by Pearl Building No -2 Co -Operative Housing Society Limited · Andheri, MumbaiAlso near Santacruz West, Khar west, Bandra East

Possession date of Pearl 2: 30 March 2027, moved from 31 July 2019 (92 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009076, and currently active. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Pearl 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Pearl 2 has moved

  1. 31 July 2019

    Completion date given when the project was registered

  2. 31 July 2020

    Extended at the builder's request (MahaRERA application EXT51800006090)

    Reason the builder gave MahaRERA: “COULD NOT COMPLETE THE PROJECT IN TIME DUE TO FINANCIAL CRUNCH.”
  3. 31 July 2022

    Extended at the builder's request (MahaRERA application EXT51800006142)

    Reason the builder gave MahaRERA: “The Project has been handed over to the Society and now the society will complete the project.. also attached is the Board Resolution of the Society and the consent of society members”
  4. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51800017028)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 71.43% allottees for purpose of extension of RERA registration period of the said project.”
  5. 30 November 2025

    Extended at the builder's request (MahaRERA application EXT51800026039)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and Insufficient funds. By implementing the outlined action plan, we aim to m…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and Insufficient funds. By implementing the outlined action plan, we aim to mitigate these delays and move forward efficiently. However, we assure you that our utmost priority is to safeguard the interests of the allottees and ensure the successful completion of the project. We kindly request an extension under section 7(3) until 30-11-2025, allowing us sufficient time to complete all necessary procedures and meet our commitments…”
  6. 30 March 2027

    Extended at the builder's request (MahaRERA application EA02062621206)

    Reason the builder gave MahaRERA:
    “We, Pearl Building No -2 Co -Operative Housing Society Limited, the promoter of the project Pearl 2 (Registration No. P51800009076) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apo…” Read the full reason“We, Pearl Building No -2 Co -Operative Housing Society Limited, the promoter of the project Pearl 2 (Registration No. P51800009076) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project. The project is delayed due to some minor pending works such as sanitary fittings, electrical fittings, lift work, compound wall work, and other finishing activities. We are actively working on the same and require additional time to complete the balance work. We are also awaiting the Occupation Certif…”

Source: Pearl 2’s extension records on MahaRERA (P51800009076), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Pearl 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009076
Status
Registered and active
Builder
Pearl Building No -2 Co -Operative Housing Society Limited
Location
Andheri, Mumbai · 400054
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
July 2019
Latest completion date
March 2027
Delay so far
92 months
Homes
15
Sold or booked
93%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of Pearl 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Commencement certificate (CC), as filed on MahaRERA

  • Pearl 2: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pearl 2 every month.

Pearl 2: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK627 – 85012
3 BHK1,055 – 1,1212
1 BHK4681

The builder’s record and reviews

Jaycee Homes has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 87 months late); 3 lapsed. 13 complaints on MahaRERA across 4 projects.

Read Google reviews of Pearl 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Pearl 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Pearl 2

What is the possession date of Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pearl 2 in Andheri, Mumbai is 30 March 2027 — 92 months later than 31 July 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Pearl 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Pearl 2's builder has filed on MahaRERA, the official one, is 30 March 2027, already 92 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Pearl 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2's builder applied to MahaRERA to extend the completion date 5 times: to 31 July 2020, giving the reason "COULD NOT COMPLETE THE PROJECT IN TIME DUE TO FINANCIAL CRUNCH."; to 31 July 2022, giving the reason "The Project has been handed over to the Society and now the society will complete the project.. also attached is the Board Resolution of the Society and the consent of society members"; to 31 March 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 71.43% allottees for purpose of extension of RERA registration period of the said project."; to 30 November 2025, giving the reason "The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and Insufficient funds. By implementing the outlined action plan, we aim to mitigate these delays and move forward efficiently. However, we assure you that our utmost priority is to safeguard the interests of the allottees and ensure the successful completion of the project. We kindly request an extension under section 7(3) until 30-11-2025, allowing us sufficient time to complete all necessary procedures and meet our commitments…"; to 30 March 2027, giving the reason "We, Pearl Building No -2 Co -Operative Housing Society Limited, the promoter of the project Pearl 2 (Registration No. P51800009076) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project. The project is delayed due to some minor pending works such as sanitary fittings, electrical fittings, lift work, compound wall work, and other finishing activities. We are actively working on the same and require additional time to complete the balance work. We are also awaiting the Occupation Certif…".

What is the RERA number of Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pearl 2 in Andheri, Mumbai is P51800009076.

Is Pearl 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2 is registered as P51800009076 and its status is "Registered and active".

What is the construction status of Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does Pearl 2 have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Pearl 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2 is registered on MahaRERA as P51800009076, its completion date has moved 92 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Pearl 2's possession date changes?

The latest dates are on Pearl 2's MahaRERA page (P51800009076). GharKundli's Kundli Watch sends a free WhatsApp update on Pearl 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Pearl 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2 has one building filed: Pearl 2 with 9 floors and 15 units.

What are the flat sizes (carpet area) in Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Pearl 2: 2 BHK: 627 to 850 sq ft carpet (12 homes); 3 BHK: 1055 to 1121 sq ft carpet (2 homes); 1 BHK: 468 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2 stands on 380 sq m of land (about 0.1 acres), with 1,039 sq m of sanctioned built-up area.

What is the track record of Pearl 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Jaycee Homes has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 87 months late); 3 lapsed. 13 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Pearl 2?

Google Maps has reviews of Pearl 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Pearl 2?

Pearl 2 by Pearl Building No -2 Co -Operative Housing Society Limited is in Andheri, Mumbai (pincode 400054), near Santacruz West, Khar west, Bandra East, Maharashtra, and is registered on MahaRERA as P51800009076, per GharKundli's check of MahaRERA records.

How many homes are in Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2 has 15 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.

When was Pearl 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pearl 2 was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Pearl 2?

No court cases are listed for Pearl 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pearl Building No -2 Co -Operative Housing Society Limited.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Andheri

All 128 projects in Santacruz West (400054) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.