Possession date of Ruparel Panache (MahaRERA P51800046597): 31 December 2026, moved from 31 December 2025 (12 months later). It has 136 homes (1 BHK, 2 BHK and 3 BHK, 331–1780 sq ft carpet), 43% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800046597, and currently active.

Source: MahaRERA website — records for P51800046597, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ruparel Panache?

Possession date khiski: ab Dec 2026. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ruparel Panache has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA21112518400)

    Reason the builder gave MahaRERA:
    ““Ruparel Panache” (MahaRERA Registration No. P51800046597) is a single residential redevelopment project comprising three wings (A, B and C) with Ground + 18 floors and two parking towers. The project is being developed by M/s. Ruparel Infr…” Read the full reason““Ruparel Panache” (MahaRERA Registration No. P51800046597) is a single residential redevelopment project comprising three wings (A, B and C) with Ground + 18 floors and two parking towers. The project is being developed by M/s. Ruparel Infra and Realty Pvt. Ltd. under the Slum Redevelopment Scheme (SRA) in accordance with Regulation 33(10) of DCPR 2034. The latest MahaRERA registration is valid up to 31 December 2025. The project has faced delays due to circumstances beyond the control of the promoter. A major impediment arose from delayed evacuation of occupants from the existing dilapidat…”

Source: Ruparel Panache’s extension records on MahaRERA (P51800046597), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ruparel Panache

Ready · November 2026 · 54 filings read

Risk & trust score locked/100
  • Risk & trust score, every point explained
  • What the title report on MahaRERA says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800046597
Status
Registered and active
Builder
Ruparel Infra & Realty Pvt Ltd
Location
Santacruz West, Mumbai · 400054
Project type
Residential / Group Housing
Registered on
25 Aug 2022
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
136
Sold or booked
43%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Yes
Latest construction certificate
31 Mar 2026
Builder's other MahaRERA projects
1

Construction progress of Ruparel Panache, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
wing C100%100%100%95%
Wing B100%100%100%95%
Wing A100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • wing C: covers up-to 17th upper floor
  • Wing B: covers C.C. is re-endorsed Wing 'A', 'B' & 'C' and further extended upto 17th upper floor for Wing 'B' of Composite Bldg. as per last approved amended plans dtd. 20/09
  • Wing A: covers Up-to 17th Upper Floor

Latest CC order on MahaRERA: dated 29/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ruparel Panache every 1–2 months.

Ruparel Panache: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK776 – 1,78071
2 BHK446 – 90446
1 BHK331 – 46214
Multi Purpose Room136 – 28712
4 BHK1,4725
  • Buildings: wing C (17 floors, 36 units) · Wing B (14 floors, 46 units) · Wing A (17 floors, 66 units)
  • Car parking: 224 covered
  • Land: 3,186 sq m (about 0.8 acres) · sanctioned built-up 10,513 sq m · recreational space 617 sq m
  • Boundaries filed include: STATION ROAD
  • Land, as filed: H/280, H/281, H/282, H/283, H/284, H/285, H/293 ,H/549 OF VILLAGE BANDRA H
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Ruparel Infra & Realty (a group of 13 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 15 still being built, 9 past the promised date (typically 30 months late); 10 lapsed. 867 complaints on MahaRERA across 21 projects.

Read Google reviews of Ruparel Panache →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ruparel Panache: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ruparel Panache

What is the possession date of Ruparel Panache?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ruparel Panache in Santacruz West, Mumbai is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ruparel Panache?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ruparel Panache's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ruparel Panache extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "“Ruparel Panache” (MahaRERA Registration No. P51800046597) is a single residential redevelopment project comprising three wings (A, B and C) with Ground + 18 floors and two parking towers. The project is being developed by M/s. Ruparel Infra and Realty Pvt. Ltd. under the Slum Redevelopment Scheme (SRA) in accordance with Regulation 33(10) of DCPR 2034. The latest MahaRERA registration is valid up to 31 December 2025. The project has faced delays due to circumstances beyond the control of the promoter. A major impediment arose from delayed evacuation of occupants from the existing dilapidat…".

What is the RERA number of Ruparel Panache?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ruparel Panache in Santacruz West, Mumbai is P51800046597.

Is Ruparel Panache registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache is registered as P51800046597 and its status is "Registered and active".

What is the current construction status of Ruparel Panache? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. The latest construction certificate the builder filed there is dated 31 March 2026. GharKundli's full report compares construction progress with the deadline.

Does Ruparel Panache have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ruparel Panache safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache is registered on MahaRERA as P51800046597, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ruparel Panache?

Ruparel Panache is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ruparel Panache are 331 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ruparel Panache?

For a flat in Ruparel Panache (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ruparel Panache received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Ruparel Panache uploaded its title report on MahaRERA?

Yes. According to GharKundli's check of MahaRERA records (updated November 2026), an advocate's title report for Ruparel Panache is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.

A loan or claim on the land can hold up your flat or your home loan. See what the title report says →

How can I get updates if Ruparel Panache's possession date changes?

The latest dates are on Ruparel Panache's MahaRERA page (P51800046597). GharKundli's Kundli Watch sends a free WhatsApp update on Ruparel Panache every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ruparel Panache have?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache has 3 buildings filed: wing C with 17 floors and 36 units; Wing B with 14 floors and 46 units; Wing A with 17 floors and 66 units.

What are the flat sizes (carpet area) in Ruparel Panache?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed these homes for Ruparel Panache: 3 BHK: 776 to 1780 sq ft carpet (71 homes); 2 BHK: 446 to 904 sq ft carpet (46 homes); 1 BHK: 331 to 462 sq ft carpet (14 homes); 4 BHK: 1472 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Ruparel Panache have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 224 covered car parking spaces for Ruparel Panache.

How big is the land of Ruparel Panache?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache stands on 3,186 sq m of land (about 0.8 acres), with 10,513 sq m of sanctioned built-up area and 617 sq m of recreational open space.

What is the track record of Ruparel Panache's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Infra & Realty (a group of 13 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 15 still being built, 9 past the promised date (typically 30 months late); 10 lapsed. 867 complaints on MahaRERA across 21 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ruparel Panache?

Google Maps has reviews of Ruparel Panache written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ruparel Panache?

Ruparel Panache by Ruparel Infra & Realty Pvt Ltd (Classic) is in Santacruz West, Mumbai, pincode 400054 (near Santacruz East, Andheri, Khar West), Maharashtra, and is registered on MahaRERA as P51800046597, per GharKundli's check of MahaRERA records. Its boundaries filed there include STATION ROAD. Its land is filed as H/280, H/281, H/282, H/283, H/284, H/285, H/293 ,H/549 OF VILLAGE BANDRA H. GharKundli lists all 128 MahaRERA projects in Santacruz West (400054).

How many flats are in Ruparel Panache, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache has 136 homes in 3 towers registered on MahaRERA, and 43% of them are sold or booked.

When was Ruparel Panache registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Panache was registered on MahaRERA on 25 August 2022. A title report on the land is on file there.

Does Ruparel Panache have any legal issues or court cases?

No court cases are listed for Ruparel Panache on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Ruparel Panache?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ruparel Infra & Realty Pvt Ltd, the company Classic files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Santacruz West (400054)

All 128 projects in Santacruz West (400054) →

Other projects by Ruparel Infra & Realty Pvt Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.