completed
  35. AUM NAV KIRAN · completed
  36. ARKADE AURA · completed
  37. FERNVEL · completed
  38. NUTEX · completed
  39. SEASONS TRIMURTI · completed
  40. WINDERMERE · completed
  41. EKAM · completed
  42. UNIQUE AURA · completed
  43. 19 DEGREE NORTH · completed
  44. EKTA ELITUS · completed
  45. Veena Solace · completed
  46. 96 TAGORE · completed
  47. WOODSTOCK GARDENS · completed
  48. RAHEJA PARK WEST · completed
  49. GATEWAY COMMERCIAL · completed
  50. Besant Arti CHS Ltd · 29 Dec 2020
  51. QUEENS SQUARE · 29 Jun 2023
  52. New Laxmi Bhavan Wing A · 31 Aug 2023
  53. VINAYAK RESIDENCY · 30 Sep 2023
  54. PANORAMA · 31 Dec 2025
  55. PREMSAGAR · 31 Dec 2025
  56. SEASONS PREM SAGAR · 31 Dec 2025
  57. DIVINE · 31 Jul 2026
  58. NAV CHETNA · 30 Aug 2026
  59. VILLA 79 · 30 Aug 2026
  60. Mangal Varsha · 30 Sep 2026
  61. New Saket Co-operative Housing Society Ltd. · 30 Oct 2026
  62. Radius Residency and Anand Bhuvan · —

Other areas in Mumbai Suburban

All areas in Mumbai Suburban →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.

MahaRERA projects in Santacruz West, Mumbai Suburban (400054): possession dates & complaints | GharKundli