Royal Fantasy Phase II

by Royal Fantasy Constructions Private Limited · Andheri, MumbaiAlso near Jogeshwari East, Mogra, Goregaon East

Possession date of Royal Fantasy Phase II: 31 December 2026, moved from 30 June 2019 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004649, and currently active. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Royal Fantasy Phase II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Royal Fantasy Phase II has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 29 June 2020

    Extended at the builder's request (MahaRERA application EXT51800001942)

    Reason the builder gave MahaRERA:
    “Our under construction real estate project is getting delayed due to several reasons as follows: 1. MCGM notified only the Draft DP sheets 2034 on 8th September 2017. Since the DP sheets had many errors, the DP/DCR 2034 was held up again. D…” Read the full reason“Our under construction real estate project is getting delayed due to several reasons as follows: 1. MCGM notified only the Draft DP sheets 2034 on 8th September 2017. Since the DP sheets had many errors, the DP/DCR 2034 was held up again. DCR-2034 was finally notified recently sometime back and MCGM has increased the FSI for building development for various categories of real estate projects. Our project is also a beneficiary of increased FSI, as already envisaged by us and proposed accordingly at the time of MahaRERA registration. Delay in finalization of DP/DCR 2034 has resulted in huge d…”
  3. 29 December 2021

    Extended at the builder's request (MahaRERA application EXT51800008935)

    Reason the builder gave MahaRERA:
    “1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition f…” Read the full reason“1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contractor’s inability to perform their contractual obligations within the timescales detailed in the C…”
  4. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012172)

    Reason the builder gave MahaRERA:
    “1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability…” Read the full reason“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending.”
  5. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018643)

    Reason the builder gave MahaRERA:
    “1. There was a temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labor, disruptions due to implementation of GST and continuous updation and non availability of sand on tim…” Read the full reason“1. There was a temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labor, disruptions due to implementation of GST and continuous updation and non availability of sand on time 3. Default from customers 4. Outstanding receivables from customers 5. Registration of some of the flats are still pending”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800027178)

    Reason the builder gave MahaRERA:
    “1. Work in Progress in Phase 2 is slow compared to our schedule because we have to take utmost care of possession given to flat buyers in Phase 1 close to the Phase 2 building during construction activity. 2. The Flat buyers are not paying…” Read the full reason“1. Work in Progress in Phase 2 is slow compared to our schedule because we have to take utmost care of possession given to flat buyers in Phase 1 close to the Phase 2 building during construction activity. 2. The Flat buyers are not paying payments as per the schedule and we have to arrange funds from other sources every time which takes time.”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EA04022619699)

    Reason the builder gave MahaRERA:
    “Phase 1 of the project has been completed, with the Occupation Certificate received and possession handed over, while Phase 3 is close to completion. Phase 2 has taken longer as it is next to the occupied Phase 1, requiring extra care and s…” Read the full reason“Phase 1 of the project has been completed, with the Occupation Certificate received and possession handed over, while Phase 3 is close to completion. Phase 2 has taken longer as it is next to the occupied Phase 1, requiring extra care and safety measures during construction. The delay was also due to irregular payments by some allottees, which created financial pressure and required the developer to arrange alternative funding to continue the work.”

Source: Royal Fantasy Phase II’s extension records on MahaRERA (P51800004649), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Royal Fantasy Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800004649
Status
Registered and active
Builder
Royal Fantasy Constructions Private Limited
Location
Andheri, Mumbai · 400093
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2019
Latest completion date
December 2026
Delay so far
90 months
Homes
68
Sold or booked
99%
Towers
2
Complaints on MahaRERA
5
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Royal Fantasy Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Dreamax Height Wing B up to 11th Floor100%100%100%55%
Dreamax Vega Wing C Full100%100%100%75%

Commencement certificate (CC), as filed on MahaRERA

  • Dreamax Height Wing B up to 11th Floor: covers 11 floors
  • Dreamax Vega Wing C Full: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Royal Fantasy Phase II every month.

Royal Fantasy Phase II: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK624 – 68426
1 BHK414 – 47322
Other28910
Shops107 – 1885
3 BHK8945
  • Buildings: Dreamax Height Wing B up to 11th Floor (13 floors, 41 units) · Dreamax Vega Wing C Full (16 floors, 27 units)
  • Car parking: 59 covered
  • Land: 6,117 sq m (about 1.5 acres) · sanctioned built-up 3,436 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Royal Fantasy Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 39 months); 2 still being built, 2 past the promised date (typically 85 months late). 8 complaints on MahaRERA across 2 projects.

Read Google reviews of Royal Fantasy Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Royal Fantasy Phase II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Royal Fantasy Phase II

What is the possession date of Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Royal Fantasy Phase II in Andheri, Mumbai is 31 December 2026 — 90 months later than 30 June 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Royal Fantasy Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Royal Fantasy Phase II's builder has filed on MahaRERA, the official one, is 31 December 2026, already 90 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Royal Fantasy Phase II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II's builder applied to MahaRERA to extend the completion date 6 times: to 29 June 2020, giving the reason "Our under construction real estate project is getting delayed due to several reasons as follows: 1. MCGM notified only the Draft DP sheets 2034 on 8th September 2017. Since the DP sheets had many errors, the DP/DCR 2034 was held up again. DCR-2034 was finally notified recently sometime back and MCGM has increased the FSI for building development for various categories of real estate projects. Our project is also a beneficiary of increased FSI, as already envisaged by us and proposed accordingly at the time of MahaRERA registration. Delay in finalization of DP/DCR 2034 has resulted in huge d…"; to 29 December 2021, giving the reason "1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contractor’s inability to perform their contractual obligations within the timescales detailed in the C…"; to 31 December 2023, giving the reason "1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending."; to 31 December 2024, giving the reason "1. There was a temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labor, disruptions due to implementation of GST and continuous updation and non availability of sand on time 3. Default from customers 4. Outstanding receivables from customers 5. Registration of some of the flats are still pending"; to 31 December 2025, giving the reason "1. Work in Progress in Phase 2 is slow compared to our schedule because we have to take utmost care of possession given to flat buyers in Phase 1 close to the Phase 2 building during construction activity. 2. The Flat buyers are not paying payments as per the schedule and we have to arrange funds from other sources every time which takes time."; to 31 December 2026, giving the reason "Phase 1 of the project has been completed, with the Occupation Certificate received and possession handed over, while Phase 3 is close to completion. Phase 2 has taken longer as it is next to the occupied Phase 1, requiring extra care and safety measures during construction. The delay was also due to irregular payments by some allottees, which created financial pressure and required the developer to arrange alternative funding to continue the work.".

What is the RERA number of Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Royal Fantasy Phase II in Andheri, Mumbai is P51800004649.

Is Royal Fantasy Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II is registered as P51800004649 and its status is "Registered and active".

What is the construction status of Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Royal Fantasy Phase II have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Royal Fantasy Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II is registered on MahaRERA as P51800004649, its completion date has moved 90 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Royal Fantasy Phase II have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Royal Fantasy Phase I (P51800009606, possession 30 Jun 2022); Royal Fantasy Phase III (P51800009920, possession 30 Jun 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Royal Fantasy Phase II's possession date changes?

The latest dates are on Royal Fantasy Phase II's MahaRERA page (P51800004649). GharKundli's Kundli Watch sends a free WhatsApp update on Royal Fantasy Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Royal Fantasy Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II has 2 buildings filed: Dreamax Height Wing B up to 11th Floor with 13 floors and 41 units; Dreamax Vega Wing C Full with 16 floors and 27 units.

What are the flat sizes (carpet area) in Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Royal Fantasy Phase II: 2 BHK: 624 to 684 sq ft carpet (26 homes); 1 BHK: 414 to 473 sq ft carpet (22 homes); Other: 289 sq ft carpet (10 homes); Shops: 107 to 188 sq ft carpet (5 homes); 3 BHK: 894 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Royal Fantasy Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 59 covered car parking spaces for Royal Fantasy Phase II.

How big is the land of Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II stands on 6,117 sq m of land (about 1.5 acres), with 3,436 sq m of sanctioned built-up area.

What is the track record of Royal Fantasy Phase II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 39 months); 2 still being built, 2 past the promised date (typically 85 months late). 8 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Royal Fantasy Phase II?

Google Maps has reviews of Royal Fantasy Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Royal Fantasy Phase II?

Royal Fantasy Phase II by Royal Fantasy Constructions Private Limited is in Andheri, Mumbai (pincode 400093), near Jogeshwari East, Mogra, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800004649, per GharKundli's check of MahaRERA records.

How many homes are in Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II has 68 homes in 2 towers registered on MahaRERA, and 99% of them are sold or booked.

When was Royal Fantasy Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase II was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Royal Fantasy Phase II?

No court cases are listed for Royal Fantasy Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Royal Fantasy Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Royal Fantasy Constructions Private Limited, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Andheri

All 74 projects in Andheri East (400093) →

Other projects by Royal Fantasy Constructions Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.