Umiya Om Palace
by UMIYA BUILDERS · Santacruz West, Mumbai 400054Also near Santacruz East, Vileparle WestRegistered on MahaRERA as “OM PALACE”
What’s in the report? →Possession date of Umiya Om Palace (MahaRERA P51800010191): 31 August 2027, moved from 15 July 2022 (61 months later). It has 41 homes (1 BHK and 2 BHK, 316–480 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800010191, and currently active.
Source: MahaRERA website — records for P51800010191, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Umiya Om Palace?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Umiya Om Palace has moved
15 July 2022
Completion date given when the project was registered
31 August 2027
Extended at the builder's request (MahaRERA application EXT51800019179)
Reason the builder gave MahaRERA:
“We request you to allow us to extend the project deadline as we sincerely wish to commence the project urgently and the reasons for the delay for the project are as under; a. The then partners of Firm were facing some financial distress and…” Read the full reason
“We request you to allow us to extend the project deadline as we sincerely wish to commence the project urgently and the reasons for the delay for the project are as under; a. The then partners of Firm were facing some financial distress and hence could not proceed with the project as per schedule. b. Onset of Covid-19 also delayed the project. c. We have not commenced any further construction activity as now new partners have come into the project to take it forward. d. The existing 2 shop tenants were not cooperating to hand over rear part of their shop for carrying out construction acti…”
Source: Umiya Om Palace’s extension records on MahaRERA (P51800010191), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Umiya Om Palace
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800010191
- Status
- Registered and active
- Builder
- UMIYA BUILDERS
- Location
- Santacruz West, Mumbai · 400054
- Project type
- Commercial
- Registered on
- 24 Aug 2017
- Completion date at registration
- July 2022
- Latest completion date
- August 2027
- Delay so far
- 61 months
- Homes
- 41
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Umiya Om Palace, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM PALACE | 100% | 20% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- OM PALACE: covers 11 (G + 10)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Umiya Om Palace every 1–2 months.
Umiya Om Palace: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 316 – 443 | 40 |
| Office Space | 333 – 503 | 5 |
| Shops | 99 – 621 | 5 |
| Showroom | 668 – 685 | 2 |
| 2 BHK | 480 | 1 |
- Buildings: OM PALACE (11 floors, 53 units)
- Land: 875 sq m (about 0.2 acres) · sanctioned built-up 2,188 sq m
- Land, as filed: 627
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Umiya Om Palace →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Umiya Om Palace: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Umiya Om Palace
What is the possession date of Umiya Om Palace?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Umiya Om Palace in Santacruz West, Mumbai is 31 August 2027 — 61 months later than 15 July 2022, the date given at registration.
The date has already moved 61 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Umiya Om Palace?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Umiya Om Palace's builder has filed on MahaRERA, the official one, is 31 August 2027, already 61 months later than the 15 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Umiya Om Palace extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace's builder applied to MahaRERA to extend the completion date once: to 31 August 2027, giving the reason "We request you to allow us to extend the project deadline as we sincerely wish to commence the project urgently and the reasons for the delay for the project are as under; a. The then partners of Firm were facing some financial distress and hence could not proceed with the project as per schedule. b. Onset of Covid-19 also delayed the project. c. We have not commenced any further construction activity as now new partners have come into the project to take it forward. d. The existing 2 shop tenants were not cooperating to hand over rear part of their shop for carrying out construction acti…".
What is the RERA number of Umiya Om Palace?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Umiya Om Palace in Santacruz West, Mumbai is P51800010191.
Is Umiya Om Palace registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace is registered as P51800010191 and its status is "Registered and active".
What is the current construction status of Umiya Om Palace? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace's status on MahaRERA is "Registered and active". As filed by the builder, slab work on OM PALACE is 20% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Umiya Om Palace have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Umiya Om Palace safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace is registered on MahaRERA as P51800010191, its completion date has moved 61 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Umiya Om Palace?
Umiya Om Palace is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Umiya Om Palace are 316 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Umiya Om Palace?
For a flat in Umiya Om Palace (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Umiya Om Palace received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace is still under construction, with 31 August 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Umiya Om Palace a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace is a redevelopment: 13 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Umiya Om Palace uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Umiya Om Palace was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Umiya Om Palace's possession date changes?
The latest dates are on Umiya Om Palace's MahaRERA page (P51800010191). GharKundli's Kundli Watch sends a free WhatsApp update on Umiya Om Palace every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Umiya Om Palace have?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace has one building filed: OM PALACE with 11 floors and 53 units.
What are the flat sizes (carpet area) in Umiya Om Palace?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Umiya Om Palace: 1 BHK: 316 to 443 sq ft carpet (40 homes); 2 BHK: 480 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Umiya Om Palace?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace stands on 875 sq m of land (about 0.2 acres), with 2,188 sq m of sanctioned built-up area.
What are the reviews of Umiya Om Palace?
Google Maps has reviews of Umiya Om Palace written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Umiya Om Palace?
Umiya Om Palace by UMIYA BUILDERS is in Santacruz West, Mumbai, pincode 400054 (near Santacruz East, Vileparle West), Maharashtra, and is registered on MahaRERA as P51800010191, per GharKundli's check of MahaRERA records. Its land is filed as 627. GharKundli lists all 128 MahaRERA projects in Santacruz West (400054).
How many flats are in Umiya Om Palace, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace has 41 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Umiya Om Palace registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Umiya Om Palace was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Does Umiya Om Palace have any legal issues or court cases?
No court cases are listed for Umiya Om Palace on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Umiya Om Palace?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UMIYA BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of Umiya Om Palace
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Santacruz West (400054)
- Mantri Prerana
- 96 Tagore
- Krishna Residency
- M.K Heritage
- Arkade Sapphire
- Shri Vikas Co-Operative Housing Society Limited
- Rustomjee Paramount - Wing F
- Mangal Varsha
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.