by SUNVISION ESTATES · Santacruz West, MumbaiAlso near Andheri, Khar West, Santacruz East

Possession date of Artteza: 30 November 2026, moved from 31 May 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800030554, and currently active. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Artteza?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Artteza has moved

  1. 31 May 2024

    Completion date given when the project was registered

  2. 31 May 2025

    Extended at the builder's request (MahaRERA application EXT51800019441)

    Reason the builder gave MahaRERA:
    “Project was registered on 30.08.2021 with MahaRERA and time for completion as mentioned under RERA is 31.05.2024. The said Project is redevelopment of co-operative housing society. The Project consists of Wing A, B, C and D each consisting…” Read the full reason“Project was registered on 30.08.2021 with MahaRERA and time for completion as mentioned under RERA is 31.05.2024. The said Project is redevelopment of co-operative housing society. The Project consists of Wing A, B, C and D each consisting of two level of basement plus ground floor plus 9 upper floors. The Promoter has completed construction of all the slabs of superstructure of Wing A and B and the finishing work is ongoing in respect of Wing A and B. The Promoter intends to apply and obtain occupancy permissions of Wing A and B on or before 31.05.2024 and shall forthwith handover possessi…”
  3. 31 May 2026

    Extended at the builder's request (MahaRERA application EXT51800028059)

    Reason the builder gave MahaRERA:
    “The present Project was originally being redeveloped by the erstwhile Developer. The present Developer acquired the development rights of project through consent terms dated 25.06.2021 r/w Addendum dated 18.03.2021. The Entire Project was u…” Read the full reason“The present Project was originally being redeveloped by the erstwhile Developer. The present Developer acquired the development rights of project through consent terms dated 25.06.2021 r/w Addendum dated 18.03.2021. The Entire Project was under severe financial crunch and had to be revived by the Promoter. In doing so, the Promoter had to avail financial facility from Lender which took considerable time in arranging necessary funds for successfully commencing the construction work of the project. Apart from financial challenges, certain litigations were also initiated in the Hon’ble Bombay…”
  4. 30 November 2026

    Extended at the builder's request (MahaRERA application EA30032620461)

    Reason the builder gave MahaRERA:
    “We, SUNVISION ESTATES, the promoter of the project ARTTEZA (Registration No. P51800030554) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. The delay in completion of the project is attri…” Read the full reason“We, SUNVISION ESTATES, the promoter of the project ARTTEZA (Registration No. P51800030554) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. The delay in completion of the project is attributable to a combination of financial, legal, and force majeure circumstances. The project was under severe financial stress, requiring restructuring and revival, which resulted in considerable time being spent in arranging financial assistance from lenders and mobilizing resources before recommencement of construction activities. The delay in completion…”

Source: Artteza’s extension records on MahaRERA (P51800030554), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Artteza

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800030554
Status
Registered and active
Builder
SUNVISION ESTATES
Location
Santacruz West, Mumbai · 400054
Project type
Residential / Group Housing
Registered on
30 Aug 2021
Completion date at registration
May 2024
Latest completion date
November 2026
Delay so far
30 months
Homes
80
Sold or booked
84%
Towers
4
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found

Construction progress of Artteza, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%100%100%
Wing B100%100%100%100%
Wing C100%100%80%0%
Wing D100%90%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A: covers 12 (2 Basements + Ground + 9 Upper Floors)
  • Wing B: covers 12 (2 Basements + Ground + 9 Upper Floors)
  • Wing C: covers 12 (2 Basements + Ground + 9 Upper Floors)
  • Wing D: covers 12 (2 Basements + Ground + 9 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Artteza every month.

Artteza: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK674 – 73580
  • Buildings: Wing A (12 floors, 20 units) · Wing B (13 floors, 20 units) · Wing C (13 floors, 20 units) · Wing D (12 floors, 20 units)
  • Land: 2,928 sq m (about 0.7 acres) · sanctioned built-up 6,476 sq m · recreational space 586 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Artteza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Artteza: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Artteza

What is the possession date of Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Artteza in Santacruz West, Mumbai is 30 November 2026 — 30 months later than 31 May 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Artteza?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Artteza's builder has filed on MahaRERA, the official one, is 30 November 2026, already 30 months later than the 31 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Artteza extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza's builder applied to MahaRERA to extend the completion date 3 times: to 31 May 2025, giving the reason "Project was registered on 30.08.2021 with MahaRERA and time for completion as mentioned under RERA is 31.05.2024. The said Project is redevelopment of co-operative housing society. The Project consists of Wing A, B, C and D each consisting of two level of basement plus ground floor plus 9 upper floors. The Promoter has completed construction of all the slabs of superstructure of Wing A and B and the finishing work is ongoing in respect of Wing A and B. The Promoter intends to apply and obtain occupancy permissions of Wing A and B on or before 31.05.2024 and shall forthwith handover possessi…"; to 31 May 2026, giving the reason "The present Project was originally being redeveloped by the erstwhile Developer. The present Developer acquired the development rights of project through consent terms dated 25.06.2021 r/w Addendum dated 18.03.2021. The Entire Project was under severe financial crunch and had to be revived by the Promoter. In doing so, the Promoter had to avail financial facility from Lender which took considerable time in arranging necessary funds for successfully commencing the construction work of the project. Apart from financial challenges, certain litigations were also initiated in the Hon’ble Bombay…"; to 30 November 2026, giving the reason "We, SUNVISION ESTATES, the promoter of the project ARTTEZA (Registration No. P51800030554) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. The delay in completion of the project is attributable to a combination of financial, legal, and force majeure circumstances. The project was under severe financial stress, requiring restructuring and revival, which resulted in considerable time being spent in arranging financial assistance from lenders and mobilizing resources before recommencement of construction activities. The delay in completion…".

What is the RERA number of Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Artteza in Santacruz West, Mumbai is P51800030554.

Is Artteza registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza is registered as P51800030554 and its status is "Registered and active".

What is the construction status of Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 90% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Artteza have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Artteza safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza is registered on MahaRERA as P51800030554, its completion date has moved 30 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Artteza's possession date changes?

The latest dates are on Artteza's MahaRERA page (P51800030554). GharKundli's Kundli Watch sends a free WhatsApp update on Artteza every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Artteza have?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza has 4 buildings filed: Wing A with 12 floors and 20 units; Wing B with 13 floors and 20 units; Wing C with 13 floors and 20 units; Wing D with 12 floors and 20 units.

What are the flat sizes (carpet area) in Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Artteza: 2 BHK: 674 to 735 sq ft carpet (80 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza stands on 2,928 sq m of land (about 0.7 acres), with 6,476 sq m of sanctioned built-up area and 586 sq m of recreational open space.

Where can I read reviews of Artteza?

Google Maps has reviews of Artteza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Artteza?

Artteza by SUNVISION ESTATES is in Santacruz West, Mumbai (pincode 400054), near Andheri, Khar West, Santacruz East, Maharashtra, and is registered on MahaRERA as P51800030554, per GharKundli's check of MahaRERA records.

How many homes are in Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza has 80 homes in 4 towers registered on MahaRERA, and 84% of them are sold or booked.

When was Artteza registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Artteza was registered on MahaRERA on 30 August 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Artteza?

No court cases are listed for Artteza on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Artteza?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUNVISION ESTATES.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400054

All 128 projects in Santacruz West (400054) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.